PharmaEng CreamProduction PDF

You might also like

You are on page 1of 9

Reprinted from

PHARMACEUTICAL ENGINEERING®
The Official Magazine of ISPE Batch Process Simulation
July/August 2006, Vol. 26 No. 4

This article
describes the Debottlenecking of a Batch
use of a batch
process Pharmaceutical Cream Production
simulator in the
modelling and
debottlenecking by Jully Tan, Dominic Chwan Yee Foo,
of an anti- Sivakumar Kumaresan, and Ramlan Abdul Aziz
allergic cream
production line
at an existing
pharmaceutical
facility.

C
Introduction the current production rate as the production
omputer Aided Process Design (CAPD) capacity was limited by the current operating
and simulation tools have been widely condition and equipment setup. Hence, a
used in the bulk and petrochemical debottlenecking study is needed for an increase
industries since the early 1960s. It in production. In addition, the debottlenecking
involves the use of computers to perform steady- study will assist the management team in fu-
state heat and mass balancing as well as sizing ture expansion plans.
and costing calculations for a process.1 How-
ever, the use of these CAPD and simulation Background Theory
tools has only emerged in pharmaceutical In order to increase production throughput,
manufacturing in the past decade.2-8 Compared process bottlenecks that limit the current pro-
to the readily available process simulators in duction need to be identified. Bottlenecks are
the bulk and petrochemical industries, there process limitations that are related to either
are only a limited number of simulators avail- equipment or resources (e.g., demand for vari-
able for pharmaceutical process modelling. This ous utilities, labor, and raw material). Hence,
situation is mainly due to the uncommon unit process debottlenecking can be defined as the
operations and the batch operation nature of identification and removal of obstacles in the
pharmaceutical processing. Due to its rela- attempt to increase the plant throughput.5 In
tively new emergence, more work needs to be batch manufacturing, two types of process
done in this sector. bottlenecks can be categorized. These are the
Due to the increasing customer demand of equipment capacity-related size bottleneck (an
the anti-allergic cream product, the pharma- equipment that is limited in size) as well as the
ceutical facility management team was looking scheduling bottleneck (due to the long occu-
for alternative expansion schemes to increase pancy of a piece of equipment during a process).

Figure 1. Base case


simulation flowsheet for
the production of anti-
allergic cream.

©Copyright ISPE 2006 JULY/AUGUST 2006 PHARMACEUTICAL ENGINEERING 1


Batch Process Simulation
The ability to identify and remove process bottlenecks that mum production. However, this is often not the case. All
create obstacles in a manufacturing process will increase process equipment will normally feature different utiliza-
plant throughput and fulfill customer needs. tion. The ability to raise utilization of the equipment will
A good tool to identify batch process bottleneck is via a help in raising process throughput. The processing step
throughput analysis study. Throughput analysis measures with the highest combined utilization is normally identi-
the equipment utilization in a batch process with two vari- fied as the first candidate for process debottlenecking.
ables, i.e., the capacity utilization and equipment uptime.5-6 Simulation tools that are capable of tracking capacity
Capacity utilization is defined as the percentage of the utilization and equipment uptime can facilitate the iden-
current operating load of a piece of equipment (e.g., vessel tification of process bottlenecks and the development of
volume for a reactor or filtering area of a filter) relative to its the scenarios for process debottlenecking. By using the
maximum load. For instance, a vessel with 100% capacity “what if” scenario, process alternatives can be simulated
utilization means that its current content has reached its via the use of simulation tools to reveal potential candi-
maximum level. dates for the debottlenecking study.
Equipment uptime measures the effectiveness of a piece of The Cost Benefit Ratio (CBR) is among the criteria that
equipment that is utilized in time. It is given as the percent- can be used to evaluate the economic performance of
age of the equipment utilization time over the plant cycle debottlenecking alternatives. As the name suggests, CBR is
time. For example, a reactor that operates for five hours a measure based on the ratio of benefits obtained for a given
within a plant with a cycle time of 10 hours has an uptime of expansion cost.9 The first step in CBR analysis is to deter-
50%. The product of equipment capacity utilization and its mine the beneficial elements, disbenefits, and expansion cost
uptime defines the combined utilization of the respective for a project. For the case of pharmaceutical process debottle-
equipment.5-6 necking, CBR formulation can be defined as shown in the
In an ideal situation, a plant should have all equipment following equation:
running at 100% combined utilization to achieve maxi-

Figure 2. Operation Gantt Chart for the base case simulation.

