VIETNAM NATIONAL OIL AND GAS GROUP

PETROVIETNAM EXPLORATION PRODUCTION CORPORATION LTD.


26th Floor, Charm Vit Tower Tel: (84-4) 3772 6001
117 Tran Duy Hung Street, Cau Giay District Fax: (84-4) 3772 6027
Ha Noi, S.R.Vietnam Email:pvep.hn@pvep.com.vn

FACSIMILE TRANSMISSION

To: VSP Fax No.: +84 64 3 839 857


Attn: Nguyen Thanh Truong
Deputy General Director

Ref.: / PVEP-KHOAN Date: 27th April, 2015


No. of page(s) (Including this cover sheet): 12

Subject: Provision of Drilling Rig and Related Services under Turnkey Contract for
PVEP’s Drilling Campaign in Block 42, Offshore Southern Vietnam

If you have not received the full text of this fax, please contact our telephone number: (84-4) 3772 6001

Dear Sirs,

PetroVietnam Exploration Production Corporation (PVEP) is the operator of the


exploration project on Block 42, Offshore Southern Vietnam, is planning to drill one (01)
firm well with the depth of at approximately 3385m (+/- 200m) which is expected to
commence in August, 2015. The estimated time for operation is around 2.5 months
including well test. The Well information summary is briefly described in the Attachment
1 – Well Information Brief herewith

In case you are interested in supplying of Drilling Rig and Related services under
Turnkey Contract for PVEP, please fill in the following forms as detailed in Attachment
2 – Survey Questionnaire, Attachment 3 – Pre-qualification Requirement, Attachment 4 –
Questionnaire for Drilling Services and Attachment 5 – Questionnaire on Safety and
providing us not later than 14h00 on 7th May, 2015 (Vietnam time) via facsimile or email
with the attention to the following:

Mr. Dinh Trong Huy (HuyDT@pvep.com.vn) - GM of Drilling Division


Mr. Pham Dinh Nguyen (NguyenPD@pvep.com.vn) –GM of Commercial Division
Mr. Pham Trung Nghia (Nghiapt@pvep.com.vn ) – Senior Drilling Engineer

Should you need any further information and/or clarification, please feel free to contact
with us.

Please acknowledge receipt of this letter by affixing your signature in the


acknowledgement box below and sending us via e-mail a scanned copy of this cover page

Thank you very much for your cooperation and look forward to your response in due time.
Yours faithfully, ACKNOWLEDGEMENT
We acknowledged receipt of your letter.
Signature: ………………………………………
Name: ……………………………………….
Title: ………………………………………
Dinh Trong Huy Date: ………………………………………
General Manager of Drilling Division Company Seal ………………………………………
ATTACHMENT 1- WELL INFORMATION BRIEF
1.1. Well location:
1.2. Preliminary Well Lithology
1.3 Preliminary Well Design
1.3.1 Well schematic
1.3.2 General well program
ATTACHMENT 2 – SURVEY QUESTIONNAIRE

No. Inquiry Response


1.0 Are you interested to participate in YES
the tender? (Yes/No)
2.0 Company Details
2.1 Company Name JOINT VENTURE "VIETSOVPETRO"
2.2 Country of Registration VIET NAM
2.3 Complete Address 105 Le Loi Street (Road), 06 Ward, Vungtau
City, S.R. Vietnam
2.4 Website http://www.vietsov.com.vn
2.5 Tel. No. +84.64.3839 871
2.6 Fax No. +84.64.3839857
2.7 Organization Chart (to submit) Please see as attached
3.0 Parent Company (if any) Details
3.1 Country of Registration
3.2 Complete Address
3.3 Company Group structure showing
affiliates and subsidiaries (to submit)
4.0 Branch Office in Vietnam (if Any)

4.1 Complete Address


4.2 Contact Person
4.3 Tel. No.
4.4 Fax No.
5.0 Contact Person for this tender
5.1 Name VU MAI KHANH
5.2 Position / Designation Deputy Director General for Investment and
Development and Services ( VietsovPetro)
5.3 Tel. No. (+84).64-383 9871, Ext: 2428.
Mob: (+84)-903848185
5.4 Fax No. +84.64.3839857
5.5 E-mail address khanhvm.pt@vietsov.com.vn
6.0 Experiences in Last 5 years (2009
-2014)
Please use the format below Please use the format in the table below for your
response. Alternatively, you may submit the
summary of your experiences in outline form
provided it will be complete with the required
information.

