Professional Documents
Culture Documents
In Constantza City, precisely the central area of the cliff situated between Traian Street and
1 Mai Avenues, a new construction designed for commercial and office spaces are going to be built.
The length is of approximately 170,0 m and a width of approximately 70 m at extremities and of
about 40 m in the central area.
The construction is placed on the slope of the cliff with a foundation of 27 m deep below the
Traian Street level.
In order to realize a geotechnical and hydrogeological study (for which it was considered the
well-known geologic history of the emplacement and the characteristics of the future construction)
a new program of geotechnical and hydrogeological investigations was realized which included the
following phases:
- terrain research;
- lab research;
- office research dealing with the interpretation of results and specific calculus;
- compiling the study with recommendations and conclusions.
The researched emplacement is situated in the east part of Constantza, precisely the superior
part of the cliff that borders the old Port, Port Gates # 3 & 4 (cadastral register No. 16678, lot # 3).
In order to characterize the emplacement a topographical survey of the area was used realized in
Constantza Local Stereo System, The 75 Black Sea Height System, coordinated with the Black Sea
level (nMN), given by the beneficiary.
The perimeter of the future construction has a rectangular shape, 170 m long and
approximately 50 m wide, bordered on the northwest side by Traian Street and on the southeast side
by 1 Mai Avenue. Beyond the perimeter limit and the 1 Mai Avenue there is the inferior part of the
cliff.
The main characteristic of the terrain is its declivity towards the Port, the height ranging
from +39+38m (nMN) in the upper part (Traian Street) to +21+24 m (nMN) in the lower part (1
Mai Avenue), which corresponds to a virtual medium inclination of 1:2,5. In the middle part the
slope of the emplacement, with heights of +26+30m (nMN) there is a flashing berm with variable
widths (1425 m), which lead at slopes adjacent to the berm with inclination of 1:2 and even 1:1.
The inferior/lower part of the cliff which is not included in the emplacement is ranging
between +21 and +9, +12 (nMN), with inclination of about 1:2.
Due to the natural configuration the cliff started losing its stability and thus it was arranged
and consolidated by various works that are to be found in certain areas of the emplacement,
partially functional even if they were in turn affected by local instabilities.
At the time of the research the emplacement is stable, however with signs of future possible
landslides as following:
- longitudinal cracks on the upper part of the embankment (Traian Street from the estate
border to carriage road),
- wavings on the surface of the embankment, displaced consolidation elements,
- marked differences and cracks in the inferior/lower part of the emplacement (1 Mai
Avenue, including the carriage road) as well as beyond the border of the emplacement
on the slope towards the port.
Due to those aspects the investigations were extended beyond the estate border (the slope
between and the port) necessarily for verifies of the stability of the area in various hypotheses.
3.2 Climate
The climate of the researched perimeter is temperate-continental, with the following
parameters:
- the annual medium temperature +11,2 º C
- the absolute minimum temperature - 25.0 º C
- the absolute maximum temperature + 38.5 º C
The annual medium precipitation/rainfall have a 378,8 mm value and they represent the
average values recorded in the past 10 years.
The distribution of precipitation could be represented as such:
- in winter …………….83,4 mm,
- in spring …………….86,0 mm,
- in summer …………108,5 mm,
- in autumn…………..100,9 mm.
Another important factor of climate is determining the course and strength of wind. The
prevalent courses of wind are north (21,5%), west (12,7%). The wind calm has a 15,2% value and a
2,44,3 m/s medium intensity on the Beaufort scale.
From a seismic standpoint the researched area is in the E zone with ks = 0,12 (according to
“Romania – Territorial division into zones from the standpoint of ks coefficient.” – P 100/1992
Norm) and Tc = 0,7 sec (according to Romania – Territorial division into zones from the standpoint
of corner periods”)
According to STAS 6054-77, the maximum frost depth is 0,70 m, the medium frequency of
frozen days with a T < 0°C is 68,9 days/year.
The terrain works began on 03.10.2005 and were finished on 30.11.2005, being the first
phase of the contract.
In order to complete the studies geotechnical borings were programmed on the East Side
between and the port, on the arranged slope.
In the researched area nine geotechnical borings were realized by S.C. ISPIF S.A. (P1, P2,
P3, P3/1, P4/2, P4/3, P4/4, P’4, P5) with 5-40m deep as well as eleven geological borings (S1, S1’,
S1’’, S2, S2’, S3, S5, S6, S7, S7’, S7).
The fulfilled terrain works are to be found in the annexed Plan.