2 PHARMACEUTICAL ENGINEERING JULY/AUGUST 2006 ©Copyright ISPE 2006


Batch Process Simulation
Revenue of
Revenue of – current
alternative operation
CBR = __________________________________________ (1)
Investment Operating Operating
cost of + cost of – cost of
alternative alternative current
operations

Model Development –
Antiallergic Cream Production
Figure 1 shows the base case simulation flowsheet for the
production of anti-allergic cream modelled in a process simu-
lator.10 The base case simulation model was developed to
Figure 3. Capacity, time and combined utilization for unit
reflect the actual operating condition in the existing pharma-
procedures in base case simulation.
ceutical manufacturing facility that is operated in batch
processing mode. This modelling environment, involves the blended product is next transferred to Filler P-5/FL-101 in
modelling of a few operations that take place sequentially in the Packaging Section where it is filled into the tubes of 15 g
a single unit procedure.10 For instance, the Jacketed Heater each. The existing filling machine is operated at a speed of 30
procedure P-1 in the Pre-Mixing section - Figure 1 was used tubes/min. The tubes are then sent to the cartoning packag-
to model the sequential operations of raw material charges, ing procedure P-7 (using a belt conveyer P-6/BC-101) where
material heating (for melting purpose), agitation processes, the anti-allergic cream in tubes are packed manually by two
as well as product discharge. All these individual operations operators into the tube cartons, each at a speed of 20 cartons/
took place in the single vessel of V-101. The modelling of these min. Next, 12 cartons of anti-allergic cream are packed into
single operations is described next. one wrapper in the Shrink Wrapper (P-8/GBX-101) with a
In the base case process, there are nine major processing speed of five wrappers/min. Finally, six wrappers are packed
steps in three different sub-sections. This includes raw into each of the pallet boxes in Packing Machine P-9/BX-102
material melting in the Pre-Mixing Section, deionized (DI) (equivalent to 72 tubes/pallet box) before they are sent to the
water heating, and material blending in the Main Blending warehouse. Approximately six sealed pallet boxes are packed
Section, as well as filling, conveying, cartoning, shrink wrap- per minute by the operator manually.
ping, and shipment packaging in the Packaging sections. Due As the manufacturing process is carried out in a batch
to the capacity limitation of the pre-mixing vessel, the raw operation mode, efforts have been made to document the
material is divided into two sub-mix batches in the Pre- scheduling details of each processing step. The Operation
Mixing Section. Two batches of Emulsifying Wax (ESW) and Gantt Chart for the complete recipe of a single batch opera-
Foam Stabilizer (FS) are independently heated in the heating tion is shown in Figure 2. It also should be noted that the
procedures P-1 (carried out in Jacketed Heater V-101) and P- process time for certain operations are dependant upon other
2 (in Jacketed Heater V-102) to approximately 100ºC before operations of other procedure (e.g., transfer-out operation in
the emulsifier (EMUL) and ointment (OIN) are added. The P-4 is set equal to the filling duration of P-5). Hence, the
emulsifier and ointment are originally in wax form and need duration of this slave operation is set to follow to the duration
to be melted for uniform mixing. All raw materials are of the master operation using the Master-Slave Relationship
charged at room temperature. function.10 The customer demand for this anti-allergic cream
DI water is heated in the electric heater EH-101 (proce- product is expected to rise another 150% of the current
dure P-3) before being transferred into the Main Blending production capacity in upcoming years. However, the process
Tank, V-103 (P-4) in the Main Blending Section. An Antimi- is currently running at its maximum capacity and any at-
crobial Agent (AM) is next added into the hot DI water, tempt to increase production is not possible due to the process
followed by agitation for 10 minutes. The mixture in the bottleneck. This calls for a systematic procedure to analyze
jacketed heater V-101 and V-102 is then transferred into V- the current production facilities and next to debottleneck the
103. The mixture of all ingredients in V-103 is blended once process. Apart from debottlenecking the current production,
more for 15 minutes in order to produce a uniform composi- the debottlenecking study also will develop solutions for
tion. The mixture is then left in an air-conditioned dispensing future expansion.
room to be naturally cooled to room temperature. This cooling
operation took approximately 19 hours to accomplish due to Bottleneck Identification Strategies
the slow rate of natural cooling. Upon the completion of the In the current operation, the annual operating time for the
cooling operation, the Active Ingredient (AI) of the anti- anti-allergic cream manufacturing is taken as 2080 hours,
allergic cream is finally added. The products are once again which is based on 52 operation weeks, five days a week and
blended for 15 minutes to obtain uniform composition before eight hours operation per day. From the base case simulation,
the product mixture is sent to the Packaging Section. a complete batch of pharmaceutical cream production is
Upon the completion of the Main Blending Procedure, the found to have a process batch time of 40.2 hrs and a minimum

