You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/4331294

Master Plan for the Electricity Distribution Network of Istanbul European Side

Conference Paper · August 2007


DOI: 10.1109/PESAFR.2007.4498101 · Source: IEEE Xplore

CITATIONS READS
0 2,097

6 authors, including:

Erkut Cebeci Osman Bülent Tör


EPRA Power Systems EPRA
29 PUBLICATIONS   78 CITATIONS    56 PUBLICATIONS   248 CITATIONS   

SEE PROFILE SEE PROFILE

Ulas Karaagac Mufit Altin


The Hong Kong Polytechnic University Izmir Institute of Technology
57 PUBLICATIONS   355 CITATIONS    43 PUBLICATIONS   583 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Smart Grid Controller for PV Network View project

Intelligent system for trading on wholesale electricity market (SMARTRADE) View project

All content following this page was uploaded by Abdullah Nadar on 19 June 2015.

The user has requested enhancement of the downloaded file.


IEEE PES PowerAfrica 2007 Conference and Exposition
Johannesburg, South Africa, 16-20 July 2007

Master Plan for the Electricity Distribution


Network of Istanbul European Side

M. E. Cebeci, O. B. Tör, U. Karaağaç, M. Altın, M. Akdeniz, and A. Nadar


TÜBİTAK-UZAY, Middle East Technical University, Ankara, Turkey

Abstract – This study presents the methodology, studies and voltage level for standardization and dispose the losses on
results of the electricity power distribution system master plan for both 34.5/10.5kV transformers and 10.5kV cable network [1].
the Istanbul City European Side. Mid-term demand projection The master plan study evaluates those regions either has to be
study made for the city based on the historical development, upgraded or remained as 10.5kV.
transformer loading measurements, municipality plans, and
constraints specific to the metropolitan are discussed. A
conservative planning solution for the next 5 years period is
proposed with additional suggestions based on the observations
and experience gained during on-site studies.

I. INTRODUCTION

The ongoing restructuring efforts in all segments of


Turkish electricity sector force all of the state-owned
electricity distribution companies in the country to make
more careful and conservative plans. Boğaziçi Electricity
Distribution Company (Boğaziçi EDC) is among those
companies which have been serving for the electricity
distribution of Istanbul City European Side since 1995. (The
term “Istanbul” will refer to European side of Istanbul Fig. 1. Istanbul European Side Electricity Distribution Regions
throughout the paper.) Supply of the high power demand (Dark regions correspond to urban regions).
increase (~8% average per year) is the main issue to be
solved by the company, particularly in congested In the scope of master plan, first the electricity power
metropolitan regions of the city. According to the current demand projection was performed for the next 5 years. If
regulations, the company has to declare 5-years master plan compared to old city districts (like the well known historical
to the state-owned transmission company, TEİAŞ. The peninsula region), the demand forecast for the developing
pressure on the Boğaziçi EDC regarding planning is due to zones, which are already organized by the municipality, is
the fact that the company is expected to be privatized within obviously rather straightforward. Therefore, the planning
the near future, and essentially, the planning department of approaches for such zones are not considered in this paper
the company concerns for the most economical and reliable which focuses rather on more challenging metropolitan
master plan avoiding to take the responsibility of more regions. Then, in order to ensure that there is adequate
comprehensive planning solutions that require high budget. substation capacity (transformer capacity) and feeder
This paper presents the methodology, studies and results of capacity to meet the load forecasts within the planning
the electrical distribution system master plan project for horizon, alternatives such as procuring transformers,
Istanbul, the largest metropolitan region in Turkey with more building new feeders and new substations evaluated [2].
than 10 million population. Peak power demand of Istanbul
was occurred as ~4GVA in 2005. This demand was supplied II. METHODOLOGY AND STUDIES
through 30 transmission substations (High Voltage/Medium
Voltage (HV/MV) with total capacity of ~6.5GVA (Fig. 1). One of the major concerns with the old city districts of
Total capacity of the transformers installed in the system is Istanbul is the classification of the load type. In several zones,
~9GVA (MV/MV and MV/Low Voltage (LV). Voltage workshops have been located at the basements and initial
levels of both 34.5kV and 10.5kV had been selected as the floors of the residential buildings. Therefore, different types
standard MV levels of the distribution system. Boğaziçi EDC of customers have located at the same buildings.
intends to upgrade the 10.5kV parts of the distribution system Consequently, the residential, commercial and industrial
to 34.5kV level systematically, in order to have a unique loads, whose characteristics are quite different, have merged