The borings were realized in a dry system by a 12-inch diameter semi-mechanical rig with
special devices for sampling. Disturbed and undisturbed samples were drawn from the borings for
accurate determinations in the Technical University of Civil Engineering Bucharest geotechnical
laboratory.
After drilling the borings were equipped with piezometers, PCV pipes of 110 mm diameter
to measure the underground water level and to determine the filtration coefficient.
The geological borings were realized with a 100 mm diameter manual rig, thus drawing
disturbed samples.
According to field works the following stratification was acquired in the attached index of
borings. The main geotechnic and hydrogeologic obtained aspects are:
- the presence main rock, which is Sarmatian limestone, at about –0,67, +0,23, +1,05 (nMN); the
contact with the covered system is made beneath a surface with a general east-west slope;
- above the Sarmatian limestone there are some inferior Pleistocene deposits made up of green-
brown clays, clay with gypsum, greysh clay with friction mirrors, 10-13 m thick (between
–0,67+ 18,00 (nMN)); the actual level of water in this layer was find, between +6,8 and +7,5
(nMN);
- in the clayey layer there is a gypsum insertion of 0,701,50 m thick with a clayey
inclusion till +10 + 15 m;
- reaching the upper layers above the gypsum layer there was a clayey materials layer of
3,65 m thick highly- kneaded, with friction mirrors and a high moisture.
- till the surface of the natural ground there are upper-medium Pleistocene formations made up of
clayey materials such as red clay with lime concretion and silty clay;
- above the natural ground from the south area of the emplacement there are clayey filling and
loess with lime blocks and gravel, with a variable thickness (13 m);
- in the north area, on a 60 m length, these fillings are 8 m thick and are made of a mixture of
clay, blocks and building material debris at the superior level, and huge limestone blocks at the
lower level; in this area the local water level was +16 (nMN);
- the underground water is quartered in the Quaternary deposits, acting as a waterbearing with a
medium-low permeability, k = 103 cm/s, made up of an vertical ascending drainage with an
under pressure water contribution from the Sarmatian limestone; the level of the underground
water from the south central area of the emplacement is between +6,825+ 7,513 (nMN), and in
the north +16 (nMN) caused by the water contribution of fillings;
- the under ground water course is from the north-west towards south-east with a slope of 12 ‰.
The detailed results of the field research are shown in the Hydrogeological Study made by
S.C.MIDA CONSTRUCT.
In the attached drawings four transversal sections as well as a longitudinal one in the soil
foundation of the emplacement are shown.
According to field and lab research, we can notice that within the emplacement, that has a
virtual inclination of 1:2,5, the soil foundation is made up of cohesive material deposits such as silty
clay and clays, above the limestone main rock.
On the entire emplacement from the actual surface of the slope there is a coarse filling layer
with different widths and composition, as follows:
- in the south area (the distance between P1, P2 and P5), fillings of 3 m thick (at the edge of the
slope) and 0,30 m (at the base of the slope), made of silty clay, silts combined with gravel and
limestone blocks. These nonhomogenous fillings have the following shearing resistance
parameters =2040° and c=252kPa;
- in the north area (60 m long), fillings of 1,5 m thick (at the edge of the slope) and over 7,8 m
thick (from the central towards the base of the slope), made of limestone blocks in clayey mass.
Beneath the coarse filling layer till +10+15 (nMN) where gypsum insertion are present, a
20 m thick cohesive material package was identified, distinguished as follows:
- A 3-5 m thick layer of earth mixture (silt, red silty clay, yellow clay) with limestone concretion,
which could come from older earth-like filling. The materials of this layer have medium to high
plasticity (Ip = 20 – 40 %), reduced moisture content and a hard state. Those from the south area
have a 60 – 75 % saturation degree (in P5 boring 45 %), which states the fact that this layer is
well preserved in an unsaturated state, as opposed to the deep saturated layers, due to the
drainage works made in the area. In the north (undrained) area the same layer is saturated. In
terms of deformability, due to inhomogeneity, the layer can be characterized as having a high
compression (M200-300 = 5700 ÷ 7800 kPa), but locally can have a reduced compression (M 200-300
= 20.000 kPa). The shearing resistance parameters are homogenous: the intern friction angle
=1020 and cohesion c=6080 kPa.
- A 1214 m red fat clay layer (clay per cent 50 %) with lime concretions and friction mirrors.
These high plasticity soils (Ip=4050 %) are in a plastic solid state, although the moisture
content is overgrown and saturated. In terms of shearing resistance the friction angle is
=10°20° and cohesion c= 6090 kPa.
