You are on page 1of 5

PROJECT : MR.

MANJESH'S RESIDENCE- MYSORE

BILL OF QUANTITIES FOR CIVIL WORKS

GROUND FLOOR TOTAL SBA IN SFT -2121

Sl. No. Description of Items Unit Nos L B D Quantity Rate Amount Remarks
1.00 EARTH WORK

Earthwork excavation for the foundation of buildings, water


supply, sanitary lines and electrical conduicts either in pits or
in trenches 1.5m and above in width, in hard soil not
1.01 exceeding 1.5m in depth including dressing and bottom and
sides of pits and trenches, stacking the excavated soil clear
from edges of excavation with lead upto 50m, after breaking
od clods complete as per specifications.

a) Footings Cum 136 - ###


F1 4.00 1.20 1.30 1.50 9.36 1,273
F2 2.00 1.30 1.35 1.50 5.27 716
F3 3.00 1.60 1.45 1.50 10.44 1,420
F4 4.00 1.65 1.80 1.50 17.82 2,424
F5 3.00 1.80 1.90 1.50 15.39 2,093
F6 2.00 2.10 1.95 1.50 12.29 1,671

b) Walls Cum 1.00 80.46 1.00 1.50 120.69 136 16,414


Earth Filling to the sides/pockets to
foundation/flooring/basement in layers of 15cm with
1.02 Selected excavated earth including watering, tampering & Cum 143.44 110 15,778 ###
consolidation to get required procter density as per directions
etc., complete.
Earth filling to the sides/pockets of foundation/flooring/ in
layers of 15cm with approved earth brought from
1.03 outside/supplied by infosys including watering, tamping & Cum R
consolidation to get required procter density as per directions
etc., complete.
Disposal of debris or excavated earth including loading and
1.04 unloading spreading and levelling etc, complete out side the Cum 72 70 5,020
premises.
Removing and clearing the jungle and bushes inside the
1.05 Sqm R
building area
TOTAL EARTH WORK 46,808

2.00 PLAIN CEMENT CONCRETE


Providing and laying in position plain cement concrete of mix
M7.5 with OPC cement @180kgs, with 40mm and down size
garded granite metal coarse aggregates @0.85cumand fine
aggregates @0.57cum machine mixed, machine
2.01 -
mixed,concrete laid in layers not exceeding 15cms, thick,well
compacted,in foundation and plinth,including cost of all
materials, labours,HOM of machinery, curing complete as per
specifications.
a) Footings Cum - 4,763 -
F1 4.00 1.30 1.40 0.10 0.73 3,467
F2 2.00 1.40 1.45 0.10 0.41 1,934
F3 3.00 1.70 1.55 0.10 0.79 3,765
F4 4.00 1.75 1.90 0.10 1.33 6,335
F5 3.00 1.90 2.00 0.10 1.14 5,430
F6 2.00 2.20 2.05 0.10 0.90 4,296

b) Walls Cum 1.00 80.46 1.00 0.10 8.05 4,763 38,323

TOTAL PLAIN CEMENT CONCRETE 63,550


3.00 REINFORCEMENT CEMENT CONCRETE

Providing and laying in position reinforced cement concrete of


design mix M20 with OPC cement @320kgs,with 20mm and
down size graded garnite metal coarse aggregates @
0.878cum and fine aggregates @0.459cum,with
supreplastisises @3lts confirming to IS9103-1999 Reaffirmed-
2008,machine mixed,concrete laid in layers not exceeding
15cms thick,vibrated for all works in foundation plinth and
Cum
ground floor level for roof slabs,staircase,lintles,retaining
walls,return walls,walls(any thickness) including attached
plasteres,columns,piers,abutments,pillars,posts,struts,buttress
es,string or lacing courses,parapets,coping,bed blocks,anchor
blocks,plain window cills,fillets etc., including cost of
materials,labour,HOM of machinery, curing complete as per
specifications.

