Professional Documents
Culture Documents
3UHVHUYDWLRQ
Page 2 of 19
1.1 GENERAL
If a boiler is taken out of operation for either a short or a long period, adequate precautions must
be taken in order to prevent corrosion during shutdown.
It shall be highlighted that the climatic conditions play an important role in determining the rate of
corrosion for unprotected equipment. In particular the rate of corrosion may increase in areas
where the atmosphere has high humidity and contains corrosive contaminants.
In general the selection of preservation type shall be also based on:
¾ presence of operating plant which could affect environmental conditions;
¾ coastal areas with presence of salty environment;
¾ sand and dust.
For reference here below is shown a curve which indicates the correlation between the relative
humidity and the corrosion rate of metal surface.
For steam generator both water side and fire side must be protected against possible corrosion
damage during idle period.
In the case that idle period is less than five days for water side and fifteen days for fireside, no
preservation procedures are deemed necessary.
This “grace” period could be longer in case of favourable environmental conditions (to be verified
case by case).
The water-side preservation can be carried out either with the wet or the dry method.
The dry method preservation is based on nitrogen filling under light pressure.
Macchi recommends also the dry method when the air temperature could be below +5°C and
wet preservation is not applicable.
Page 3 of 19
The wet preservation is based on the neutralization of the dissolved oxygen existing in the boiler
water by adding suitable chemicals, and pressurization with nitrogen.
The preservation period has been divided in:
¾ SHORT-TERM preservation up to 3 months
¾ LONG-TERM preservation more than 3 months
The following diagram indicates the preservation procedure to be applied for pressure parts and
for fire side care.
Each time the boiler is put out of service, the flue gas side must be
preserved according to the procedure #1 or #2 as applicable (refer to
preservation chart). Indeed if the boiler is not properly preserved the
ambient temperature variation between day and night facilitates the
condensation of the air humidity and this water is absorbed by the
refractory castings. Consequently the excess of water in the castings
can lead to corrosion on the tubes embedded in the refractory.
Page 4 of 19
Preservation activities may require the access of a confined space, the use
of hazardous chemicals and/or toxic/asphyxiating gas, electric equipment,
etc…dedicated PTW procedures to be respected
During preservation period, if inspections to steam drum internals are
required, be sure to vent completely the nitrogen and assure proper
ventilation before entering the drum.
When nitrogen is vented to atmosphere, do not draw near the vent zones for
not breathing this gas.
Page 5 of 19
Page 6 of 19
Page 7 of 19
The boiler (economizer, evaporating tubes and the superheater) has to be filled with deaerated
water containing suitable chemicals to neutralize the dissolved oxygen contained in water.
The short term boiler preservation ( 3 months) of the water side may be carried out as follows.
For the wet preservation of the water side of a boiler it is recommended to follow this procedure:
1) Let cool the boiler.
2) Open the following valves:
Saturated steam line vents (tag No. 113, 114).
Main steam line drains (tag No. 121, 125).
3) Close the following valves:
Main steam stop valve and its by-pass (tag No. XV-500, 010).
Continuous blowdown line isolation valve (tag No. 172).
All sampling lines isolation valves (tag No. 130, 131, 173).
Start-up vent valves (tag No. 007, HV-500).
All steam traps isolation valves.
4) Connect the nitrogen temporary filling line to the connection provided on the saturated
steam line vent.
5) Fill the boiler with deaerated water and inject an oxygen scavenger (volatile type) to
maintain a residual concentration in the range 200 ppm to 400 ppm. Add sufficient
alkalinizer agent (typically ammonia or morpholine) to adjust the water pH between 10 and
11. The superheater is filled with deaerated water too.
6) Stop the boiler filling when the water overflows from saturated steam line vent and from
main steam line drain. Close all vents and the drain valves previously opened.
Page 8 of 19
7) Pressurize with nitrogen at 0.3 bar(g). It is important to pressurize the boiler to avoid air
entry.
8) Once a day check the nitrogen pressure
9) After one week the boiler water has to be tested to verify the concentration of oxygen
scavenger and the pH.
10) If the pH decreases below 9.5 and/or the concentration of oxygen scavenger < 200 ppm,
add required amount of chemicals by partially draining the boiler (opening one drain each
time during refilling) and then fill it up again with fresh conditioned water.
Page 9 of 19
Page 10 of 19
NOTE: The boiler, SH and economizer drain valves shall be operated in order to remove
the humidity that condenses when nitrogen is introduced inside the pressure parts. This will
improve the oxygen removal from pressure parts.
7) Check that the relative humidity is lower than 40%. If not, it will be necessary to repeat
air/nitrogen pressurization cycles. Pressurization with nitrogen and quick opening of start-up
vent valve will improve water removal.
8) Provide to flush the boiler with nitrogen (typically five boiler volumes).