- A 3-6 m greyish fat structured clay (90 % clay), with degraded limestone and friction mirrors.
These specific clays have a high plasticity (Ip= 4060 %), and are in a plastic solid state, high
moisture (w= 40 %) and are saturated. From compressibility point of view, these clays can be
characterized by oedometric moduli M200-300 = 12000 ÷ 12500 kPa, as part of soils with medium
compression. The shearing resistance parameters have the following values: the friction angle
= 6° - 8°, cohesion c = 50 – 60 kPa.
`The materials that are in contact with the gypsum layer have high friction angles (due to
coarse inclusion) = 17° – 20°, and same cohesion (c= 50 – 60 kPa).
The red and greyish fat clays are structured clays with sensibility to wetting volume increase
and glomerules grow up.
Supplementary tests on wet samples have been made that revealed the drastic decrease of
shearing resistance parameters.
Between the gypsum insertion, 0,70 – 1.50 m thick, and the base rock (cracked limestone)
situated between –0,70+1,50 (nMN), there is a cohesive layer of 11 m thick. This layer is
made of clay and yellow–green–greyish silty clays, with limestone concretions and even mixed
with limestone blocks in depth.
Materials with a medium-high plasticity are found in a solid plastic state, saturated and have
medium compression (M200–300=10000 ÷ 20000 kPa), reduced friction angles = 9 °– 16° and
high cohesion c = 100 – 200 kPa.
For the material below +11 (nMN) such as limestone, according to recorded data, the
compression resistance is c=15000 – 20000 kPa.
According to field and lab researches the studied site situated between Traian Street and 1
Mai Avenue, with a medium slope of 1:2,5 is formed of:
- coarse nonhomogenuous fillings of cohesive or less cohesive materials mixed up with limestone
gravel or blocks. These fillings have a high thickness (up to 7,80 m) in the north area
(approximately 60 m long) and a low one (up to 3,20 m) in the south area (80 m long), whereas
in the central area (on a 3,5 m length) there was none present.
- a 20 m thick package of cohesive soil, precisely silty clays and clays. Several layers are to be
encountered within this package: a 3-5 m thick silty clay layer of different colours and silt with
limestone concretions, a 12-14 m red fat structured clay layer, a yellow-greyish one on a 36 m
length and a green-greyish one (in depth). The surface silty materials have a high
compressibility, are in a solid unsaturated state in the south area, thus proving the efficiency of
the drainage system and his influence area (approx. 7 m depth). The red and greyish fat clays
have high moisture content, a medium compressibility and are saturated. They are structured
clays with a high degradation tendency in direct contact with air and water. The green-greyish
clays are saturated, have a medium compressibility and an increased cohesion opposed to upper
layer materials. The existence in that cohesive package of gypsum intrusion (+ 10, +15 level)
and a greyish clay layer with friction mirrors and reduced shearing resistance leads to
assumption of possible appearance of a yielding plan in this area,
- the basis rock is made of limestone and is placed between –0,67+1,05 (nMN)
According to NP 074/2002 norms, in order to establish the geotechnical category and risk,
the following aspects are to be considered:
- field conditions,
- underground water,
- the importance class of construction,
- neighboring structures
Considering the height and technological necessities (4th underground floor) of the
forthcoming building, the imposed level of foundation is approximately +11 (nMN).
Under these conditions the direct foundation system can be applied, at the imposed depth,
when the foundation soil is made up of green-greyish clays, considered a foundation soil.
When be finding the gypsum inclusions at this depth they will be removed till the green clay
layer is reached.
For the green–greyish clays between +11 (nMN) (slab foundation level) and the basic rock
(limestone), the conventional pressure of the foundation soil (pconv) is 450 kPa according to STAS
3300/2-85.
When adopting the direct foundation solution in the deep clay layer we have to verify the
foundation soil at the Limit Deformation State and at the Limit Bearing Capacity State, according to
direct foundation design Romanian Norm NP 112-04/2005.
Thus the plastic failure pressure (ppl) is 1352,5 kPa and the critical lateral yield pressure (p cr)
is 1950,4 kPa.
The settlement have negligible value in case of the foundation solution with rigid foundation
mat at +11 (nMN), taking into account the fact that there is no loading spore as opposed to the
geological charge at that depth (Sg= 560 kPa).
Due to the fact that the forthcoming building is to be built on a sloping field according to the
already mentioned Norm (NP 112-04) both the local stability of foundation and the general stability
of soil foundation-building assembly must be checked. The construction must be checked at sliding
on the foundation base, so that active earth pressure can be taken over by friction.
