Inspection Flash Report

Flash Report No. : JI2043-PPF021-FL-4-005 Date Of Inspection :29-07-2020

CLIENT: SONATRACH CONTRACTOR: PETROFAC


VENDOR: Kinetic Energy Factory Company LOCATION: Jubail

SUB VENDOR:N/A LOCATION: N/A

PETROFAC PURCHASE ORDER NO.:JI2043-PPF021


ITP No. & Sl No : W20015-ITP-001& 12,13.
RFI NO & Date: 02 REV 03 26-07-2020
1.0 TYPE OF VISIT:

Pre-Inspection Meeting  Visual and Dimensional Inspection of clamps


 Painting Inspection for clamps
Intermediate Inspection

Final Inspection

2.0 MATERIAL INSPECTED DURING THIS VISIT:


ITEM / TAG No. DESCRIPTION QUANTITY

98,101,102 &104 CLAMP FOR SHOES & DCBVD 09.

3.0 RESULT OF INSPECTION:

Accepted Rejected ORDER STATUS Complete


Incomplete
4.0 AREA OF CONCERN:
5.0 SUMMARY:
1. Final Visual and dimensional inspection of the Structural items was performed at the
vendor facility as per the approved drawings. The items included Clamp of shoe,All
the dimensions were verified which included length, width, height thickness etc.
The results of Dimensional inspections were found to be ok as per the drawings, the
results were found to be acceptable.
2. Final coating inspection of the finished structural items was also performed, DFT
was checked for the top coat randomly by using a calibrated DFT meter
6.0 PHOTOS:

08572-TRHT-AQ-QC-00-OO-206 FRM 03
Inspection Flash Report

Note:
1.This report must be completed by hand/typed while at the Vendor and E-mailed from the vendor to Inspection
Coordinator and Functional Quality Engineer of Petrofac.
2.Any NCR observed during Inspection shall be notified to PECO Quality Engineer within 24 hours of Inspection for issuance
and concurrence.
Inspector detail :
Fahad Ahmad
Name
Signature
29/07/2020
Date