1-4244-1478-4/07/$25.00 ©2007 IEEE


gradually. The ratio of the loads should be known in order to metropolitan regions, has almost completely been based on
make a realistic demand projection. Moreover, the lack of the experience of personnel. The geographical placement of
customer database makes the classification and essentially the underground cables has not been recorded to a database
demand forecast issue more difficult. The distribution unfortunately. This dependency on personnel experience
company has a customer database indicating the load type. indispensably affects the fault isolation and restoration
However, it has not being updated regularly by the company. periods. Essentially, the deficiency of such asset database
Therefore, the database ignores the fact that the considerable reduces the electricity supply reliability performance of the
amount of customers has concealed their exact electrical company. In this regard, Geographical Information System
demand characteristic intentionally, in order to take (GIS) is the most essential solution, in particular for the
advantage of residential rates. congested regions of the city.
Another concern is the lack of demand records at the In addition, there is no computerized database that stores
distribution level. Boğaziçi EDC keeps the measurements of asset information regarding the aging, maintenance, etc. The
HV/MV substation transformer loadings for the last ten years. records available at the regional offices and central office of
However, the measurements of the MV/MV and MV/LV the company are personnel specific in general. That is, these
Distribution Transformer Centers (DTC) loadings have not records are not processed and not included to a central
been kept for a period long enough to apply sophisticated database for possible surveys in the future. This deficiency
projection approaches. impediments efficient capital project identification and
In consequence, on-site visits were the indispensable stage selection processes.
in the master plan project, particularly for the congested old Taking into account these issues, a database in MS Access
city districts, due to the reasons some of which are mentioned format was formed and a user interface, which stores the
above. On-site studies involve visits to the DTCs, system data including peak loadings of transformers, supply
measurements of the peak loads, and interviews with the structure (single line diagram), asset details (aging,
representatives of both Boğaziçi EDC and municipality of the manufacturer, substations type, cable cross-section, etc.), was
city to get information about the load characteristics. developed in the scope of the project. In addition, a digital
map that indicates geographical location of the substations
A. On-site studies and feeder routes was developed utilizing ArcGIS software
Parallel work has performed with about 75 people which enables to interrogate the asset database through the
(including engineers and technicians) during on-site visits. All digital map. A snapshot taken from the developed software is
MV/MV substations and more than 5000 DTCs were visited given in Fig 2.
within 3 months. Asset conditions including the substation
buildings and the areas suitable for the possible new
substation buildings were determined during these visits.
Energy meters were installed at all MV/MV substations and
the outgoing feeder loadings were logged during a period of
week to observe the daily load curves and determine the peak
demand intervals of each feeder. Based on the recordings, the
distribution substations that fed from the feeders equipped
with meters were visited to reveal the peak loadings of each
transformer on the feeders.
In addition, the customer profile was classified in terms of
wealth level based on the observations during on-site visits
and interviews with Boğaziçi EDC, the municipality (Istanbul
Metropolitan Planning and Urban Design Centre (IMP),
Prime Ministry Turkish Statistical Institute and Prime
Ministry State Planning Organization (SPO).

B. Asset database Fig. 2. Snapshot from the software developed by TÜBİTAK-UZAY


One of the main issue specific to Turkey in all sectors
including power distribution is the obligatory retirement (due C. Demand projection
to legislation) of highly experienced personnel. It was Energy and peak demand projections were made
observed that the loss of knowledge/experience has decreased regionally based on the customer profile, historical data kept
the performance measures of the company dramatically due to by Boğaziçi EDC, and projections of the IMP and SPO. The
lack of a centralized database. For example, the identification followings are among the most important figures taken into
of a faulted point on an underground cable, in particular at the account during demand projection phase:
a) Load pattern to describe the load behavior (stable or buildings. Moving is still in progress and expected to be
dynamic pattern, cyclic or seasonal or combination, completed by the end of 2008.
system peak time, load type, etc.). Compared to industrial loads, the residential consumption
b) Historical peak load to indicate annual and seasonal will be considerably less such that there will be a drastic
growth, coincidence factor, etc. reduction in loadings of DTCs no: 1352 and 1038. On the
c) Historical energy figures. other hand, the other DTCs’ loadings have already reduced
d) Major factors affecting the system peak including: due to loss of industrial loads that have already moved, and
- Economic and demographic figures, loadings of those DTCs will expected to increase along with
- Bulk loads to be connected to the network soon. the growth in residential buildings shortly. Demand forecast
of the region was performed considering these regional
The regions, where load forecast (or demand projection) specific developments. The results are summarized in Table
studies to be performed, were selected as islands as illustrated 1.
in Fig. 3. The islands were selected in a way such that the
total energy of the DTCs within the islands can be calculated
by the records of energymeters placed on the feeders
(avoiding any confusion due to ordinary operational
maneuvers). The islands in general correspond to the region
fed by DTCs of a loop designed radial operated MV feeder.