For flushing the status of the following valves will be:
¾ Nitrogen filling line valve: Opened
¾ Saturated line vent valve: tag No. 113 Opened
¾ Drain of SH steam line tag No. 119 Opened
¾ Main steam line isolation valve tag No. 011 Closed
¾ Main steam stop valve tag. No. MOV-500 Opened
¾ Saturated line vent valve: tag No. 114 Closed
The amount of the residual oxygen in the gas vented from boiler and SH line must be
checked. When its concentration is lower than 2% in every venting point, it is possible to fill
the boiler with protective gas. The boiler total volume is 44 m³.
NOTE: the term “venting point” is referred not only to the vents themselves but also to all
drains from which the nitrogen can be discharged.
9) Seal the boiler after gas filling; keep constantly the protective gas under low pressure of
0.3-0.4 bar(g).
10) Apply warning labels in proximity of boiler manholes to prevent anybody to enter while in
preservation.
Although nitrogen is not toxic, it is an asphyxiating gas that can cause
a rapid death.
11) Periodically check the nitrogen pressure.
Page 11 of 19
Page 12 of 19
¾ Machined and untreated carbon steel surfaces to be coated with rust preservative or a rust
protective wax.
¾ All uncoated studbolts / nuts shall be coated with grease or other suitable rust preservative.
¾ Lubricate door hinges (if provided), grease nipples and fastener.
¾ In case desiccant are used (i.e. Silica gel), desiccant material shall not be in direct contact
with metallic surfaces and shall be placed onto wood trays inside the items.
¾ During preservation period temperature and relative humidity shall be recorded regularly.
¾ Stainless steel equipment must be dried and thoroughly cleaned on both the inside and
outside and must be coated with a thick plastic based water-resistant coating.
Page 13 of 19
These suggestions shall be applied to rotating machinery such as forced draft fan and driver(s).
For these types of equipment, the exclusion of moisture is essential to avoid pitting and oxidation
of critical components such as gear teeth, bearing journals, shaft seals, blading, etc.
Moreover these equipment must be properly sealed to prevent ingress of sand or sand dust
since this could cause seizure/damage.
The Preservation of the rotating equipment is made directly at site; in same cases where it is not
possible to proceed with an acceptable extent of protection it could be decided to remove and
store some components (i.e. electrical motor, rotors, ...) in a controlled atmosphere.
As a general rule, for medium and long period before starting any preservation activities
¾ Stop all rotating equipment and ensure the facility is not operating.
¾ De-energize and lock out all breakers.
¾ Isolate equipment from line.
¾ Remove and preserve coupling or spacer between the driven machine and driver to facilitate
rotating of rotor.
¾ Properly tag and store spacer and/or coupling parts.
¾ Provide electric motors with a warning that they “Energized” or “De-energized”.
¾ Provide equipment with warning when space heaters have been installed.
¾ All exposed shafts and polished surfaces shall be thoroughly cleaned and protected with a
rust preservative (e.g.: Tectyl 506-EH or equivalent).
¾ Manual rotation of shafts at weekly intervals is recommended. Rotation through a minimum
of 3½ complete turns. The position of the shaft at rest should be advanced by a ¼ turn each
time.
¾ Cover and seal with plastic sheets the suction side to prevent entrance on contaminants.
Page 14 of 19
Page 15 of 19
1.3.6.1 General
¾ De-energize equipment.
¾ Clean equipment internally with air-hose.
¾ Energize space heaters (if provided).
¾ Energize equipment that is to remain in service during the preservation period.
¾ Put inside equipment exposed to humidity porous bags of VCI or VCI emitters, or desiccant
(silica gel).
¾ Spray VCI on wiring and electronics.
¾ Close door and openings and seal it.
¾ Check tightness of cable glands.
¾ Electrical equipment to be wrapped in glass fiber aluminium cloth and sealed with tape.
1.3.7 Burners
For both short and long preservation the burners will remain installed on the boiler.
¾ Short term preservation
¾ Protect pilot burner and flame scanners by applying a corrosion inhibitor on wirings and
wrapping the equipment with glass fibre aluminium coat and seal with tape. Seal tightly
the openings. Seal the burner sight glasses tightly (if applicable).
Page 16 of 19
¾ Drain the eventual fluid still present in the primary connections and close the interception
valves.
¾ Check the tightness of the cable glands.
¾ For long period storage apply/fasten a 6 mm plywood board to all glasses in
instrument/panel fronts and cover with aluminium glass fiber cloth and tape. For panel
fronts, a wooden frame for corner protection shall be installed in addition to the front panel.
¾ Aluminium sheeted glass fiber cloth wrapped with tape, shall be used to envelope pressure
gauges, local electronic transmitters, panels, junction boxes, temperature instruments.
¾ Protect instruments internal parts by means of VCI (Vapor Corrosion Inhibitor).
¾ All wired instrument equipment containing electronic components shall be protected with
vapor corrosion inhibitor VCI according to Manufacturer’s instructions.
¾ All openings in hydraulic/pneumatic tubing shall be provided with steel caps/plugs of
material compatible with the metallurgy of the component being capped or plugged (if any).
Non-metallic plugs shall not be used.
Page 17 of 19
Page 18 of 19
Page 19 of 19