©Copyright ISPE 2006 JULY/AUGUST 2006 PHARMACEUTICAL ENGINEERING 3


Batch Process Simulation
Economic Parameters Base Case Scheme 1 Scheme 2 Scheme 3 Scheme 4 Scheme 5
Batch Production (tubes/batch) 13,333 13,333 13,333 13,333 13,333 13,333
Plant Batch Time (hour) 40.2 41.7 26.2 23.3 27.7 24.8
Minimum Cycle Time (hour) 29.0 21.6 15.0 12.0 9.9 7.6
Number of Batches/year 66 87 121 147 173 215
Annual Production (tube/yr) 880,000 1,160,000 1,613,300 1,960,000 2,306,600 2,866,600
Cost of Investment ($) - 10,000 255,000 555,000 265,000 565,000
Annual Operating Cost ($) 947,200 1,310,000 1,432,700 1,536,000 2,167,200 2,393,500
Unit Production Cost ($/tube) 2.30 1.13 0.89 0.78 0.94 0.83
Annual Revenue ($) 2,200,000 2,900,000 4,033,000 4,900,000 5,766,700 7,166,700
Gross Margin 57.0 54.9 64.5 68.7 62.7 66.6
Cost Benefit Ratio (CBR) - 1.88 2.47 2.36 2.40 2.47
Table A. Throughput and economic evaluation of base case study and various debottlenecking schemes.

cycle time of 29 hrs - Figure 2. The minimum cycle time of the option at the present moment. Hence, debottlenecking options
process is defined as the minimum time possible between the will only focus on the reduction of equipment uptime of P-4/V-
start of two consecutive batches. It is equal to the longest 103. This is described in the next section.
occupation time among all pieces of equipment involved in
this process.10 In the case of anti-allergic cream manufactur- Debottlenecking Schemes
ing; the minimum cycle time corresponds to the prolonged After identifying the candidate for process debottlenecking,
cooling operation in the Main Blending procedure P-4. With the feasibility of various debottlenecking schemes were evalu-
an interval of two hours for tank cleaning between batches, ated. Five debottlenecking schemes were analyzed in which
this sets the plant annual production at 66 batches. The all schemes were applied focusing on reducing the equipment
throughput of the base case is summarized in Table A (col- uptime of P-4/V-103 as the process time bottleneck.
umn 2). The simplest option to increase the process through-
put by increasing daily operating duration is determined to Alternative Debottlenecking Schemes
be uneconomical due to the high operating cost in hiring Figure 4 shows the simulation flowsheet for debottlenecking
additional staff. This leads us to explore the use of combined Scheme 1. As shown, a new intermediate tank V-104 is
utilization concept as has been discussed earlier. installed after the Main Blending vessel. The main rationale
Figure 3 displays the capacity, time, and combined utiliza- underlying this scheme is to reduce the equipment uptime of
tion of all the procedure/equipment pairs in the base case Main Blending vessel (P-4/V-103), by spending a minimal
simulation. As shown, the Main Blending Procedure P-4 (V- investment cost of US $10,000 (purchase cost for V-104). By
103) with an equipment capacity utilization of 89.9% and the adding the intermediate tank V-104, the two subsequent
equipment uptime of 93.6% has a much higher combined procedures P-4/V-103 and P-5/FL-101 are disconnected. The
utilization percentage of 84.1% as compared to other proce- Transfer-Out operation in P-4/V-103 is no longer constrained
dures. The high equipment uptime of this procedure is mainly by the slow filling operation in Filler P-5/FL-101. Upon the
due to the long cooling operation (19 hours) and Transfer-Out completion on the blending operations in P-4/V-103, the
operation (8.4 hours). This also makes P-4/V-103 the sched- product mixture is transferred into the newly added V-104 for
uling bottleneck of the process, i.e., process with longest temporary storage while waiting for the filling operation to
operating duration (see Operation Gantt Chart in Figure 2). complete. The main blending procedure can then be carried
Note that certain procedures (e.g. Filler P5/FL-101, Belt out for a subsequent operation. Simulation results showed
Conveyer P-6/BC-101, etc.) are not considered as size bottle- that the annual production for this scheme has increased to
necks even though they have 100% size utilization, as the 87 batches due to the reduction of minimum cycle time that
operation speed of this equipment can be adjusted according limits the number of annual production from 29 hrs (in the
to the operational needs.5 base case simulation) to 21.6 hrs (shown in the third column
After identifying the Main Blending Procedure P-4 (V-103) in Table A). This corresponds to an increase of annual
as the first process bottlenecking candidate, debottlenecking production rate of 32%, but is insufficient to fulfill the
strategies will next be focused on reducing either the size or projected customer demand.
time utilization of this procedure/equipment. However, since Scheme 2 for process debottlenecking is shown in Figure 5.
there are two pre-mixing tanks that serve as the mixture It focuses on the reduction of cooling operation of P-4/V-103
preparation proceeding to P-4/V-103, any attempt of changing instead. A multifunctional blending tank with a cooling
a larger Main Blending vessel will lead to the replacement of system (purchase cost of US $255,000) is installed to replace
the two pre-mixing tanks V-101 and V-102. This has been the main blending tank. This reduces the cooling time of the
determined by the management team to be an infeasible product mixture from the current 19 hours to five hours.

