1 Scope............................................................. 2
2 Conflicts and Deviations................................. 4
3 Definitions....................................................... 4
4 Applicable Documents.................................... 9
5 Purpose........................................................ 11
6 Responsibilities............................................. 11
7 Authorization Requirements......................... 26
8 Authorization Procedures............................. 26
9 Marking and Identifying RVs......................... 27
10 Rupture Disks (RD) and Rupture Pins (RP). 28
11 Spare RVs.................................................... 28
12 Pressure Testing RVs.................................. 29
13 Mothballed RVs............................................ 30
14 Test and Inspection Interval Determination.. 31
15 Surge Relief Valves (SR).............................. 31
1 Scope
1.1 This engineering procedure defines the approval and authorization requirements
for the identification, installation, addition, deletion, replacement, mothballing
and maintenance of Saudi Aramco Pressure Relieving Devices (PRDs).
1.2 Roles and responsibilities and the references used to control and maintain the
RV Program are outlined.
1.3 PRDs covered including safety valves, relief valves, safety relief valves, surge
relief valves, pressure-vacuum relief valves, rupture pins, buckling pins and
rupture disks will be referred to as a 'RV' throughout this procedure.
1.4 This procedure applies to RVs also defined as PZV in SAES-J-600, installed on
fixed, mobile, skid mounted and packaged equipment, except as noted in 1.4.
It also applies to surge relief valves defined as SRV in SAES-J-605.
1.5 This procedure shall also apply to flow modulating, i.e., Ful-Flo or equivalent,
relief valves, providing:
1.5.1 They are the sole relieving device for the system being protected.
1.5.2 They can be tested in-place when an approved In-Place Test Procedure is
used.
1.6 The following are EXCLUDED from the requirements of this Procedure:
Page 2 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
1.6.12 ¼ inch NPT Relief Valves in Well Shut Down (WSD) hydraulic cabinets.
1.8.1 Determine and state clearly whether the RV is in critical service (i.e.,
no redundancy or sparing, service is sour, heavy fouling, or associated
circuit has experienced high corrosion rate and obtain approval of all
below, as applicable:
i) Supervisor Operations Engineering (in operating facility) or
Project Engineer (in projects)
ii) Operations Superintendent (in operating facility) or Senior
Project Engineer (in projects).
iii) Manager of the Operating Department or Sr. Operations’
Representative (in projects).
Page 3 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
1.9 RVs excluded from the RV TRV Tracking Program. Tracking Program shall
meet the following:
1.9.2 the list of RVs in the PM program shall be audited at least once every
3-years by RV Coordinator for completeness and compliance with the
set PM interval.
1.9.4 PM interval once approved, can only be altered with Operating Facility
Manager’s prior approval.
2.1 Conflicts
Any conflicts between this standard and other applicable Mandatory Saudi
Aramco Engineering Requirements (MSAER) or industry standards, codes, and
forms shall be resolved in writing through Chairman, Inspection Engineering
Standards Committee of Saudi Aramco.
3 Definitions
Changes that do not directly affect valve reliability and operation, such as: RV
identical location, installation code, RV type indicators, ISS drawing number,
PZV tag number, and other non-mechanical changes.
Page 4 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Data sheet, for verification of RV design for installation into any Saudi Aramco
facility, which is the permanent record of initial design for approval and changes
of a RV in the Saudi Aramco Relief Valve Program. The approval signatories
are noted on the specific Instrument Specification Sheet (ISS). ISS used for
RVs within Saudi Aramco include:
ISS 8020-605-ENG Instrumentation Specification Sheet – Surge Relief
Valves
ISS 8020-611-ENG Instrument Specification Sheet – Pressure Relief
Valves Conventional & Balanced Types
ISS 8020-612-ENG Instrument Specification Sheet – Safety Relief
Valves Pilot Operated
ISS 8020-613-ENG Instrument Specification Sheet – Pressure –
Vacuum Relief Valves
ISS 8020-614-ENG Instrument Specification Sheet – Rupture Disks
ISS 8020-615-ENG Instrument Specification Sheet – Rupture Pin
3.7 Lost RV
A safety relief device that has been verified to have a SAP database record
assigned to it but cannot be located and is verified to no longer exist in the field.