Fig. 4. Industrial loads in Bakırköy District

Table. 1. Load forecast of the Bakırköy Region for 2010


Veliefendi Max. Max.
Installed
HV/MV Demand Demand % Increase
Capacity ...
Substation 2005 2010 in 5 Years
(kVA)
1164 Feeder (kVA) (kVA)
Fig.3. Partition criteria of the load forecast area
Dist. Tr. No
Furthermore, load forecasts of DTCs were also performed ... ... ... ... ... ...
taking into account the observations during on-site visits and 1352 1600 1310 ... 917 -30
1038 1600 1280 ... 960 -25
the interviews with the Boğaziçi EDC representatives. The
1344 1000 470 ... 705 50
DTC based demand projection results were compared with
1736 630 300 ... 510 70
the regional demand projection results iteratively. In case of a ... ... ... ... ... ...
conflict between the results, the corresponding forecast was Total 19740 11111 ... 11496.8 3.5
revised together with IMP and SPO representatives. Site
visits had to be repeated in some regions to clarify the
inconsistency between regional and DTC based demand Demand projection was performed for all substations based
projections. on the same approach. Some of the results are summarized in
The following example illustrates the importance of the Table 2. According to the demand projection results, the
DTC based demand projection which necessitates on-site annual increase in total demand of the city is around 7-7.5%
investigations. The DTCs fed from Veliefendi Substation (last raw of Table 2). On the other hand, according to the
through feeder no: 1164 in Bakırköy Region, a small region historical energy figures of the city, annual demand increase
depicted in Fig. 4, have been supplying industrial loads. has occurred around 8% for the last 15 years (excluding the
However, according to recent regulations declared by the major economical crisis and earthquake effects in 1999). In
municipality, these industrial loads were forced to move in this regard, the DTC based demand projection study gives the
order to relieve the region for the growth of residential regional details of the characteristic demand increase of the
city, enabling to determine both optimal investment decisions
at the distribution level as well as the optimal location for the equipped with Supervisory Control and Data Acquisition
new transmission substations. New HV/MV transmission (SCADA) system, which is integrated with a Feeder
substations proposed to be in service within next 5 years are Automation System (FAS) designed specifically to improve
shown in Fig 5. the reliability of electricity distribution system of
metropolitan Istanbul [4]. Master Plan solution proposed in
Table. 2. Transmission substation based demand projection the study considers this design criteria taking into account the
summary
expansion of the envisaged FAS integrated SCADA
2005 2006 2007 2008 2009 2010 application and constraints of the city.
Transmission Max Max Max Max Max Max
Substation Demand Demand Demand Demand Demand Demand When the ratings of the distribution transformers and load
(MVA) (MVA) (MVA) (MVA) (MVA) (MVA) forecast study results were compared, it was observed that the
... ... ... ... ... ... ... existing distribution transformers are not expected to be
ALTINTEPE 82 90.2 108.24 124.47 145.63 163.11
overloaded within next 5 years. Accordingly, there is no need
ETİLER 171 182.97 210.41 235.66 304.02 349.61 to upgrade the capacity of any distribution transformer
TAŞOLUK 55 66 77.88 88.78 97.66 105.47 meanwhile. On the other hand, the MV network capacity
TOPKAPI 160 166.4 171.39 183.53 162.43 167.43 should be enforced in order to mitigate overloadings during
YENİKAPI - - - - - 80.51 contingencies (due to fault) particularly at the 10.5kV system.
... ... ... ... ... ... ... Hence, the planning solution considers the upgrade of some
TOTAL MVA 4036 4326.56 4646.76 4972.14 5330.87 5708.41 10.5kV DTCs to 34.5kV level to relieve the distribution
Annual inc. (7.2%) (7.4%) (7%) (7.1%) (7.2%)
system. The followings are among the major system relieving
solutions proposed in the study.