4 PHARMACEUTICAL ENGINEERING JULY/AUGUST 2006 ©Copyright ISPE 2006


Batch Process Simulation

Figure 4. Debottlenecking Scheme 1 with the installation of an intermediate tank.

Chilled water is used as cooling agent to cool the mixture from purchase cost of $300,000) is installed in addition to the new
85ºC to room temperature. This leads to the reduction of multifunctional blending tank in Scheme 2 to accelerate the
minimum cycle time to 15 hrs. Hence, an increase of 83.3% is filling rate. Simulation results showed that with the reduc-
achieved for annual production as compared to the base case, tion of Transfer-out duration in P-4/V-103, combined utiliza-
i.e., from 66 to 121 batches (fourth column in Table C). From tion values of P-4/V-103, P-5/FL-101 and P-6/BC-101 have
Table B, it is shown that even although P-4/V-103 remains as been reduced slightly, while other unit procedures increase in
the overall process bottleneck, its combined utilization value their combined utilization values - Table B. The net result is
has actually been reduced from 84.2% in the base case the reduction of minimum cycle time to 12 hrs and an increase
simulation to 79.3%, due to the reduction of its uptime. On the annual production rate of 147 batches, i.e., 122.7% compared
other hand, combined utilization of other unit procedures to the base case (fifth column in Table A).
have increased significantly. This leads to an overall increase Another debottlenecking alternative focusing on reducing
of process throughput. Further debottlenecking can only be the overall uptime of P-4/V-103 is presented in Scheme 4 -
achieved if the long duration of the Transfer-out operation in Figure 7. Instead of installing a new filling machine as in
P-4/V-103 (to filler P-5/FL-101) can be reduced. Scheme 3, an intermediate storage tank (V-104; purchase
Figure 6 shows the simulation flowsheet of Scheme 3 that cost of US $10,000) is added in addition to the installation of
explores the reduction of P-4/V-103 uptime from a different a new Blending Tank (P-4/V-103). This scheme exhibits the
perspective. As the Transfer-Out duration of P-4/V-103 is same characteristics as the combination of Scheme 1 and
dependent upon the filling rate in P-5/FL-10, one alternative Scheme 2. Simulation results showed that the annual pro-
to reduce the duration of Transfer-Out operation in P-4/V-103 duction for this scheme is 173 batches with a minimum cycle
is to install a high speed filler to shorten the filling duration time reduced to 9.9 hrs (sixth column in Table A). This
in P-5/FL-10, and hence the Transfer-out duration in P-4/V- corresponds to an increase of annual production rate of 162%,
103. As shown in Figure 6, a new filler (50 tubes/min; fulfilling the future market demand. It also should be noted