Page 5 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
The organization that oversees the maintenance work of Saudi Aramco RVs in
Contractor Shops, In-Kingdom.
3.12 Operations
The business line department that is directly responsible for the management of
the facilities with installed RVs.
3.13 Originator
3.14 Projects
Facilities that are under the management of a Project Manager, and not yet
transferred to an Operations Organization by the signing of the Mechanical
Completion Certificate, MCC.
3.15 RV
The generic term used in this procedure and the field when referring to pressure
relieving devices, as defined in the Scope.
Page 6 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
3.16 RV Administrator
3.17 RV Coordinator
The process of authorizing the RV maintenance test data (on the Form
SA-3750-ENG) entered into the RV Tracking Program database of SAP R/3.
This approval is by the local Operations Inspection Unit's RV Coordinator.
Page 7 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
3.28 SAP - CC
3.30 Spare RV
A new or used RV that is a potential replacement unit or can be used for parts.
This is not to be confused with the on-line spare RV.
The generic term used in this procedure and the field when referring to surge
relieving devices, as defined in the Scope of this procedure.
3.32 Test RV
Page 8 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
strength or leakage.
4 Applicable Documents
Page 9 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 10 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
5 Purpose
5.1 Installation, deletion, or changes are approved and accurately recorded in the
corporate SAP system.
6 Responsibilities
6.2 RV Administrator
6.2.4 Approves the RV Work Flow (WF) data entry in SAP R/3 and verifies
it against the attached SA 8020-6XX-ENG, Instrument Specification
Sheet (ISS).
Page 11 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.2.8 Ensures records for Deleted RVs are stored in the SAP system
indefinitely.
6.3.1 Manages the implementation of the SAP R/3 system in Saudi Aramco.
It is comprised of four (4) functional departments namely, SAP
Applications, SAP Computing, SAP Training & Change Management
and SAP Design.
6.3.5 Maintains all SAP transaction codes that may be used in the SAP R3
system for RV tracking system see Appendix C for a sample.
6.4 Engineering
Page 12 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.4.1.5 Enters the RV data into the SAP System using Transaction
Code IE01 with Equipment Category “R” for new RVs or
IE02 for any updates.
6.4.1.10 Ensures the PM02 Work Order is created by SAP R/3 through
Transaction Code ZI0014 after approval of the RV SAP
Authorization WF and sent to the Maintenance Foreman or
Supervisor, RV Test Shop Unit to initiate the field work.
Page 13 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.4.1.16 Ensures units used for PRDs are Standard Units where
requested by proponent management as per SAEP-103.
Page 14 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
under Construction.
6.4.2.8 Ensures that RVTS used for testing PRD in projects meets the
requirements of SAEP-1132.
Page 15 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.4.4 RV Coordinator
6.4.4.5 Investigates why a relief valve has not been tested if the period
following the RV number approval exceeds three months.
6.4.4.6 Ensures that copies of all RV data are scanned and attached to
the SAP Authorization WF for any changes/updates,
approved Form SA-8020-6XX-ENG, current P&ID drawing,
SIS if applicable and MOC as required by this procedure.
Page 16 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 17 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
(DN).
6.4.5.4 Verifies that installed RVs are sealed, in the correct location
as per current verified P&ID, correctly painted and properly
piped to a safe location per SAES-J-600.
6.4.5.5 Verifies that block valves are properly installed and painted,
as per SAES-J-600 and SAES-B-067.
6.4.5.6 Verifies that the isolation valve installed between the remote
pressure gauge and the area being monitored (the area
between the rupture disk or rupture pin and the relief valve) is
locked open.
