You are on page 1of 14

Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in

the state of AP.


Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500
to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS Rev.


: 0 W.e.f: 03-03-2011

Page 1 of 7

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS

1. GENERAL

This item of work shall be dealt with construction of Pipe culverts in


complete
compliance to the technical specifications.

2. PROCEDURE

The procedure for construction of Pipe culverts is elucidated as under:

# DETAILED CONSTRUCTION DRAWING PREPARATION:

Detailed working drawing will be prepared & submitted for approval for
each and
every Pipe Culvert.

# SETTING OUT:

After the site has been surveyed, the limits of excavation shall be set
out to true
lines, curves and slope as per the MORT&H Specifications.

# DISMANTLING OF EXISTING STRUCTURE:

In case of re-construction the existing structure will be dismantled


after taking the
joint measurement of existing structure up to NGL. In case of widening
of pipe
culvert only the head wall will be trimmed as shown in drawing.

# EXCAVATION:

The excavation for foundation bed for pipe culverts shall be done true
to the lines
and grades shown on the drawings or in accordance with the Cl. No. 2903
of
MoRT&H. After completion of the PCC and head wall up to the bottom of
the pipe
level, the open trench will be cut in existing embankment up to the
level shown in
the drawings and as per MORT&H Cl. No. 2903 (Para 1).

In case of high embankments where the height of fill is more than three
times the
external diameter of the pipe, the embankment shall first be built to an
elevation
above the top of the pipe equal to the external diameter of the pipe,
and to width
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01
in the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03:
Km.144+500 to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS


Rev. : 0 W.e.f: 03-03-2011

Page 2 of 7

on each side of the pipe of not less than five times the diameter of
pipe, after
which a trench shall be excavated and the pipe shall be laid.
The pipe shall be placed where the ground for the foundation is
reasonably firm. If
the soil at the bed level of the pipe is soft, spongy or other
unsuitable soil, it shall
be removed to such depth, width and length as directed by the Engineer
and the
extra depth shall be backfilled with approved granular material and
compacted up
to specified level.

If bed-rock or boulder strata are encountered, excavation shall be taken


down to at
least 200 mm below the bottom level of the pipe in accordance with the
Para-4 of
the Cl. No. 2904 of MORT&H.

Excavation shall consist of the removal of the material for the


construction of
foundation for apron, head wall and other similar structures, in
accordance with
the requirement of MORT&H specifications and the lines and dimensions
shown on
the drawings or as indicated by the Engineer. The work shall include
draining and
pumping. The removal of all logs, stumps, grubs and other deleterious
matter and
obstructions, necessary for placing the foundations, trimming of
excavations,
backfilling and clearing up the site and disposal of all surplus
material.

# FORM WORK:

Formwork of required length and size shall be provided for laying and
placing of
lean concrete layer. Side formwork shall be used for apron as well as
the head wall
concrete work. All materials for formwork will conform to IRC:87
Formwork shall be removed not earlier than 24 hours after placing of
concrete. The
design and erection of formwork shall be as per IRC-87 and conforming to
Section-
1500 of the Technical Specifications (MORT&H).

# LAYING OF LEVELLING COURSE / HEAD WALL:

i. Approved Design mix concrete would be provided.


ii. Till commissioning of our batching plant, Concrete mixer of 10/7
capacity with
matching number of weigh batches will be provided in adequate
number for
concrete production for use in box culverts. Utmost care will be
taken to
ensure the quality of the concrete.
iii. Adequate number of needle vibrator will be used for proper
compaction of
concrete.
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in
the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03:
Km.144+500 to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS


Rev. : 0 W.e.f: 03-03-2011

Page 3 of 7

iv. Levelling course Concrete M15 shall be laid to the thickness of


150 mm to
reach the required founding level.
v. After completion of PCC, head wall below sill level (M15 concrete)
is laid
accordingly as stated above. And after bedding and laying of
pipes, Head wall
top lift (M15 Concrete) is laid accordingly.

# BEDDING FOR PIPE:

The bedding surface shall provide a firm foundation of uniform density


through out
the length of the culvert conforming to the specified levels and grade
shown on the
drawing and will be as per the following cases.

Case – 1:- If the height of the fill of embankment above the top of the
pipe is less
than 4 m, the bedding will be prepared with granular material as per Cl.
No.
2904(1) of MORT&H.

Case – 2:- If the height of the fill of embankment above the top of the
pipe will be
more than 4 M, the bedding will be prepared with PCC as per Cl. No. 2904
(II)
MORT&H.

# PIPE LAYING:

Pipes will be laid in true length and line as per working drawings at
the approval of
the foundation bed by Engineer. In case of double or multiple pipe
culverts the row
of pipes shall be separated by a distance equal to at least half the
diameter of the
pipe subject to a minimum of 450 mm or as per the site conditions. Pipe
centres
will be matched in case of widening.
The lifting, loading and unloading of concrete pipes will be done by
small cranes /
JCB at the factory / yard in such a manner that the pipes do not suffer
any undue
structural strain or damage.

The lowering of the pipe in the bed shall be done with small crane or
tripod-pulley
arrangement. If above two options are not feasible then the pipes will
be laid in the
bed manually.

The pipe will be laid from PCL to both directions depending on the case.
It will be
kept in view that pipe edge towards PCL be at such place that both the
ends will be
matching to the outer face of the headwalls.
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in
the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500
to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS Rev.


: 0 W.e.f: 03-03-2011

Page 4 of 7

The entire operations will be in accordance with the Clause No. 2905 of
the
MORT&H.