No. Project Name Contract Value Client Time Location


(USD)
1
2
ATTACHMENT 3- PRE-QUALIFICATION REQUIREMENT
( FOR MURMANSKAYA/ JACK UP RIG)

No Items Requirement Your Proposal


Drilling depth
1 5000m with 5 1/2" DP or 5 7/8" DP  5” DP/ G-105
capacity
2 Drawworks rating Minimum 3000HP  3000HP
TDS 10 or equivalent (min 30,000 ft-lbs
3 Top Drive System Max 94,000 ft-lbs
torque)
03 x 1600HP
Triplex Mud pum.
4 Mud pump Minimum 3 x 1600 HP triplex mudpump
Max Pressure:
5000PSI
Equipped with the following BOP equipment: • One (01) BOP
a) 01 x 21 1/4" 2k or 20 3/4" 3K annular Stack: 13 5/8" x
preventer and 01 x 21 1/4" 2k or 20 3/4" 3K 10,000 PSI
5 BOP system
duoble ram preventer. • One (01) BOP
b) 01 x 13 5/8" 5k Annular preventer and 01 x Stack: 20 3/4" x
13 5/8" 10k double and single ram preventers. 3000 PSI
6 Choke manifold Safe working pressure: 10,000psi 10,000 PSI
Standpipe working
7 5000psi 5,000psi
pressure
total active tank capacity of 1500bbls and
8 Mud tank capacity 2289bbls
reserve of 1000bbls
Accommodation and Minimum for 120 personnel (COMPANY &
9 84 person
catering facilities third party)
Solid control 04/ National Oilwell
10 Minimum 3 unit linear motion shakers
equipment / DLMS-380P
Expect time to
 73 days  75
carry out
+ Mobilization  2.5 days  2.5
+ Start up drilling  2.5 days  2.5
11 + Drilling  40 days  41
+ Testing 24 days 24
+ P&A 3 days 3
+ Demobilization  1 day  2

ATTACHMENT 4- QUESTIONNAIRE FOR DRILLING SERVICES


Notes: Please answer all the questions by placing a tick in the appropriate boxes, and a brief
description of the disposable materials/services. The general direction on the type of materials or
services is provided.
All supporting documents may be sent to the address provided above.

Brief
Is it possible description of
Complianc
Drilling materials to provide for materials and Contractor
No. e with API
and services project in services Comments
standards
drilling? (examples
shown)
Rated
horsepower,
max drilling
depth, nominal
Yes _X_ Yes _X_
4.1 Drilling Rig pressure of
No ___ No __
drilling riser,
the presence of
the top drive,
etc.
The set of types Yes _X_
Yes _X_
4.2 Drill bit and sizes of drill No ___ PTO
No ___
bits
The drilling fluid and Yes _X_ Types and kinds Yes _X_
4.3 Phòng DD
service No ___ of drilling fluids No ___
Yes _X_ Halliburton
Type of
Yes _X_ No ___ /HT-400.
4.4 Cementation cementing unit,
No ___ Halliburton
aggregate, etc.
services
Variety of
Yes _X_ additives Yes _X_
4.5 Cement and additives Anh Hà
No ___ (chemicals) of No ___
cement
Yes _X_ Set sizes, Yes _X_
Oilfield pipe goods,
No ___ brands, No ___
4.6 products (casing and PTO
couplings and
tubing)
thread
Yes _X_ Set sizes of the Yes _X_
Additional casing No ___ floats, No ___ Phòng Cơ
4.7
equipment stabilizers, khí
thrust washers
Yes _X_ Several sizes of Yes _X_
No ___ outboard No ___
4.8 Liner hangers Anh Hà
devices shanks
(liner hangers)
4.9 Coring and Set sizes of core Viện NIPI
laboratory services Yes _X_ barrel, core Yes _X_
No ___ conservation No ___
techniques and
methods of
research
The range of
Services for the Yes _X_ services for the Yes _X_
XNĐVL
4.10 detection of No ___ detection No ___
xác nhận
hydrogen sulfide of hydrogen
sulfide
Allowable
Wellhead equipment,
Yes _X_ pressure and the Yes _X_ Phòng cơ
4.11 installation and
No ___ size of the No ___ khí
maintenance
wellhead
Methods of
Monitoring and
Yes _X_ control for Yes _X_
4.12 controlling drilling
No ___ drilling waste No ___
waste
Monitoring Types of
equipment and Yes _X_ equipment for Yes _X_
4.13
processing solid No ___ processing solid No ___
waste waste
Yes _X_ A set of Yes _X_
XNĐVL
4.14 Perforation No ___ methods for No ___
xác nhận
punching
A set of XNĐVL
Yes _X_ methods for Yes _X_ xác nhận
No ___ testing wells, No ___
4.15 Test wells
providing the
drilling rig for
testing wells
Range of XNĐVL
Yes _X_ services for Yes _X_ xác nhận
4.16 Electric logging
No ___ electrical No ___
logging
Yes _X_ A number of Yes _X_ XNĐVL
4.17 Mud logging No ___ services for mud No ___ xác nhận
logging
The range of
services to
directional
Directional drilling,
Yes _X_ drilling, Yes _X_ Phòng
borehole
4.18 No ___ borehole No ___ khoan xiên
investigations in the
investigations in xác nhận
drilling process
the drilling
process, logging
while drilling
Yes _X_ A set of sizes of Yes _X_
Fishing downhole
4.19 No ___ fishing No ___ Ban Sự Cố
tool
downhole tools
Yes _X_ Types, sizes, the Yes _X_
Rental services of No ___ characteristics No ___ Phòng Dịch
4.20
drilling tools of the drilling Vụ
tool
Yes _X_ Range of Yes _X_
Inspection of the
No ___ services for No ___ XNĐVL
borehole and
4.21 gyroscopic/ xác nhận
gyroscope
other borehole
surveys
Yes _X_ The Range of Yes _X_
Wear control tube,
No ___ services to No ___
thread and repair Xưởng Cần
4.22 monitor wear of
ống
pipes