A. Load sliding
The most practical and economical solution is to
disconnect one (or more) transformer(s) from the feeder
which overloads in case of a contingency, and connect it to a
more convenient feeder, as illustrated in Fig. 6. In the scope
of the project, totally 135 of the distribution transformers in
the metropolitan were proposed to switch to another feeder to
relieve their existing supply feeders.
For congested regions, demand increase will not be due to
new developing areas. Hence a distribution network in the
area already exists. Essentially, load sliding is a more
economical solution compared to others if such a solution is
feasible. Only cabling investments are required to realize the
solution. However there are cases where a convenient feeder
does not exist or cabling route is not allowed to be excavated
Fig. 5. HV/MV Transmission Substations (i. KAYABASI & YENIKAPI
by municipality.
ST are the proposed HV/MV transmission substations, ii. Dark
regions correspond to urban regions)

III. SOLUTIONS TO RELIEVE THE MV-NETWORK

The primary distribution feeder arrangement, as practiced Fig. 6. Feeder load sliding
in the large cities of Turkey, is based upon the simple open-
loop system where the feeder and loop components have B. Split of the feeder
sufficient reserve capacity to serve the load that may be
The second idea is to split the overloaded feeder into two
switched through loop switching (i.e. 50% loading). The
distinct feeders through the most convenient MV substation,
lower limit of the cable size is limited to 95 mm2 Cu because
as illustrated in Fig. 7. Only two of the feeders were proposed
the fault level chosen in the MV distribution systems is 16 kA
to be split due to the constraints of the network including
with the total fault clearing time of 1 sec at most. On the other
physical limitations of the substations (spacing constraints)
hand, as the load densities are high, voltage drop constraints
and too long cabling requirement.
are not critical and loading of cables is thermally limited [3].
Some of the critical feeders at the congested districts are
In upgrading of 10.5kV DTCs to 34.5kV level, the
compact Ring Main Units (RMU) should be the only option
due to building space constraints as the 10.5kV transformer
stations are relatively smaller than regular 34.5kV substations
[3]. The FAS integrated SCADA that already designed for
Fig. 7. Split of the feeder Istanbul requires installment of RMUs as well. Consequently,
the utilization of RMUs in the upgraded DTCs will enable the
C. Feeder installation inclusion of SCADA application without additional
replacement cost in the near future. Therefore, all of the
The most essential option is to install feeder(s) in order to
DTCs to be upgraded to 34.5kV level are proposed to be
relieve the overloaded feeders by switching some of the
equipped with compact RMUs in order to be ready for the
transformers that already supplied by the old feeder(s) to the
expansion of SCADA. The priority of the regions to expand
new feeder(s), as illustrated in Fig 8. The installation of
the SCADA was also determined in the scope of the project.
totally 41 feeders is proposed in the scope of the project
The DTCs closer to the 34.5kV supply rings that already
considering the constraints of DTCs (aging of assets, building
involve SCADA application were determined and given the
size, etc.).
priority.