For direct foundation solutions, according to STAS 3300/2-85 and NP112 – 04 Norms, at
the preliminary and final calculus we have to obey the conditions:
- for centric loads:
pefpconv - in the fundamental loading group (GF)
p’ef1,2 pconv - in the special loading group (GS)
- for loads with:
- a single direction eccentricity:
pefmax1,2pconv ( GF)
p’efmax1,4pconv (GS)
- for two direction eccentricity:
pefmax1,4pconv ( GF)
p’efmax1,6pconv (GS)
where:
- pef, p’ef is the vertical medium pressure on the base of the foundation derived from the calculus
loads of fundamental and special group,
- pconv is the calculus conventional pressure determined according to STAS 3300/2-85, B Annex,
- pefmax, p’efmax is the maximum effective pressure on the basis of foundation derived from the
calculus loading of fundamental and special group.
For direct foundation at level +11 (nMN), retaining structures (vertical shields) are
necessary which imply deeper foundation elements.
The indirect foundation of the forthcoming building implies using reinforced concrete piles
or barrettes that will take over the vertical and horizontal stresses. Therefore the infrastructure
solution must be linked with retaining shields solution in order to overtake the horizontal loads of
the earth.
The bearing capacity of a 1,0 m diameter and 10 m long bored pile embedded in the cracked
limestone is 7500 kN.
To overtake the horizontal loads can be use barrettes with a high overtaking capacity of
horizontal load (perpendicular on the short side of the section).
The distance between the infrastructure elements will be set considering both the position of
resistance piers and walls and the general displaying of the bearers of the retaining shields.
The horizontal loads are preserved during exploitation period and are necessarily to be
carried out after execution.
When the solution of bored piles embedded in the base rock is taken, considered as tip
carrying piles, the calculus must be made at the Limit Bearing Capacity State according to STAS
2561/3-90. The Limit Bearing Capacity State is considered in accordance with STAS 3300/1-85.
At Limit Bearing Capacity State (under vertical and horizontal loads) must be accomplished
the following condition:
S≤R
where:
- S is the calculus effort on one pile
- R is the bearing capacity of the pile according to its type of loading
The section of the pile are designed and verified at a maximum loads that can appear in
different parts of the pile, considering the calculus resistance of the materials that make up the pile.
The calculus were made under static and seismic conditions (ks = 0,12) using different
methods, the results of Janbu method being the most unfavorable ones. The following aspects can
be drawn:
1. under the actual conditions the emplacement is stable,
2. possible yielding surfaces can appear under the actual conditions:
- at contact between the filling layer and the natural ground (which explains the already
existing superficial local failures within the emplacement), reaching stability at limit just in
case of water infiltration in the base of filling,
- deeper in the clay layer with friction mirror.
3. the deep possible yielding surfaces can affect the emplacement far beyond the borders of the
forthcoming building extending up to the upper part of the slope from Traian Street closely to
the existing mansions, and up to the lower part from the 1 Mai road territory to the slope of the
harbour side.
In case of a deep shield execution adjacent to Traian Street the sliding stability is ensured
under the most unfavorable hypotheses, however conditioned by resistance characteristics of the
shield:
- if the shield can’t entirely overtake the stresses from the failure plan (situated in the deep into
weak clay layer) the influenced areas are extended up to the neighboring structures,
- if the shield can entirely overtake the stresses, the possible shield downstream area to be
affected is reduced, the influence extending to the harbor,
- to shield is necessarily to restrict and control the displacement at minimum values to avoid the
displacement of adjacent soil (Traian Avenue and 1 Mai Avenue).
If excavation is made in step by 5m deep under protection of principal and secondary
retaining shields the sliding stability is assured.
The retaining structure stability (resistance and deformations) will be assured and assessed
depending on fixed designed solutions.
The general stability of the emplacement after the execution will be assured by the presence
of the building, which was designed and verified for that precise purpose (at horizontal loads).
Chapter 7 – Solutions to carry out the necessary excavations for the construction
The surface of the forthcoming building is 170x50 m 2, being superposed on the cliff,
between Traian Street (+ 39 (nMN)) and (+ 22 (nMN)).
The foundation solution of the building, from a technologic standpoint is going to be
situated at + 11 (nMN). Under these circumstances a deep enclosure is needed (for the excavations
and foundation execution) with a maximum depth of 27 m adjacent to Traian Street and a minimum
depth of 11 m adjacent to and a 50 m width.