For remote areas, the Inspection Field Supervisor has the authority to
act on behalf of the Inspection supervisor for the following items:
Page 18 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.4.6.6 Ensures that installed RVs are tagged, sealed, in the correct
location, and piped to a safe location, as required by
SAES-J-600, during annual external inspections by
designated OIU staff.
6.4.6.7 Ensures that block valves are properly installed and painted,
as per SAES-J-600 and SAES-B-067, during annual external
inspections by designated OIU staff.
Page 19 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.5 Operations
Page 20 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.5.2.2 Verifies that the RV location and marking are correct as per
the current verified P&ID.
6.5.2.2 Verifies that inlet and outlet block valves, for active RVs, are
open completely and properly sealed.
6.5.2.4 Verifies that the block valves are painted orange, as required
by SAES-J-600 and SAES-B-067.
6.5.2.5 Verifies that the block valve stems are oriented horizontally
or sloping away down maximum 45 degree from the valve as
per SAES-J-600.
Page 21 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.5.2.9 Initiates Maintenance Orders for the repairs of RVs not Due
for T&I under the Preventive Maintenance system in SAP
and attach the SAP notification with the SA-3750-ENG
maintenance report.
6.6 Maintenance
Page 22 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Commentary Note:
Page 23 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.6.1.17 Maintains and update the RV Test Shop Annual Audit items.
A quarterly report on the status of agreed corrective actions
and ETC (Expected Time of Completion) shall be sent to
local Inspection Unit.
6.6.3.2 Creates maintenance package, plan, and develops task list and
other items related to the PM program for all approved RVs.
Page 24 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
6.6.3.3 Ensures the availability of critical material spare parts list for
PRDs in SAP which are used in proponent facilities.
6.7.2 Audits Contractor facilities annually. Copies of the Audit reports are
to be sent to Operations Inspection Division/Inspection Department,
Dhahran.
6.7.5 Notifies the valve proponent when problems are identified, such as
stuck, dirty, corroded, etc., so that an Engineering decision can be
made prior to release/testing of the valve.
6.7.6 Enters the Relief Valve Maintenance Report data, Form SA-3750-ENG
into SAP system using the SAP transaction QE17. The original Form
SA-3750-ENG is then sent to the proponent to forward to the local RV
Coordinator.
The division head of the Area Loss Prevention Division is to review and concur
with RV in-place testing procedures, as well as on Form SA-2760-ENG
“Approval Request to Deviate from Equipment Inspection Schedule” as required
by SAEP-319.
Page 25 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
7 Authorization Requirements
7.5 Changes that DO NOT AFFECT RV operations require the SAP Authorization
WF approval of the Supervisor of Operations Engineering, and should be
reviewed by the local RV Coordinator and Supervisor of the Operations
Inspection Unit.
7.6 Deletion of an existing Relief Valve number can only be authorized through
SAP Authorization WF and only when the equipment being protected has been
permanently dismantled, when the existing RV is to be replaced or if the RV is
lost.
7.7 When a deleted RV is to be replaced with another RV, authorization for the new
RV should be completed through SAP Authorization WF and a new RV number
assigned, prior to deleting the old RV.
8 Authorization Procedures
Page 26 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
8.2 RV Deletion in SAP is only authorized when the equipment being protected is
dismantled, the RV function is no longer required, or the RV is lost.
8.3.2 Immediately remove the old RV number stamped in the field and
stamp the new RV number on the location new RV number. Test, set,
seal, and tag in accordance with SAEP-319.
9.1 Each RV shall be identified by attaching a corrosion resistant metal tag FIRMLY
secured by a 16 gage stainless steel wire. Tags are available from storehouse
stock (SCM SAP Stock # 1000168143). For rupture disks and rupture pins, attach
the tag to the holder. (Galvanized metal tags should not be used).
