Professional Documents
Culture Documents
Guideline
PUBLIC
PROJECT IDENTIFICATION
Project Name CPI Project Number
<Project Name>
Customer Name Customer Number
<Customer Name>
SAP Project Manager Customer Project Manager
<SAP Project Manager> <Customer Project Manager>
DOCUMENT IDENTIFICATION
Author Document Location (repository/path/name)
<Author> <Document location>
Version Status Date (YYYY-MM-DD) Document Classification
2 Final <Date> Public
REVISION HISTORY
Version Date Description
1 February 4, 2010 Initial
2 November 24, 2015 Various updates
3 January 30, 2018 Updated template
2
TABLE OF CONTENTS
APPROACH.......................................................................................................................................................... 4
Creating the Program/Project Schedule............................................................................................................ 4
Step 1 – Create the Program/Project Summary................................................................................................ 4
Step 2 – Create the Phase Summaries.............................................................................................................. 4
Step 3 – Add Deliverables and Sub-deliverables.............................................................................................. 4
Step 4 – Add Tasks.............................................................................................................................................. 4
Step 5 – Define the Task Types.......................................................................................................................... 5
Step 6 – Define Task Durations.......................................................................................................................... 5
Step 7 – Linking Tasks........................................................................................................................................ 5
Step 8 – Defining Milestones.............................................................................................................................. 5
Step 9 – Assigning Resources to Tasks............................................................................................................ 5
Step 10 – Creating the Schedule Baseline........................................................................................................ 6
Managing the Program/Project Schedule.......................................................................................................... 6
Updating Tasks.................................................................................................................................................... 6
Closing Tasks...................................................................................................................................................... 6
Reporting Schedule Results............................................................................................................................... 6
Using the Gantt Chart to Show Progress.......................................................................................................... 6
Maintaining Schedule Currency and Updates................................................................................................... 6
Creating Effective Reports.................................................................................................................................. 6
Headers, Footers, and Labels for Schedule Reports.......................................................................................7
Schedule Report Legends.................................................................................................................................. 7
Advanced Options............................................................................................................................................... 7
Project/Program Interfaces................................................................................................................................. 7
Internal Dependencies........................................................................................................................................... 7
External Dependencies......................................................................................................................................... 7
Schedule Symbols for Interfaces........................................................................................................................... 7
Interface Management........................................................................................................................................... 7
REFERENCES AND RELATED GUIDELINE....................................................................................................... 8
3
Project Schedule Guidelines provide assistance in helping to prepare the Project Schedule. They are intended to
supplement the project planning and scheduling approach described in the SAP Project Management
Methodology (PM Methodology and PM Handbook) and the related SAP Field Services PM Methodology
Knowledge Area Guidelines (Scope, Time, and Cost) and SAP references.
APPROACH
The Project Schedule is typically created by the Project Manager, Program Manager, or designate – working
closely with members of the planning team -- and is used to plan and manage tasks over the entire lifecycle of
the project. The use of these guidelines help build consistency in scheduling techniques across the enterprise,
ensuring that the Project Manager benefits from scheduling best practices and the Project Management Office
can provide effective oversight of assigned projects and provide consistent project status information to
members of the project organization. The following key steps are suggested for developing and maintaining a
project schedule, as well as some additional advanced techniques for dealing with internal and external
dependencies.
4
Step 5 – Define the Task Types
Project Scheduling tools (e.g. Microsoft Project) allow for two types of tasks, Effort Driven Tasks and Fixed
Duration Tasks. Effort Driven Tasks change as the amount of labor is applied while Duration Driven Tasks
remain unchanged regardless of the number of labor hours (people) applied.
Example:
Effort Driven Task - Software Testing is identified to require 10 days (80 hours). One person can
complete the task in 10 days while two people can complete it in five days (In reality, two people may
take more than five days, due to tasking complexities).
Fixed Duration Task - Code Review (a one day meeting) with four people will still take one day if only
two or four people attend.
For each task entered, select the desired task type.