3.01 FOOTINGS Cum - 5,902 -


F1 4.00 1.20 1.30 0.30 1.87 11,049
F2 2.00 1.30 1.35 0.30 1.05 6,215
F3 3.00 1.60 1.45 0.45 3.13 18,485
F4 4.00 1.65 1.80 0.45 5.35 31,552
F5 3.00 1.80 1.90 0.50 5.13 30,277
F6 2.00 2.10 1.95 0.55 4.50 26,586
3.02 COLUMNS Cum - 5,902 - ###
C1 9.00 0.23 0.30 3.15 1.96 11,545
C2 2.00 0.23 0.375 3.15 0.54 3,207
C3 3.00 0.23 0.30 3.15 0.65 3,848
C4 1.00 0.23 0.30 3.15 0.22 1,283
C5 2.00 0.23 0.45 3.15 0.65 3,848
C6 1.00 0.30 0.30 3.15 0.28 1,673

3.03 PLINTH BEAMS Cum 1.00 80.46 0.23 0.45 8.33 5,902 49,150 ###

TOTAL REINFORCED CEMENT CONCRETE 198,718

4.00 STEEL

Providing H.Y.S.D Steel ( Cold,twised,reinforcement (TMT) for


R.C.C work including
Straightening,cutting,bending,hooking,placing in
position,lapping and/or welding wherever required,tying with
4.01 MT ###
binding wire and anchoring to the adjoining members
wherever necessary complete as per design(laps,hooks and
wastage shal not be measured and paid) cost of all materials,
labours,HOM of machinerycomplete as per specifications.

TOTAL CC M20 MT 1.00 33.67 135.00 4.55 73,851 335,686


TOTAL STEEL 335,686

5.00 CENTRING AND SHUTTERING


Providing and removing centering,shuttering,strutting
propping etc. for columns,pillars,piers,abutments,post and
struts,square/rectangular/polygon in plan including cost of all
materials,labour complete as per specifications.
Providing and removing shuttering for RCC works at all levels
5.01 For Footings Sqm 218 -
F1 4.00 1.20 1.30 0.30 6.00 1,308
F2 2.00 1.30 1.35 0.30 3.18 693
F3 3.00 1.60 1.45 0.45 8.24 1,795
F4 4.00 1.65 1.80 0.45 12.42 2,708
F5 3.00 1.80 1.90 0.50 11.10 2,420
F6 2.00 2.10 1.95 0.55 8.91 1,942

5.02 For Columns/Pedestals Sqm 18.00 0.60 0.23 4.70 218 - ###
C1 9.00 0.23 0.30 3.15 30.05 6,551
C2 2.00 0.23 0.375 3.15 7.62 1,662
C3 3.00 0.23 0.30 3.15 10.02 2,184
C4 1.00 0.23 0.30 3.15 3.34 728
C5 2.00 0.23 0.45 3.15 8.57 1,868
C6 1.00 0.30 0.30 3.15 3.78 824

5.03 For Plinth Beam Sqm 1.00 80.46 0.23 0.45 72.41 218 15,786

TOTAL CENTERING AND SHUTTERING 40,469

6.00 MASONRY WORKS

Providing & Constructing granite size stone masonry stones


hammer dressed in CM 1:6 for foundation and plinth in
6.01 Cum - ###
courses not less than 20cm with bond stones at 1.8Mtrs apart
in each course, including scaffolding, curing, etc, complete
A) WALLS 1 80.46 0.6 0.6 28.97 3,912 113,313
Providing and constructing burnt brick masonry with
approved quality class designation 50 with cement mortar 1:4
6.02 for basemant and superstructure including cost of Cum - ###
materials,labour charges,scaffolding,curing.Complete as per
specifications.
A) 230mm brick work 1 72.23 0.23 3.15 52.33 6,537 342,085.36 ###
Deductions
Door (D) 2 0.9 0.23 2.1 0.87 (5,683)
MD 1 1.5 0.23 2.1 0.72 (4,736)
Ventilator 2 0.9 0.23 0.6 0.25 (1,624)
Window (W1) 4 1.3 0.23 1.8 2.15 6,537 (14,073)
Window (W2) 2 1.5 0.23 1.3 0.90 (5,864)
Window (W5) 1 0.75 0.23 0.9 0.16 (1,015)
Window (W4) 1 1.2 0.23 0.9 0.25 (1,624)
B) 150mm brick work 1 8.23 0.15 3.15 3.89 6,537 25,420.27 ###
Deductions - ###
Door (D1) 1 0.9 0.23 2.1 0.43 (2,842)