9.2 The tag shall be die stamped with the following in the same units:
RV number ___________
CDTP ___________
9.3 The Due Date on the RV tag equals to the Planned Date which is designated
automatically by SAP system based on the last test date. This represents the
date at which the next T&I is due for a RV based on the specified interval.
9.4 The RV number, as described in tag requirements, shall be die stamped on the
body of screw type valves. The RV number shall be stamped on the outlet
flange of flanged RVs. Stamping the mating pipe flange or installing a field RV
number tag is recommended to avoid installation errors.
9.5 The mounting flange of a rupture disk or a rupture pin holder shall be die
Page 27 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
9.6 The bonnets of all bellows type RVs shall be painted GREEN, per SAES-B-067.
This is to indicate that the bonnet must be vented and the vent piping is to be
directed away from other equipment or walkways.
9.7 All other RVs shall be painted with the mandatory aluminum color, as per
SAES-B-067.
10.1 Rupture Disks and Rupture Pins installation shall be per SAES-J-600.
10.2 The Authorization Procedure for Rupture Disks and Rupture Pins is the same as
for all other RVs.
10.3 The Authorization Procedure for Series Rupture Disk requires approval by
creating SAP Authorization WF through Transaction Code IE01 for both the
Rupture Disk and the reclosing Relief Valve. Both Relief Valve Authorization
Forms shall be accompanied by the approved Instrumentation Specification
Sheets (ISS), Forms SA-8020-6XX-ENG, showing the capacity calculations,
and conformance to ASME SEC VIII D1 as per SAES-J-600.
11 Spare RVs
11.1 The RV Tracking Program recognizes the following (RV SPARE types).
11.1.2 An Off-line spare RV that is used for a specific location (to be moved to
the designated “spare” Functional Location, entry code is OFSP in SAP).
11.1.3 A General use spare RV that can be used in different locations. See 11.5.
The entry codes (i.e., INIS, OFSP) for INSTALLATION/SPARE CODE shall be
selected from the User Status menu for spare RV in SAP system.
11.2 SPARE RVs may serve as extra open stock, assigned replacement RVs (e.g., an
extra superheater replacement safety valve), or for parts. The use determines
how it is controlled in the database.
11.3 SPARE RV which is cannibalized for parts shall be deleted from the SAP
system. The SPARE PARTS RV shall be stored in the RV Shop inventory, and
Page 28 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
11.4.1 The SAP system shall reflect the Installation/Spare Code status by
entering the appropriate spare code in SAP - INSTALLATION/SPARE
CODE field (i.e.; INIS, OFSP). See SAEP-1131.
11.5 SPARE RVs in open stock (General use) are used RVs that are maintained in the
Shop inventory with no service assigned. The Data Base record and number are
kept current, the RV is put on Mothball status, and the RV should be moved to
the designated spare Functional Location. The Relief Valve should generate a
SAP Authorization WF through Transaction Code IE02 by selecting “SDEC” -
Awaiting Deactivate to complete the “change” authorization.
When an open stock SPARE is to go into service it shall meet all the
requirements of this procedure.
12.1 Each RV shall be assigned with a serial number for tracking and record purposes.
Page 29 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
12.2 Each RV shall have a history log file in SAP. This file should include the RV
Engineering data, and components (i.e.; spring), changes and updates.
12.3 TEST RVs used for PRESSURE TESTING shall be identified with a corrosion
resistant metal tag, as described within this SAEP, and stamped as follows:
“TEST RV”
12.5 The TEST RV shall not have a data base RV number assigned to it.
13 Mothballed RVs
13.1 A RV in a mothballed facility shall remain in SAP system under Relief Valve
equipment category.
13.3 The Maintenance Plan (Maintenance Order) shall be put on “INAK” status,
i.e., Inactive, by the responsible Plant Maintenance Plan Processor.
Page 30 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
15.1 The selection, sizing and installation of surge relief valves shall be in
accordance with SAES-J-605.