Equipment Tag Procedure Name Base Case Scheme 1 Scheme 2 Scheme 3 Scheme 4 Scheme 5
V-102 P-2 Jacketed Heater 2 4.71 6.19 8.59 10.41 12.26 16.00
V-101 P-1 Jacketed Heater 1 8.04 10.56 14.66 17.76 20.92 27.30
V-103 P-4 Main Blending Tank 84.12 82.30 79.34 77.11 57.27 79.13
FL-101 P-5 Filler 27.13 35.65 49.48 38.81 70.61 56.81
BC-101 P-6 Belt Conveyor 23.90 31.41 43.60 31.68 62.21 46.38
BX-101 P-7 Manual Cartoning 17.93 23.56 32.70 39.60 46.66 57.97
GBX-101 P-8 Shrink Wrapping 11.95 15.70 21.80 26.40 31.10 38.65
BX-102 P-9 Manual Pallet Packaging 1.66 2.18 3.03 3.67 4.32 5.37
Table B. Combined utilization for different debottlenecking schemes.

©Copyright ISPE 2006 JULY/AUGUST 2006 PHARMACEUTICAL ENGINEERING 5


Batch Process Simulation
Raw Material Symbol Price ($/kg) Unit/Batch Cost/Batch ($) Annual Cost ($) % Contribution
Emulsifier EMUL 15.50 30.00 kg 465.00 30,690.00 11.15
Emulsifying Wax ESW 5.05 3.60 kg 18.18 1,200.00 0.44
Foam Stable FS 3.00 14.40 kg 43.20 2,851.00 1.04
Antimicrobial Agent AM 4.00 0.24 kg 0.96 63.00 0.02
Active Ingredient AI 650.00 2.00 kg 1,300.00 85,800.00 31.17
Emulsifying Ointment OIN 15.00 12.00 kg 180.00 11,880.00 4.32
Deionized Water DI water 0.50 137.76 kg 68.88 4,546.00 1.65
Water Water 0.03 69.63 kg 2.09 138.00 0.05
Tube Tube 0.10 13,333.00 1,333.30 88,000.00 31.97
Carton Box Small box 0.05 13,333.00 666.65 44,000.00 15.98
Pallet Box Big box 0.50 185.00 92.50 6,110.00 2.22
TOTAL COST 3,635.44 239,939.06 100.00
Table C. Cost of raw material for base case simulation.

that after the installation of intermediate storage tank V- the presence of the additional intermediate tank and the high
101, filler P-5/FL-101 has became the unit procedure with the speed filling machine, the production increases to 215 batches
highest combined utilization value. As shown in Table B, all per annum, i.e., an increase of 225% with minimum cycle time
unit procedures experienced an increase in their combined reduced to 7.6 hr (seventh column in Table C). The capital
utilization values except that of P-4/V103. This is consistent investment needed in this scheme is calculated as the sum-
with the finding of Koulouris et al,5 where new bottleneck mary of individual equipment in the previous schemes, i.e.
equipment will emerge after the current bottleneck is over- $565,000.
come. Debottlenecking efforts are stopped at this scheme as All the proposed debottlenecking schemes have demon-
the debottlenecking objective is reached, i.e., achieving the strated significant improvement on the annual production
150% increase in production as compared to current produc- throughput. This is mainly due to the reduction of minimum
tion. However, to cater for future expansion plan as re- cycle time associated with main blending tank procedures. As
quested by the management team, the replacement of a new previously mentioned, Scheme 4 serves as the debottlenecking
P-5/FL-101 is studied in the next debottlenecking scheme. scheme for current increase of production; while Scheme 5
Figure 8 shows the simulation flowsheet for Scheme 5, with the highest process throughput is reserved for future
which includes filler P-5/FL-101 for debottlenecking. With expansion plans.

Figure 5. Debottlenecking Scheme 2 with the installation of new multifunctional blending tank.

6 PHARMACEUTICAL ENGINEERING JULY/AUGUST 2006 ©Copyright ISPE 2006


Batch Process Simulation

Figure 6. Debottlenecking Scheme 3 with the installation of new multifunctional blending tank and new filler.