TOTAL MASONRY WORKS 443,359 ###


###

7.00 MISCELLANEOUS ###


Providing and injecting chemical emulsion pre constructional
antitermite treatment and creating a chemical barrier
7.01 under and around the column wall trenches, basement, Sqm 156.25 99 15,469 ###
excavation, top surface of plinth filling junction of wall and
floor, along the perime
15,469 ###

Providing Teak wood farmes for doors, windows,clerestory


windows. Ventilators and other frames,wrought,framed or
assembled including making plater groves(excluding cost of
7.02 Cum
cement concrete and side clamps), but including cost of
materials,labour,HOM of machineries. complete as per
specifications
Doors 44.6 0.125 0.1 0.558 163,288
Windows 55.2 0.075 0.075 0.311
Total 0.868 141,734
TOTAL MICELLANEOUS 157,203
TOTAL COST 477,420

BOQ FROM LINTEL LEVEL TO FIRST FLOOR SLAB

Sl. No. Description of Items Unit Nos L B D Quantity Rate Amount Remarks
8.00 REINFORCEMENT CEMENT CONCRETE

Providing and laying in position reinforced cement concrete of


design mix M20 with OPC cement @320kgs,with 20mm and
down size graded garnite metal coarse aggregates @
0.878cum and fine aggregates @0.459cum,with
supreplastisises @3lts confirming to IS9103-1999 Reaffirmed-
2008,machine mixed,concrete laid in layers not exceeding
15cms thick,vibrated for all works in foundation plinth and
Cum
ground floor level for roof slabs,staircase,lintles,retaining
walls,return walls,walls(any thickness) including attached
plasteres,columns,piers,abutments,pillars,posts,struts,buttress
es,string or lacing courses,parapets,coping,bed blocks,anchor
blocks,plain window cills,fillets etc., including cost of
materials,labour,HOM of machinery, curing complete as per
specifications.

8.01 Slab Cum 165.00 45.00 5,902 265,590


8.02 Staircase Cum 4.50 26,559

TOTAL REINFORCED CEMENT CONCRETE 292,149

9.00 STEEL
Providing H.Y.S.D Steel ( Cold,twised,reinforcement (TMT) for
R.C.C work including
Straightening,cutting,bending,hooking,placing in
position,lapping and/or welding wherever required,tying with
9.01 MT
binding wire and anchoring to the adjoining members
wherever necessary complete as per design(laps,hooks and
wastage shal not be measured and paid) cost of all materials,
labours,HOM of machinerycomplete as per specifications.

TOTAL CC M20 MT 1.00 50.93 135.00 6.88 73,851 507,766


TOTAL STEEL 507,766

10.00 CENTRING AND SHUTTERING


Providing and removing centering,shuttering,strutting
propping etc. for columns,pillars,piers,abutments,post and
struts,square/rectangular/polygon in plan including cost of all
materials,labour complete as per specifications.