Considering the neighboring structures and their function, to realize the work enclosure a
contour shield will be provided to support the ground and restrict the affected execution area.
The shield from Traian Street will be approximately 27 m high. The pile shaft under the
work enclosure level will depend on the chosen supporting solution, 11-12 m, embedded in the base
rock (cracked limestone). When choosing the shield and the embedded level we will consider the
existence and level of underground water, so that it won’t be disturbed by the shield, for the
neighbouring structures and the enclosure. The increase of water level changes the effort state from
the adjacent field of enclosure, which triggers the increase of stresses and field distortions.
The shield will be made of reinforced concrete and will be the first phase in the enclosure
execution.
The shield can be made of concrete panels or bored piles.
Due to the extreme height of the shield and to the field’s nature that has to be excavated,
1,00 m diameter bored piles should be used. These piles can overtake the high loads caused by
active earth pressure and underground water pressure.
At the upper part of the shield a reinforced concrete beam is to be used supporting the
infrastructure of bored piles.
The shield from (towards the harbour) will be approximately 11 m high. When establishing
the embedded length the same aspects will be considered. The building solution will be the same,
bored piles.
For this side of the emplacement we could analyze the excavation within the sloped.
Between + 22 (nMN) and +11 (nMN) the field is made of structured red silty clay, in a plastic
consistency state, wetting sensitive, with reduced shearing resistance parameters that allow a 1:3
inclination within the stable slope up to a 11m height. Such an inclination could entirely affect that
will have to be closed during the execution, involving additional excavations and controlled filling.
Therefore a vertical shield is necessary on this side, too.
In order to border the enclosure in terms of length, the border areas will be properly
arranged. We could use some transversal shields at the borders of slope using the same building
solution, precisely reinforced concrete walls made of bored piles.
A 1:3 virtual inclination slope could be used. Due to the 27m maximum height of enclosure,
80 m plane surface excavations will be made at each border involving additional excavation and
filling works. The main shield will be elongated far beyond the borders of the emplacement on a 85
m length.
Considering the geotechnic aspect of the emplacement as well as the dimensions of the
construction, the shield as part of the construction requires a final design.
In order to assure the excavation stability we will consider the loads of underground water
pressure and earth pressure, a restriction of deformations to avoid any influences that could affect
the neighbouring structures thus being necessary.
The underground water level (+6÷+7 (nMN)) was beneath the excavation level (+11 (nMN)
and even +16 (nMN) in the north area). Certain water accumulations could be formed due to
infiltration in the filling layer of the south area on a 3 m depth after the drainage arches have been
taken out of order.
The active earth force that acts upon the most stressed shield (adjacent to Traian Street)
when excavating at +11 (nMN), could vary from 4950 KN/m to 3200 KN/m. If the overload
conveyed by the load of the adjacent platform is 20 KN/m² a 320 KN/m active earth force is added.
When designing the shield we will consider the retaining system and the distances between
the supporting elements as well as the embedded length.
The shield has different heights in the working enclosure, an aspect that was discussed when
evaluating the stresses.
When checking the shield’s behaviour during excavations we will consider the designer’s
established plan.
The supporting of the shields during execution could be accomplished using anchorage or
supporting in the interior of the enclosure.
For the anchorage, we need 70 m long drillings and anchors to create the anchorage bloc as
well as their injection. The anchorages will be realized on several levels, differently for the
longitudinal shields, depending on the free needed height of enclosure walls.
In case of supporting in the interior of the enclosure, the horizontal loads will be taken by
lining supported by founded elements on the bored pile or on barrettes with a depth reaching the
base rock, cracked limestone.
This supporting will be realized from top to bottom during excavation.
The vertical supporting elements (infrastructure) must be executed in the first phase at the
desired dimensions. As the excavation moves downwards (5 m stairs) the necessary lining will be
executed. We could support the shield by using lining supported by longitudinal beams that assure
the co-operation of the piles of the shield’s wall.
The supporting elements will be designed according to the construction structure for a better
efficiency (cross sections, distances).
Therefore the supporting infrastructure should be the construction founding solution
(indirect founding).
7.3 Excavations
When we realize an enclosured bordered by a vertical perimetric shield we need a 165.000
m3 minimum excavation volume.