Yes _X_ Set sizes of Yes _X_


casing cutter,
Materials and
No ___ the size of No ___
services of
4.23 congestion
Elimination/conserva
bridges and
tion well
conservation
methods
Types of
Responding to oil Yes _X_ equipment to Yes _X_
4.24
spills No ___ respond to oil No ___
spills
Types of
software to
provide for
reporting under
Daily reports on
Yes _X_ the standards of Yes ___
4.25 drilling and software
No ___ IADC No _X_
monitoring
(International
Association of
Drilling
Contractors)
The personnel of Yes _X_ Experience and Yes _X_
4.26
drilling (Office) No ___ national staff No ___
Experience in
Providing catering Yes _X_ providing food Yes _X_
4.27
services No ___ and drinking No ___
water
Providing base,
Providing Base, Yes _X_ warehouse
4.28 warehouse, handling No ___ facilities and
equipment & services handling
services
Yes _X_ Range of
Providing
services for Yes _X_
Transportation VSP, Vận
4.29 transportation of No ___
(Vessel, Helicopter, Tải Biển
cargo and
Trucks)
Personnel
Yes _X_ Types of Yes _X_
Satellite
4.30 satellite No ___ TTCNTT
communication
communications
Yes _X_ Experience in Yes _X_
4.31 Providing fuel XNDV
No ___ providing fuel No ___
ATTACHMENT 5 - QUESTIONNAIRE ON SAFETY

5.1. Security policy of the company.


Does your company have a Politician policy on health protection, the safety precautions and
environment? (HSE)? Yes____ No____
If Yes, please put a copy of these documents for our consideration. Please see attachment.

5.2. The organization on safety precautions.


Does your company have a structured reporting system for safety with distribution of duties and
responsibilities? Yes____ No____

5.3. Competent staff on safety precautions.


Does your company hires the experts in safety precautions on a basis of full employment?
Yes____ No____

5.4. Instructions and procedures on safety precautions.


Does your company establish working practices, instructions or procedures on safety precautions?
Yes____ No____
How often are they being reconsidered? _____01__every year_______________________

5.5. Techniques on an estimation of efficiency on safety precautions.


Does your company estimates efficiency on safety precautions? Yes____ No____
We keep a record of all incidents. Below is a chronology of the safety of our company for the last
three years:
Description 2014 2013 2012
Number of cases with a loss of temporary disability* 0 3 1
Number of cases with transfers to another job* 0 0 0
Number of cases with medical intervention* 0 3 1
Number of cases with first aid* 0 1 0
Number of dangerous occurrences 0 1 1
Total man-hours worked 2.294.632 2.335.552 2.135.720
Total lost days 0 89 28

5.6. Accident investigation and reporting.


Does your company have established procedures for accident investigation and reporting?
Yes____ No____

5.7. Accidents with fatalities.


Have there been any accidents with fatalities during the work of your company for the last 3
years? Yes____ No____
If Yes, please specify:_________________________________________________

5.8. Awareness of safety.


How do you see the involvement of management in motivating and educating staff to improve
knowledge on safety?
Management should participate in meetings, discussions on safety of the staff and conduct regular
tests to check on safety at places of work, etc. Yes____ No____
Employees need to see how the leadership is taking the necessary steps and providing resources?
Yes ____ No____
Other, please specify:
______________________________________________________________________________