Providing and removing shuttering for RCC works at all levels

10.01 Slabs Sqm 1.00 165.00 165.00 218 35,970

TOTAL CENTERING AND SHUTTERING 35,970

TOTAL COST 835,885

BOQ FROM FIRST FLOOR LEVEL TO TERRACE FLOOR SLAB

Sl. No. Description of Items Unit Nos L B D Quantity Rate Amount Remarks
11.00 REINFORCEMENT CEMENT CONCRETE

Providing and laying in position reinforced cement concrete of


design mix M20 with OPC cement @320kgs,with 20mm and
down size graded garnite metal coarse aggregates @
0.878cum and fine aggregates @0.459cum,with
supreplastisises @3lts confirming to IS9103-1999 Reaffirmed-
2008,machine mixed,concrete laid in layers not exceeding
15cms thick,vibrated for all works in foundation plinth and
Cum
ground floor level for roof slabs,staircase,lintles,retaining
walls,return walls,walls(any thickness) including attached
plasteres,columns,piers,abutments,pillars,posts,struts,buttress
es,string or lacing courses,parapets,coping,bed blocks,anchor
blocks,plain window cills,fillets etc., including cost of
materials,labour,HOM of machinery, curing complete as per
specifications.

11.01 COLUMNS Cum - 5,902 -


C1 1.00 9.00 0.23 0.30 3.15 1.96 11,545
C2 1.00 2.00 0.23 0.375 3.15 0.54 3,207
C3 1.00 3.00 0.23 0.30 3.15 0.65 3,848
C4 1.00 1.00 0.23 0.30 3.15 0.22 1,283
C5 1.00 2.00 0.23 0.45 3.15 0.65 3,848
C6 1.00 1.00 0.30 0.30 3.15 0.28 1,673
11.02 Beams Cum 1.00 84.56 0.23 0.45 8.75 5,902 51,654
11.03 Slab Cum 195.00 0.15 29.25 5,902 172,634
11.04 Staircase Cum 4.50 5,902 26,559

TOTAL REINFORCED CEMENT CONCRETE 276,252

12.00 STEEL

Providing H.Y.S.D Steel ( Cold,twised,reinforcement (TMT) for


R.C.C work including
Straightening,cutting,bending,hooking,placing in
position,lapping and/or welding wherever required,tying with
12.01 MT
binding wire and anchoring to the adjoining members
wherever necessary complete as per design(laps,hooks and
wastage shal not be measured and paid) cost of all materials,
labours,HOM of machinerycomplete as per specifications.

TOTAL CC M20 MT 1.00 46.81 135.00 6.32 73,851 466,690


TOTAL STEEL 466,690

13.00 CENTRING AND SHUTTERING


Providing and removing centering,shuttering,strutting
propping etc. for columns,pillars,piers,abutments,post and
struts,square/rectangular/polygon in plan including cost of all
materials,labour complete as per specifications.

Providing and removing shuttering for RCC works at all levels


13.01 For Columns/Pedestals Sqm 218 -
C1 9.00 0.23 0.30 3.15 30.05 6,551
C2 2.00 0.23 0.375 3.15 7.62 1,662
C3 3.00 0.23 0.30 3.15 10.02 2,184
C4 1.00 0.23 0.30 3.15 3.34 728
C5 2.00 0.23 0.45 3.15 8.57 1,868
C6 1.00 0.30 0.30 3.15 3.78 824

13.02 Slab Cum 1.00 195.00 195.00 218 42,510

13.03 Beams Sqm 1.00 84.56 0.23 0.45 76.10 218 16,591

TOTAL CENTERING AND SHUTTERING 72,917

14.00 MASONRY WORKS Cum


Providing and constructing burnt brick masonry with
approved quality class designation 50 with cement mortar 1:4
14.01 for basemant and superstructure including cost of
materials,labour charges,scaffolding,curing.Complete as per
specifications.
First floor
A) 230mm brick work 2 18.9 0.23 3.15 27.39 6,537 179,023

B) 150mm brick work 2 4 0.15 3.15 3.78 6,537 24,710

TOTAL CENTERING AND SHUTTERING 203,733

TOTAL COST 1,019,592

Total cost upto Terrace floor level 3,014,490