When excavating we should consider the following aspects of the emplacement:
- the diggings will be realized from top to bottom in 5 m deep phases in relation to shield
supporting;
- between 3 m (the south area) and 8 m (the north area) the filling layer contains coarse limestone
elements as big as boulders or stone blocks in the north;
- beneath the filling layer there is the reddish macrostructured clay layer that has a specific
mechanical behaviour. This ground is subjected to dilantancy caused by shearing deformation,
and when is wetting, due to structural discontinuities, the materials change their consistency and
it fails by shearing yielding, and their cohesion as well as their internal friction angle drastically
reduces. A shear yielding occurs as a result of constant tangential efforts caused by moisture.
Therefore during execution, adequate measures are taken to avoid moisture by reducing the
quantity of water and decreasing the contact of clay with water;
- slopes and gutters will be used to collect and drain rainfall;
- in the north area direct drainage works will be used where the underground water level reaches
+16, 00 (nMN);
- the temporary slopes within the excavation can have 1:1 in the filling layer and the mainly
cohesive material layer , in case of a rapid and dry execution. During excessive rainfall weather
the slopes will have 1:2;
- the excavation will be 2,5 m high stepped, with execution of the necessarily technological roads;
- the transporting of the excavated materials could be realized on the already existing roads
(Traian Street and 1 Mai Avenue), but when designing the shield enclosure we will consider the
overload induced by this activity;
- the excavations can only be executed after rain waters from the enclosure have been drained.
According to Ts norm index, the excavations will be part of third category, in case of
mechanized excavation and part of “extremely strong“ category in case of manual execution.
In the north area, huge dimension stone blocks are encountered which will require
preliminary breaking.
The drainage within the emplacement during and after execution starts considering the
already research-revealed situation.
According to hydrogeological study the underground water is beneath construction mat
foundation level, with a 1,2 % slope gradient towards the harbour from north-west to south-east.
The already existing water collecting devices are still running. The taking out of order of the old
drainage elements, the supporting elements (shields) of the excavation and of the final construction
should not modify the hydraulic regime.
Therefore the following aspects should be considered:
- in the south area the falling into disuse of arches and transversal gutter could lead to a local
increase of water level;
- in the north area there is a higher water level (+ 16 (nMN)) precisely in the central and lower
part of the slope;
- in the west area (adjacent to Traian Street) water level could be increased accidentally in the
long run by leaking of water supply and sewage pipes that serve the nearby mansions.
1. General data.
The actual reference material was signed according to 20/S/2005 contract between SC
MIDA CONSTRUCT SRL, as Accomplisher, and SC HECON SRL, as Beneficiary, and deals with
“The hydrogeologic study of the emplacement situated between Traian Street and 1 Mai
Avenue, Constantza, Survey no. 16678, Port Gates # 3 & 4, lot #3“.
The following papers and documents were used to prepare the study:
- geologic and hydrogeologic field mapping realized in august to october 2005;
- hydrogeologic drillings (piezometers) and geologic drillings made by SC ISPIF SA;
- direct observations, tests and hydrogeological measurements “in situ“ to establish the
hydrogeological characteristics of water-bearing traced out during drilling;
- the calculus, analysis and data interpretation considering the tests and hydrogeological
measurements;
- the topographic plan of the studied perimeter, at 1:500 scale, in the Constantza Local Stereo
System and in the 75 Black Sea Height System given by the beneficiary;
- general data concerning the geology, hydrologic and climate regime of the region provided
by specialized literature.
2. The emplacement
The studied perimeter is placed between the east part of Constantza, the # 3 & 4 gates of
Constantza harbour, in the upper part of the cliff that borders the harbour, between Traian Street and
1 Mai Avenue (1st and 2nd drawing boards).
The perimeter has a quasirightangled shape, 170 m long and 50 m wide. On the northwest
side the field height is between 39 and 38 m with a slight southwest to northeast inclination. The
southeast side is bordered by 1 Mai Avenue and is placed at 21 - 24 m with northeast inclination.
The upper slope of the cliff is broken in the central area by a 14 m to 25 m wide bench situated
between 26 m level to 30 m level. The inclinations of the slopes that border the bench are placed at
1:2 – 1:1.
The lower part of the cliff develops up to the 9 m level to 12 m level in the southeast border
of the perimeter and 1 Mai Avenue, the bottom of the slope being surrounded by the harbour walls.
Constantza City is part of the maritime geographic area of Dobrudjea Plateau and develops
along the seacoast on a 10-15 km length. On the seacoast we can identify 3 altitude areas: the
peninsular area with a NW-SE orientation and inclination, the continental area (the east border of
Dobrudjea Plateau) with a high altitude in the west (60 m) and a low one on the seashore (25 m)
and the seashore including the beach and the harbour.
On the background of temperate-continental climate, Constantza climatic aspect has specific
characteristics due to alternative continental and maritime air coverings.