Economic Evaluation dominate the raw material cost, each contributing 31% of the
Preliminary economic evaluations are next carried out for the overall production cost. Note that the distribution of raw
base case simulation and each of the debottlenecking schemes. material costs remains the same for all schemes as shown in
This is done via the economic evaluation function of the Table C, only differing by total annual cost for each scheme
simulation software.10 In order to regenerate a realistic cost due to the different annual throughput.
estimate, raw material costs and equipment purchase costs The economic evaluation comparing the various
are obtained from local industrial suppliers. Table C shows debottlenecking schemes with respect to the base case study
the cost of the raw material for the production of anti-allergic is shown in Table A. The Cost Benefit Ratio (CBR) is used as
cream and their contribution to the overall production cost in a tool in comparing the alternative schemes. As shown,
the base case simulation. The active ingredient for the anti- except for Scheme 1, all other debottlenecking schemes are
allergic cream and the tube (where 15 g of cream is filled) having similar CBR values with Scheme 2 and Scheme 5

Figure 7. Debottlenecking Scheme 4 with the installation of intermediate tank and new multifunctional blending tank.

©Copyright ISPE 2006 JULY/AUGUST 2006 PHARMACEUTICAL ENGINEERING 7


Batch Process Simulation

Figure 8. Debottlenecking Scheme 5 for future plant expansion.

having the highest value of 2.47. This indicates that except 4. Ernst, S., Garro, O. A., Winkler, S., Venkataraman, G.,
for Scheme 1 all debottlenecking schemes have equal value Langer R., Cooney, C. L., and Sasisekharan, R., “Process
for investment. Simulation for Recombinant Protein Production: Cost
In the previous debottlenecking section, it is shown that Estimation and Sensitivity Analysis for Heparinase I
Scheme 4 was selected to be the debottlenecking scheme due to Expressed in Escherichia coli,” Biotechnology and Bioengi-
its fulfillment to future customer demand, i.e., by producing neering, Vol. 53, No. 6, 1997, pp. 575-582.
more than 150% of the current production. On the other hand, 5. Koulouris, A., Calandranis, J., and Petrides, D. P.,
Scheme 5 that has been identified to be the future debottlenecking “Throughput Analysis and Debottlenecking of Integrated
scheme also shows a promising CBR value of 2.47. Batch Chemical Processes,” Computers and Chemical
Engineering, Vol. 24, 2000, pp. 1387-1394.
Conclusion 6. Petrides, D. P., Koulouris, A., and Siletti, C., “Throughput
In this work, Computer-Aided Process Design (CAPD) and Analysis and Debottlenecking of Biomanufacturing Fa-
simulation tools are used in the systematic identification of the cilities: A Job for Process Simulators,” BioPharm, August
process bottleneck and a debottlenecking study. An operational 2002, pp.2-7.
pharmaceutical case study of anti-allergic cream production is 7. Petrides, D. P., Koulouris, A., and Siletti, C., “The Role of
used to demonstrate the effectiveness of the tools. The base case Process Simulation in Pharmaceutical Process Develop-
and four debottlenecking schemes are simulated using SuperPro ment and Product Commercialization,” Pharmaceutical
Designer. The annual process throughput is increased signifi- Engineering, Vol. 22, No. 1, 2002, pp. 56-65.
cantly with the reduction of equipment uptime of the process 8. Oh, S. K. W., Kuek, K. H., and Wong, V. V. T., “Design,
time bottleneck. The study produced a debottlenecking scheme Simulation and Optimisation of A Large Scale Monoclonal
that achieves the current production needs, with a scheme that Antibody Production Plant: Upstream Design,” Pharma-
will cater for a future expansion plan. ceutical Engineering, Vol. 24, No. 6, 2004, pp. 42-60.
9. Blank, L. T. and Tarquin A. J., Engineering Economy,
References New York: McGraw-Hill, 2003.
1. Westerberg, A. W., Hutchison, H. P., Motard, R. L., and
10. Intelligen, Inc., SuperPro Designer User’s Guide, Scotch
Winter, P., Process Flowsheeting, Cambridge: Cambridge
Plains: Intelligen, Inc., 2005.
University Press, 1979.
2. Petrides, D., Sapidou, E., and Calandranis, J., “Com-
puter-Aided Process Analysis and Economic Evaluation
Acknowledgement
The authors would like to thank Dr. Alexandros Koulouris,
for Biosynthetic Human Insulin Production – A Case
the Managing Director of Intelligen Europe, for his construc-
Study,” Biotechnology and Bioengineering, 48, 1995, pp.
tive feedback with this project.
529-541.
3. Hwang, F., “Batch Pharmaceutical Process Design and
Simulation,” Pharmaceutical Engineering, January/Feb-
ruary 1997, pp. 28-43.

