When it comes to boilers, the work — in this case, the work is heat transfer — is done
by the boiler tubes. The design type of the boiler (firetube, watertube, etc.) changes the
orientation and layout of the boiler but the boiler tubes are still transferring the heat
from the fire side to the water side. It is for this reason that boiler tube maintenance
and repair are essential to proper boiler operation.
Boiler tubes undergo a tremendous amount of stress due to the large temperature
gradients, so the tube design, material, and thickness have all been carefully selected
for optimum and efficient operation. The importance of the proper operation,
maintenance, and repair cannot be understated as the boiler tubes may be the most
crucial component for most boilers. Repairs to boilers built to ASME Boiler & Pressure
Vessel Code (BPVC) must be repaired by a National Board certified repair company to
ensure compliance with all the required rules and regulations.
One of the first questions that come about when looking into boilers is the different
types. Two of the main types of boilers are firetube and watertube. The main difference
is pointed out in the name but is clarified in the definitions, advantages, and
disadvantages below.
Firetube Boiler
A pressure vessel boiler, in which the exhaust gases pass through one or more tubes to
transfer heat into the surrounding water of the sealed containment.
• Simple design
• Ease of maintenance and repair
• Lower initial cost
• Higher water volume per boiler horsepower
Watertube Boiler
A pressure vessel, boiler, in which the exhaust gases travel between small diameter
tubes to transfer heat into the water circulating through the tubes between two larger
drums. Watertube boilers are more efficient than firetube boilers.
The top reasons we see for boiler tube failures in firetube boilers are:
The top reasons we see for boiler tube failures in watertube boilers are:
Over the years, there have been many boilers that have been “repaired” for extended
periods of time by a temporary solution meant to provide enough time to adequately
prepare for a boiler shutdown. Many boiler room personnel and boiler repair companies
have installed boiler tube plugs in firetube and watertube boilers not realizing the
impact on boiler performance and operation.
At Powerhouse, we strongly advise all of our clients to only consider a boiler tube being
plugged in an emergency situation when a proper shutdown and repair is not possible
but is planned in the near future. In both firetube and watertube boilers, the majority of
the heating surface area is accounted for in the boiler tubes. When any boiler tubes are
plugged, there is a loss of surface area which reduces efficiency, lowers the output
capacity, and creates an additional failure mechanism:
Firetube Plugs
Boiler tube plugs are installed in a ruptured tube which now is filled with high pressure
boiler water. These plugs, when not properly installed by a certified repair company,
can become dislodged and shoot at a high velocity from the tubesheet doing further
damage to your boiler.
Watertube Plugs
Boiler tube plugs in a watertube boiler result in water no longer flowing through the
tube, which is what keeps the tube from overheating as the heat from the
combustion/flue gas needs to pass through the metal into the water. Depending on the
location of the tube, plugging a watertube boiler tube requires slicing the entire length
of the tube and installing refractory to protect the exposed metal from overheating and
further damage being done to your boiler.
1 Assess the failure, perform any preliminary testing, and develop an approved repair
plan with an Authorized Inspector that will be acceptable to the code and local
jurisdiction.
2 Remove the failed tube and determine the probable failure mechanism to assist in
operational changes that could prevent future failures.
3 Assess the condition of the tube end connection locations (tube sheets, steam drum,
mud drum, etc) and perform any additional NDE required.
4 Installation of the new boiler tube in accordance with the code requirements (rolled,
beaded, welded, etc.).
5 Perform a pressure test in accordance with the code requirements and any additional
NDE to verify the integrity of the repair.
6 Complete the repair forms and submit them to the National Board and jurisdiction, as
required and install the repair plate on the boiler.
FAQs
How long do boiler tubes last?
Contact us
1-800-377-8326 (Emergency Phone) (tel:+18003778326)
ph-quotes@powerhouse.com (mailto:ph-quotes@powerhouse.com)
Contact us (/en/contact-us)
Request a Quote (/en/contact-us)
Subscribe to our Journal
Legal
Terms & Conditions (/en/terms-and-conditions)
Privacy Policy (/en/privacy-policy)
Sitemap (/en/sys/sitemap)
Facebook (https://www.facebook.com/PowerhouseBoilers/)
LinkedIn (https://www.linkedin.com/company/powerhouse-boiler-equipment/)
Twitter (https://twitter.com/80037steam)
Youtube (https://www.youtube.com/channel/UCD21wAN1DB9K2svulBLS4jg)
© 2023 Powerhouse Equipment & Engineering Co. Inc., all rights reserved.