D. Distributed generation (DG)


Distributed generation is a developing concept with many
applications. Indeed, the employment of DG could provide
several benefits to almost all entities of power systems.
Delaying or avoiding the need for above solutions, improving
the reliability by providing support to the local distribution
network, reducing operation costs, and providing clean
energy by renewable energy sources are among the attributes
of DG for utilization in power distribution systems. However
application of DG to the distribution network of Istanbul will
Fig. 8. New feeder installation encounter various barriers even after the privatization of the
network. These barriers can be categorized as technical,
A reliable medium voltage distribution system is the business practices, and regulatory barriers. Business practices
backbone for a reliable and stable supply with electrical associate with contractual and procedural requirements for
energy. FASs are indispensable to provide reliability system operation and market participation. Regulatory
particularly in metropolitan cities, like Istanbul, where the barriers include matters of policy that usually fall within the
distribution network is sophisticated due to heavily meshed jurisdiction of state utility regulatory commissions (such as
underground cable network with lateral branches to adjacent FERC of USA). These barriers arise from or are governed by
loops. The considerable increase in supply performance statutes, policies, tariffs, and regulatory filings by utilities,
figures of Boğaziçi EDC after the installation of SCADA that which are approved by the regulatory authority. Technical
consists of a FAS verifies this fact. challenges associated with the utilization of DG in
In the scope of determining the most reasonable expansion distribution systems can be divided into three categories: DG
planning of the existing SCADA system, the electricity interfaces with distribution systems, operation and control of
interruption statistics of the distribution network were DG, and planning of DG utilization.
surveyed and the share of planned (for maintenance) and DG brings new challenges to the operation of distribution
unplanned (due to system faults) outages were determined. In system due to its radial topology. Utility requirements of the
metropolitan Istanbul, actually most of the interruptions are DG utilization intend to address engineering compatibility of
due to the infrastructure works of the municipality in DG with the grid and various operational requirements, which
particular during excavation processes (piping, street include specifications for power quality, dispatch, safety,
maintenance, etc.). The main reason is the lagging of reliability, metering, local distribution system, and control
infrastructure development behind the residential issues. For example, DG units could inadvertently energize
improvement due to very high population increase rate. part of the distribution or transmission system when that part
Considering the crowdedness of the city and the traffic jam, of the system is not supposed to be energized. This could
re-energization after faults on MV feeders can take up to one endanger utility personnel and the general public, and damage
hour in certain regions. After the privatization of the company utility or other customer equipment. DG units could cause
the interruptions will become more vital. A duration limit for voltage flickers, harmonics, or other power quality problems
interruptions will be defined with a certain penalty in case of to nearby customers. Multiple DG units operating in parallel
limit violation. could cause stability problems in adjacent power systems.
These concerns manifest themselves in numerous technical
requirements such as the need for utility-grade breakers,
dedicated isolation transformers, and feeder relay
coordination [4].
Given these technical barriers, BEDAS EDC decides to
keep the MV feeders as the passive termination of the
transmission network and allows the connection of DG to the
grid only at the MV side of the HV/MV substations through a
dedicated feeder. Nevertheless, the existing SCADA system
would respond the needs of an active distribution system with
some modifications.

IV. CONCLUSION

Master plan project performed for the Istanbul European


Side Electricity Distribution Network for the next 5 years
period is discussed. The project was carried out for the state-
owned Boğaziçi Electricity Distribution Company which is
expected to be privatized within the near future. Our planning
approach essentially concerns for the most economical and
reliable solutions avoiding comprehensive planning
alternatives that require high budged.
Distribution transformer based demand projections were
performed based on the measurements and observations
during on-site visits, and interviews with planning
departments of municipality. On-site visits were required due
to the lack of updated distribution system database and
dynamic characteristic of residential developments in the city,
as explained in the paper. A geographical information system
based software, which includes an asset database collected
during on-site visits to the transformer substations, was
developed. The software is open for further developments
such as addition of customer management system.
Transformer based demand projection study results enables to
determine not only optimal investment decisions to relieve
the medium voltage network but also the optimal size and
location of the new transmission substations, as discussed in
the paper. Further studies will include technical loss analysis
of the distribution network and reveal of the electricity theft
ratio in total consumption.

V. REFERENCES

[1] N. Ozay, A. N. Guven, A. Buyuksemerci, M. Fettahlioglu, “Design and


Implementation of a Feeder Automation System for Distribution
Networks,” IEEE Power Tech’99 Conference, Aug 1999.
[2] S. K. Khator and L. C. Leung, “Power distribution planning: A review
of models and issues,” IEEE Trans. Power Syst., vol. 12, no. 3, pp.
1151–1159, Aug. 1997.
[3] N. Ozay, A. N. Guven, A. Buyuksemerci, M. Fettahlioglu, “Technical
and Economic Feasibility of Conversion to a Higher Voltage
Distribution”, Generation, Transmission and Distribution, IEE
Proceeding, Vol. 142, Issue 5, Sept. 1995 Page(s): 468 – 472.
[4] O. B. Tor and M. Shahidehpour, “Power Distribution Asset
Management” Proceedings of IEEE PES General Meeting, Montreal,
Canada, June 2006.

View publication stats

You might also like