The medium annual temperature is 11 °C. The maximum absolute temperature was recorded
in July (38,5 °C), and the lowest one in January (-25 °C).
Baric systems and general atmospheric circulation determine the winds. The north and west
winds are prevalent in January, whereas the north and southeast winds are predominant in July. The
daily-night breeze caused by high differences between water and land temperature is specific to this
area.
The minimum annual precipitation is the lowest ever-registered in Dobrudjea, the values
ranging from 350 mm to 400 mm. The snow layer is discontinuous, not uniform and it maintains
just for a few days.
The most important watercourse in the area is Carasu valley, in the north of Constantza.
Although it has a low flow, the watercourse is permanent. Most valleys have a temporary character,
running dry immediately after rainy or snow melting periods.
In the north, Tabacarie and Siutghiol lakes that have a lagoonal character border the city.
These lacustrian basins are caused by Black Sea level variations, in the last geological periods, by
seashore draughts and alluvial deposits brought by maritime draughts from Danube mouth. Sea
seclusion and anthropic sewer supply led to sweetening water.
From a geological standpoint Constantza territory belongs to the structural area of south
Dobrudjea which is developed in the south of the Capidava - Ovidiu connection line and is made up
of a higher moesic platform with a pleated foundation composed of pre-proterozoic and proterozoic
green and crystalline schists, above which there is a paleozoic, mesozoic and neozoic sedimentary
layer.
The Paleozoic is represented by Silurian clay shale deposits mixed up with thin limestone
insertions.
The mesozoic is made up of medium and upper Jurassic and cretaceous deposits composed
of arenaceous limestone, mixed limestone, siliceous limestone, limestone and limestone dolomite,
zoogene limestone, chalk limestone, sand and glauconite sandstone, marl and conglomerate.
The objective of the present study focuses on neogene deposits (Quaternary and Sarmatian).
The upper Holocene is composed of deposited alluvia from the main valleys, redeposited
loess, maritime sand and ooze of the beach.
From a hydrogeologic standpoint there are 3 water-bearing layers in Constantza:
- the deep water-bearing layer quartered in cretaceous and jurassic limestone with tens of litre
per second flow. This layer assures the drinking water for the city from the pumping stations
Cismea I and II.
- the medium-depth water-bearing layer with water quartered in sarmatian sandstone and
limestone with a reduced flow. The Sarmatian clay that acts as a waterproof layer favours
the underground water accumulation of this layer.
- the low-depth water-bearing layer of low permeability loess deposits, mainly supplied by
precipitation.
5. Geological and hydrogeological considerations concerning the studied perimeter
Within the studied perimeter a series of drillings such as low-depth geological borings and
geotechnic borings defined later as piezometers in order to identify the soil lithologic nature and the
hydrogeological conditions of low-depth low permeability water bearing layer have been realized.
Field recognition of the emplacement and the surrounding areas has been realized on a series of
alignments along the cliff.
Field recognition
Studying borings
These were placed on and outside the surface of the studied perimeter, in the lower part of
the cliff to obtain additional information (11th drawing board).
The geotechnical borings were realized in a dry system with a semi-mechanical drill rig (7 th
picture) with a 12 ¾ in diameter. Disturbed samples and undisturbed samples have been extracted
from the boring and given to UTCB geotechnical lab. After digging the borings have been equipped
with 110 mm diameter PCV pipes to measure the underground water level and to determine the
permeability coefficient. The piezometers were equipped with a protective metallic cap embedded
in the concrete slab.
The geological borings were executed using a 100 mm diameter manual drill rig. Disturbed
samples were extracted from these borings.
When choosing the emplacement we took into account the obtaining of a maximum amount
of information on different alignments of the perimeter as well as easy access of the drill rig on each
location.
The equipped boring, the intercepted lithology, the testing depths, the underground water
level are shown in the boring data sheets (12th to 26th drawing board). The borings were stopped
when the geological objective or the filling hard material or the hard rock was reached.
The data concerning the level of each boring, the boring depths as well as the intercepted
underground water level (NHs) are shown in Table 1.
(Table 1)
Boring Boring Level Boring Depth NHS Depth NHs Level
[m] [m] [m] [m]
P1
P2
P3
P4/1 dry
P4/2 dry
Some of the borings have intercepted sarmatian limestone formations at -0,67 m level (P1),
+0,23 m level (P3) and +1,05 m level (P5), the contact with the covering Quaternary formations
being realized on a general east-west sloping surface.