# PIPE JOINTING:

The pipe shall be jointed by flush joint. Flush joint may be internal
flush joint or
external flush joint. In either case, the ends of the pipes shall be
specially shaped
to form a self centering joint with a jointing space 13 mm wide. The
jointing space
shall be filled with cement mortar, I cement to 2 sand, mixed
sufficiently dry to
remain in position when forced with a trowel or rammer. Care shall be
taken to fill
all voids and excess mortar shall be removed

# BACK FILLING:

Immediately after the pipes have been laid and the jointing material has
hardened
the trench will be backfilled. The backfilling will be done in
accordance with Cl.
No. 2907 of the MORT&H.

Backfilling up to 300 mm above the top of the pipe shall be done


carefully and the
soil shall be thoroughly rammed, tamped or vibrated in layers not
exceeding 200
mm. The gaps between two adjacent pipes shall also be filled in the same
procedure as explained above.

The entire operation will be in accordance with the Cl. No. 2907 of the
MORT&H.

# PROTECTION AND CURING:

As per section 1713.1, exposed surface of concrete shall be kept


continuously in a
damp or wet condition by ponding or by covering with a layer of gunny
bags or
similar materials and shall be kept constantly wet for a period of not
less than 14
days from the date of placing of concrete.

3. EQUIPMENT/MACHINERY:

a. Excavator / J.C.B. which ever is


applicable
b. Batching Plant of capacity 30 M3/ hr
c. Mixer Machine of Capacity 10/7
d. Weigh Batches of Capacity 500 Kg.
e. Petrol/Electrical Vibrator & 60mm Nozzle.
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in
the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500
to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS Rev.


: 0 W.e.f: 03-03-2011

Page 5 of 7

f. De-Watering Pump
g. Transit Mixer of Capacity 4 M3
h. Other relevant tools

4. RECORDS AND DOCUMENTS MAINTAINED:

i. RFIs
ii. Level control sheets (if reqd.)
iii. Concrete Pour card / Concrete cube results

5. QUALITY CONTROL PROCEDURES:

To ensure the suitability of materials / concrete, tests would be


conducted at
field/laboratory as per Cl.1000 & Cl.1700 of MoRT&H. And the same
is detailed
in Inspection test plan.

6. SAFETY MANAGEMENT ACTION PLAN

In order to minimize the occurrence of site accident, the provision of


a safe
working environment for workers to work is essential. Our company
endeavors
to make a zero accident record in each site. In addition to the above,
the
following safety precautions must also be implemented in achieving the
minimization of site accidents.

SAFETY MEASURES:

a) Provisions for workmen:


i. It is required that all persons working at the site shall be
provided with
the safety equipments, protection means such as safety
jackets, hand
gloves, safety helmets and other necessary kinds.
ii. All persons working on the site shall be trained by
conducting the training
course for safety to ensure that they are fully aware of the
contents.
b) Provisions for Equipment, Machine:
a. All equipment will be ensured to operate safely, maintained
and
repaired periodically.
b. All power equipment should be insulated and covered to all
exposed live
parts.
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in
the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500
to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS


Rev. : 0 W.e.f: 03-03-2011

Page 6 of 7

c. A competent person shall inspect equipment during shift duty.

c) Provisions for Job Site:


i. Relevant Caution boards and sufficient lighting system
shall be installed
at the working area to ensure safety for construction
activities at night
time.
ii. The working area shall be free from hazards before
starting the work.
iii. Unnecessary materials such as empty bags and rubbish shall
be removed
periodically.
iv. Proper safety measures like barricading, guard poles
painted with
florescent in alternate bands, flags etc. will be provided
prior to the
commencement of excavation operations.
v. Signal man will be placed at heavy traffic locations at
the time of
Execution.
vi. Reflective sign boards will be placed during night near
risky locations.
vii. All workers shall be educated in the use of excavators,
bulldozers,
backhoes, graders and rollers such as the excavator arm &
bucket
distance and buffer zone in order to prevent from
injuries.
viii. Operators would be thoroughly instructed to prevent
pushing soil loads
into the main road area if any.
ix. Photographs would be taken to disseminate and maintain
traffic safety
records
x. Working area will be cordon with traffic cones to identify
survey setting
out to oncoming traffic on both sides.
xi. During excavation of foundations, if any hard rock is
encountered
special care shall be taken while blasting.
7. ENVIRONMENT CONTROL

i. All necessary measures shall be taken to maintain all


plants and
silencing equipments in good conditions so as to maintain
air and noise
emission during the operation.
ii. All necessary measures shall be taken to control the
disposal of all
forms of waste generated by the construction operations
and in all
associated activities.
Four Laning of Hyderabad – Karimnagar – Ramagundam Road on SH-01 in
the state of AP.
Package - 01: Km.28+200 to Km.82+000 & Package - 03: Km.144+500
to 197+000

Client : Andhra Pradesh Road Development Corporation


Independent Engineer : Louis Berger Group Inc.
Concessionaire : HKR Roadways Ltd.
EPC Contractor : Megha Engineering & Infrastructures Ltd.

METHOD STATEMENT FOR CONSTRUCTION OF PIPE CULVERTS Rev.


: 0 W.e.f: 03-03-2011

Page 7 of 7

iii. Disposable materials would not be dumped into streams or


unauthorized
areas. Every effort would be made not to disturb prevailing
surface
water runoff.
iv. All necessary measures and precautions shall be taken to
avoid any
nuisance or disturbance arising from the execution of the
work.

You might also like