15.2 The Authorization procedure for surge relief valves is the same as for all other
RVs. Surge Relief valve is tracked as a RV in SAP system under “R” category
and is identified as “SR” in the equipment data record of SAP.
15.3 The Authorization procedure for single or multiple installations of surge relieving
devices requires approval by creating SAP WF through Transaction Code IE01.
The relief Valve Authorization SAP WF shall be accompanied by a certified and
approved Instrumentation Specification Sheet (ISS), Form SA-8020-605-ENG,
showing the capacity calculations as stipulated in SAES-J-605.
Revision Summary
11 June 2015 Revised the Next Planned Update, reaffirmed the content of the document, and reissued as
major revision.
Page 31 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 32 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
B-E. Effect of change in user status of RV equipment master during active workflow.
Page 33 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 34 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 35 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 36 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 37 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 38 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 39 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 40 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
IE02
Go back to
Approver 3 Continue
IE02
Workflow is
Approver 4 terminated
Page 41 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Role : 04 Engineer
TRANSACTION TASK
Role : 35 RV Coordinator
TRANSACTION TASK
ZI0127 Maintain RV Workflow Approvers by Cost Center, Plant for a Project or Non-Project
Role : 19 Maintenance
Transaction Description
Page 42 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 43 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
RV HANDLING:
Question 1. Is there any type of protection being provided to RV's flanges, threads, and nozzles during
transporting and handling to and from the maintenance shop?
Question 2. Are RV's at Yanbu NGL Maint. RV shop received and shipped in the vertical position?
Question 3. Is the RV permanent No. stamped on the flange or body of each relief valve maintained at
Yanbu NGL Maint. RV shop.
Question 4. Is every RV identified by an attached corrosion resistant metal tag with full information per
SAEP-318 paragraphs 9.1 and 9.2?
Question 5. Is manufacturer's nameplate found on each RV being received at Yanbu NGL Maint. RV shop?
Is the nameplate information maintained in the files? Is the shop using some method to identify
valves that may contain hazardous products?
Question 6. Is maintenance reporting discrepancy in tested RVs? Are comments being entered in SAP as
required?
Question 7. Is there a permanent record file including (ISS, SA-3750, memos, letters, etc.) for each RV that
comes to Yanbu NGL Maint. RV shop for maintenance?
Question 8. Is there an approved quality assurance (QA) manual for Yanbu NGL Maint.? RV shop? Is the
manual updated?
Question 9. Does Yanbu NGL Maint. RV shop have an up to date and complete reference library at the
testing shop for servicing RV's including:
1. Manufacturer's service manuals for each type of RV serviced
2. QA Manual
3. RV's SAEPs and SAESs.
4. Related industry standards (ASME and API)?
Question 10. Is there any verification carried out to assure that RV design description and tag number
conforms to the RV test shop files and SAP and the body identification stamp before testing or
repairing begins?
SAFETY PRECAUTIONS
Question 11. Is there any type of noise suppression being used at Yanbu NGL Maint.? RV shop to maintain
safe working conditions?
Question 12. Is the air-service RV test bench used at Yanbu NGL Maint.? RV shop designed in accordance
with RV's SAEP specifications? Is the Test Stand approved by Inspection Department? Is there a
Page 44 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
SIS or design sheet to support the design pressure calculations? Is there a protecting RV on
stand?
Question 13. Is the liquid-service test stand at Abu NGL Maint.? RV shop per the minimum design
requirements of RV's SAEP?
Question 14. Is RV disassembly and testing carried out by, or under the supervision of, a qualified and
certified RV technician (s)?
Question 15. Are there written shop procedures that detail the steps involved for each type of RV services
presently used by Yanbu NGL Maint. RV shop?
Question 16. Are RV tested with the correct test medium i.e.; air for air-service RVs and liquid for liquid-
service RVs?