Above the sarmatian limestone there are the lower Pleistocene deposits composed of green-
brown clay with manganese spots, gypsum clay, grayish friction mirrors clay. In P1 boring these
deposits were found at around +15,63 m level. The gypsum clay level within P1, P2, P3, P’4, P5,
was found at +10 to +15 m level. Its thickness was 50-70 cm.
Further on, near the surface medium-upper Pleistocene formations were found, composed of
reddish and brown clay, silty clay and loess.
Above the Quaternary deposits in the south part of the perimeter there are fillings made up
of limestone and gravel boulders, with a 3,30 m thickness (P1 and P2 borings).
In the north part on P4/1, P4/2, P4/3 and P4/4 borings, over 7,80 m thick fillings (P4/2
boring) were discovered made up of a mixture of clay with boulders and brick remains in the upper
part and at the base 15-25 cm limestone boulders. The area in which these fillings have been
identified lies in the north part of the median bench that interrupts the slope; according to the field
morphology they have a decreasing thickness close to P5, and far beyond the north border of the
studied perimeter they might have a over 5 m thickness.
The lithological structure of the soil is represented in 4 transversal sections and a
longitudinal one. (5th to 10th drawing boards).
The measured hydrostatic level in the borings is between 6,825 to 7,513 m, except for P’4
boring where water was found at 16.12 m and that is due to the percolated water supply in the
filling base (9th drawing board) where precipitation-percolated water could be stored. Downriver the
P’4 boring there was no water at the near surface. In the P4/4 boring, completed as a piezometer, no
water was found, not even after a month since the completion. However, water could be present at
the boring sole in the boulder filling.
The lack of water near the surface is caused by the low precipitation regime and by the
existent draining system that collects infiltrations and discharges them in the harbour area.
The existence of water in the lower Pleistocene clay could be the result of the pressurized
sarmatian aquifer, the water boosting itself through the vertical drainpipe and forming a low
permeability water bearing layer.
We determined the permeability coefficient by using Hooghoudt method (recurrence
method), considering the leakings in the borings that intercepted the underground water and the
recurrence measurements of the hydrodynamic level.
The recurrence diagrams and the calculus of the permeability coefficient for the low
permeability water bearing layer opened through P1, P2, P3, P’4 and P5 borings are shown in
Annexes 1 to 5. The value of these coefficients is shown in Table 2:
(Table 2)
Boring Permeability Coefficient Value - Kf
m/day cm/s
P1
The filtration coefficient determined in P’4 boring can characterize the medium-upper
Pleistocene formations whereas the other values can characterize the lower Pleistocene clay.
The direction of the underground water flow is from northwest to southeast with a 12 ‰
average slope (11th drawing board).
The chemical bulletin of the collected water from P1 boring shows a weak carbonic and a
high sulphate aggression on concrete and no carbonic aggression against metals.
The chemical analysis of the collected underground water from P’4 boring (Annex no.7)
shows that they have a weak aggression on concrete due to their salty content, an extremely weak
carbonic aggression, but a high sulphate and manganese aggression. They, also, have a high
carbonic aggression on metals.
6. Conclusions
The borings within the studied perimeter have identified Quaternary formations mainly
composed of clay and upper sarmatian limestone formations between –0,67 and +1.05 (nMN). In
the north area of the perimeter filling material made up of clay, limestone boulders and brick
remains, with a 7.8 m thickness have been identified. In the central and southern area the filling
material is up to 3.30 m thick.
The underground water is quartered at the bottom of the Quaternary deposits composing a
low waterproof aquiferous probably caused by the pressurized water supply of the sarmatian
deposits through an ascending vertical drainpipe. The underground water level measured within the
southern and central borings is between +6.825 to +7.513 (nMN). In the north area the underground
water level is approximately +16 (nMN) and it is probably caused by the water supply from the
filling area.
The direction of the underground water flow is from northwest to southeast with a 12 ‰
slope.
In the south part of the perimeter, hillside retaining walls and water collecting drainpipes are
built. On the surface of the forthcoming building there are no active slidings or water leakings. They
appear at a few tens of meters of the southern part of the area nearby a pluvial water-collecting
gutter, parallel to 1 Mai Avenue.
When excavations and/or retaining walls are realized we would have to build a new drainage
system to collect underground and pluvial waters. A drainage system is going to be built in order to
overtake the water from Traian Street and the nearby blocks of flats in case of a major damage that
might affect the potable water pipes and sewage for the nearby blocks. The drainage system must
have a permanent character in order to avoid water accumulation in the upper part of the cliff.