8 PHARMACEUTICAL ENGINEERING JULY/AUGUST 2006 ©Copyright ISPE 2006


Batch Process Simulation
About the Authors Sivakumar Kumaresan is a lecturer in
Jully Tan is a research student at the Chemi- chemical engineering at the Universiti Ma-
cal Engineering Pilot Plant, Universiti laysia Sabah. He has a BS in chemical engi-
Teknologi Malaysia (CEPP, UTM). She re- neering from Texas A&M University (US),
ceived her BEng degree in chemical engi- an MSc in advanced control from the Univer-
neering from the Universiti Teknologi Ma- sity of Manchester Institute of Science and
laysia and is currently pursuing her MSc Technology (UK), and is currently complet-
research work in CEPP, UTM. She conducted ing his PhD in herbal processing at the Chemi-
her industrial attachment at a local pharma- cal Engineering Pilot Plant, Universiti Teknologi Malaysia.
ceutical production plant where this project is carried out. At His area of work includes the application of process simula-
the plant, she assisted the plant management team to evalu- tion tools to pharmaceutical modelling and he is currently
ate different debottlenecking schemes for various pharma- working on model-based phytochemical processing design
ceutical production processes using computer-aided process and optimization focusing on the standarization of herbal
simulation tools. She can be contacted via e-mail: extracts for pharmaceutical applications. He can be con-
tanjully@yahoo.co.uk or by phone: +60(12)-6670382. tacted via e-mail: shiva@ums.edu.my or shiva@cepp.utm.my,
Chemical Engineering Pilot Plant, Universiti Teknologi by phone: +60(88)-320000 ext. 3064, or by fax: +60(88)-
Malaysia, 81310 Skudai, Johor, Malaysia. 320348.
Chemical Engineering Program, School of Engineering
Dominic C. Y. Foo is an Assistant Professor and Information Technology, Universiti Malaysia Sabah,
at the University of Nottingham Malaysia. Locked Bag 2073, 88999, Kota Kinabalu, Malaysia.
Prior to this position, he served as a Post-
graduate Researcher at the Chemical Engi- Ramlan A. Aziz is a Professor and Director
neering Pilot Plant, Universiti Teknologi of the Chemical Engineering Pilot Plant,
Malaysia (CEPP, UTM), where this work Universiti Teknologi Malaysia. He obtained
was completed. He obtained his BEng, MEng, his BEng and MEng from the University of
and PhD from the Universiti Teknologi Ma- Manchester Institute of Science and Tech-
laysia, all in chemical engineering. His main areas of work nology (UMIST, UK). His main areas of work
include that of process synthesis, analysis, and design for include developing small and medium scale
cleaner production and efficient manufacturing. He makes enterprises in Malaysia through process and
use of computer-aided process design and simulation tools in product development based on natural products and
optimizing and debottlenecking batch manufacturing pro- bioprocessing. He is a member of the Filtration Society of UK
cesses, such as pharmaceutical, fine, and specialty chemical and has served as a Vice President for Institution of Chemical
production. He is a member of the Institution of Engineers, Engineers Malaysia (IChEM). He can be contacted via e-
Malaysia (IEM) and the Institution of Chemical Engineers mail: ramlan@cepp.utm.my, by phone: +60(07)-5531662 or
UK (IChEM) Malaysia Branch, previously known as the by fax: +60(07)-5569706. His Web site is http://www.cepp.
Institution of Chemical Engineers Malaysia (IChEM). He utm.my/.
can be contacted via e-mail: Dominic.Foo@nottingham.edu.my Chemical Engineering Pilot Plant, Universiti Teknologi
or foodominic@ yahoo.com, by phone: +60(03)-89248130, or Malaysia, 81310 Skudai, Johor, Malaysia.
by fax: +60(03)-89248017. His personal Web site is http://
www.geocities.com/foodominic/.
School of Chemical and Environmental Engineering, Uni-
versity of Nottingham Malaysia Campus, Broga Rd., 43500
Semenyih, Selangor, Malaysia.

©Copyright ISPE 2006 JULY/AUGUST 2006 PHARMACEUTICAL ENGINEERING 9

You might also like