Question 17. Is each RV disassembled at every third consecutive RV operating interval or when indicated on
PM schedule?
Question 18. Is an initial visual inspection carried out by the RV testing personnel to evaluate the overall
condition of the RV against corrosion, scale, obstructions, and obvious damage before
conducting the “As Received” pop test? What action will be taken, if any?
Question 19. Is “As Received” pop test conducted for each RV serviced at Yanbu NGL Maint. RV shop?
Question 20. Is “ As Received” seat leak test conducted immediately after pop test?
Question 21. Is a bellows leak test carried out to verify that the bellows sealing joint is 100% effective and the
bellows are not leaking?
Question 22. Is there a RV sealed bonnet leak test being performed at Yanbu NGL Maint. RV shop?
Question 23. Is there any procedure being followed at Yanbu NGL Maint. RV shop to identify or classify
dismantled parts of RV being tested?
Question 24. Is there a written lapping procedure for seats and discs that describe lapping compound, lap ring
and lapping machine use and calibration practiced by Yanbu NGL Maint. Shop?
Question 25. Is each RV tagged and sealed immediately upon final setting?
Question 26. Is a RV maintenance report, form SA-3750, prepared for each RV for entry into the database?
Are copies in the files?
Question 27. Is the SA-3750 report form completed during the maintenance work by the RV technician
performing the work? Who approves the test data?
Question 28. Are bonnets of all the bellows type RV received at Yanbu NGL Maint? RV shop painted green?
Question 29. Are all the non-bellows type RVs painted the aluminum color per SAES-B-067 para. 4.1.1?
Page 45 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Question 30. Are there “test” RVs for pressure testing purposes, with associated service and design records,
maintained at Yanbu NGL Maint. RV shop?
Question 32. Is there an inventory of “spare” RVs and their records maintained at Yanbu NGL Maint?
RV shop?
Question 33. Are there a shop inventory for spare parts RV (cannibalized), and a complete file maintained for
spare parts? Are they identified by manufacturer & part number?
Question 34. Is there any RV field identification followed to avoid installation errors?
RV TECHNICIAN
Question 35. If the technicians are certified, who certified them? Was the evaluator a third party person?
Question 36. Do the RV technicians meet the education and experience levels required?
MISCELLANEOUS
Question 37. Are air filters used and cleaned periodically to remove any dirt or moisture from the air system?
Question 38. Are test stand pressure gauges calibrated? Is there a logbook? Are they identified with a tag as to
who calibrated the gauge?
Question 40. How does the shop ensure that the RVs when tested are corrected for temperature or
backpressure?
Page 46 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Page 47 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
Please find attached Yanbu NGL Fractionation Department (YNGLFD) Relief Valve (RV) SAP Report for
March 2015 that shows Zero Overdue RV Testing; hence, YNGLFD safely achieved Eighty-Eight (88)
consecutive months with Zero Overdue RVs.
YNGLFD RV Standard and Excellence KPI were successfully accomplished during this month by testing the
Forty (40) scheduled RVs before the 25th day of the month.
On the other hand, below table reflects the findings of the Monthly Review of RV Data in SAP and indicates
the required actions and the assigned organizations (see attachment for more details).
EIU would like to thank all parties involved in maintaining Zero Overdue RV Testing at YNGLFD and urges
timely attending the above tabulated findings for RV Data in SAP.
Should you have any inquiry, please call Nawaf al Jodaibi at 397-4392 or the undersigned at 397-4670.
Page 48 of 49
Document Responsibility: Inspection Engineering Standards Committee SAEP-318
Issue Date: 11 June 2015 Pressure Relief Valve Program
Next Planned Update: 11 June 2018 Authorization for Installation, Deletion, and Changes
NSJ:nsj
Letter Book
This SAP Report shows Zero Overdue RV Testing for the Month of March 2015, however all
RVs in this report with previous month plan date are supported by deviation requests.
Page 49 of 49