5
Step 10 – Creating the Schedule Baseline
When approved, save the project schedule baseline. Approval to Baseline the schedule is the responsibility of
the Program/Project Manager. The baseline schedule will be used to compare actual progress as the project is
executed.
Updating Tasks
Tasks should be updated to reflect the completion of work. Tasks can be updated in three different ways as
follows:
Enter the actual start date and the expected actual duration.
Enter the actual start date and the percentage completed so far.
Enter the actual start date, the actual duration so far, and the remaining duration needed to complete the
task.
Tip: Detailed tracking of tasks use the Update Tasks Dialog Box. For quicker, broader tracking, when
detailed tracking is not necessary, use the Update Project Dialog Box.
Closing Tasks
Once work is completed on a task, close it. Once closed (i.e., 100 percent complete), the task should not be
opened again for additional work. If additional work is required, a new task should be opened to complete any
additional work.
6
Headers, Footers, and Labels for Schedule Reports
Labelling schedule reports is important for identification and tracking the dates the reports are produced. In the
Header (under page setup), place the Program/Project Name in the center. In the Footer, place on the left side
the file name, system date, and system time (i.e., date/time report is printed). In the center of the Footer insert
the page number as “Page _ of _ Pages.” On the left side, place the Program/Project Manager’s name and
telephone number. Use the default font for all entries in the Footer.
Advanced Options
Project/Program Interfaces
There are typically two types of interfaces that need to be identified and placed in the schedule:
Dependencies on other program products
Dependencies on external sources (e.g., vendor products such as Oracle Database Releases and facility
availability for installations).
Internal Dependencies
Dependencies (interfaces) with other Programs must be identified and placed in the schedules of both projects
to establish a point in time for the handover of a product or service that is mutually agreeable to both
Program/Project Managers and consistent with the delivery requirements of the receiving program. Frequent
tracking and agreement that the delivery is going to be made on time is required to ensure there is no impact on
the receiving program.
External Dependencies
Dependencies (interfaces) with external sources, such as vendors delivering products, must be identified and
tracked on a continuous basis to ensure any potential slippage is addressed early on. The interfaces are placed
in the schedule at the point of expected receipt, but the management of those interfaces is continuous.
Tip: When schedules are combined into a Master Schedule, these may be electronically linked using the
DDE feature.
Interface Management
Interfaces must be actively managed to ensure the best possible solution or the earliest identification of a
mismatch in meeting the time requirements. Once there is agreement between the delivering and receiving
7
parties, the Interface Point Milestones should be fixed (made fixed dates in the schedule). A schedule of
contacts between the parties should be established for updating or confirming the validity of the date. Any
indication that the delivery will negatively impact the receiving program should be immediately addressed and
contingency actions planned.
8
www.sap.com/contactsap
The information contained herein may be changed without prior notice. Some software products marketed by SAP SE and its distributors contain proprietary software components of other software vendors.
National product specifications may vary.
These materials are provided by SAP SE or an SAP affiliate company for informational purposes only, without representation or warranty of any kind, and SAP or its affiliated companies shall not be liable
for errors or omissions with respect to the materials. The only warranties for SAP or SAP affiliate company products and services are those that are set forth in the express warranty statements
accompanying such products and services, if any. Nothing herein should be construed as constituting an additional warranty.
In particular, SAP SE or its affiliated companies have no obligation to pursue any course of business outlined in this document or any related presentation, or to develop or release any functionality
mentioned therein. This document, or any related presentation, and SAP SE’s or its affiliated companies’ strategy and possible future developments, products, and/or platform directions and functionality are
all subject to change and may be changed by SAP SE or its affiliated companies at any time for any reason without notice. The information in this document is not a commitment, promise, or legal obligation
to deliver any material, code, or functionality. All forward-looking statements are subject to various risks and uncertainties that could cause actual results to differ materially from expectations. Readers are
cautioned not to place undue reliance on these forward-looking statements, and they should not be relied upon in making purchasing decisions.
SAP and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP SE (or an SAP affiliate company) in Germany and other
countries. All other product and service names mentioned are the trademarks of their respective companies. See http://www.sap.com/corporate-en/legal/copyright/index.epx for additional trademark
information and notices.