Professional Documents
Culture Documents
New Projects
Administration Phase: Select A Qualified Contractor
Risk Assessment
Pre-Qualification
Selection CSMS
Contract Award
Data Bank
Field Implementation Phase: Ensure Field Safe Work
900-RFP-104, Revision 1
BP Indonesia
Contractor Safety, Health and Environment Program Management
System (CSMS) Guidelines
Management Endorsement
Contractor Safety, Health and Environmental Program Management System
(CSMS) Guidelines Revision 1.0 / December 2000
Authorized By
Endorsed By
Bill Schrader
Table of Contents
The key activities in this CSMS are recorded in a web based database system
that is accessible to all relevant personnel, including the management team
consisting of Asset and Line Managers, Delivery Unit Managers and Team
Leaders, as well as the President and Resident Manager. This system will
enable the management to monitor the CSMS activities conducted by his/her
employees. A CSMS System Guideline that provides a step-by-step process on
using this system is available separately.
There are six steps in the CSMS structured into two groups, in which each
consists of three steps:
Qualification Phase
1. The objectives of this phase are to mine the necessity of the subsequent
CSMS steps. Jobs, which risks are classified as High must go through a
mandatory pre-qualification process.
2. Pre-qualification is a step to screen potential suppliers to establish that
they have the experience and capability to undertake the activities in
question safely and in an environmentally sound manner. This may
include HSE inspection and audit.
3. Selection is a step to assess whether the HSE program specific to the
level of risk involved in the work and the bid evaluation criteria have been
met and to select, where necessary on the basis of clarification meetings
and inspections, the successful bidder.
Field Implementation Phase
The field implementation phase is aimed at ensuring compliance to company
HSE standards prior to, during and after the performance of a work. This
phase constitutes the following steps:
1. Pre-job activities, where all relevant aspects of the contract risk
assessment and any other HSE aspects of the contract are
communicated and understood by all parties prior to implementation of
the contract.
2. Work In Progress, where the actual job implementation is inspected
and evaluated. Included in this stage is the mandatory requirement
for the Team Leaders accountable for the work to carry out visits at all
contractor-managed sites within seven days of start-up.
3. Final Evaluation is a step to conclude a contractor’s HSE performance
during the entire field implementation phase. The results will be used
as considerations to employ the contractor for future projects.
The following table provides a matrix of CSMS requirements for jobs
classified as low, medium and high risks.
All of these steps will be recorded in a database that will be used for future
analyses of contractor’s HSE performance. Table 2 in the following page is
provided to give assessors an idea of several types of works and the levels of
risks associated with the works. This table shall not be used to determine
the risk associated with certain jobs. Jobs illustrated as Low or Medium in the
Table may be classified as High when accidents frequently happen during the
performance of the jobs. Assessors should, however, verify the risk analysis
for the specific job based on the factors described in Section 4.1. “Risk
Assessment”.
10 EPC contracts H
17 Land transportation H
The objectives of this step are to describe the work and to assess the
HSE risks associated with the work.
Define
requirements
Electronic
endorsement by
Asset/Line
Manager
HSE
Verify risk
verification Yes No
assessment
required?
No
DUM/TL approval
Yes Agreed?
(electronic)
Approved?
Yes
Prepare Contract
Requisition
Pre-qualification Process
Not all jobs require pre-qualification. There are four conditions that do
not necessitate suppliers to be pre-qualified:
• Services classified as Low Risk and Medium Risk.
• Waived by the respective Delivery Unit Manager or Team
Leader for contractors that have passed previous pre-
qualifications for the same work or for those who received a
high pre-qualification score, or for contractors who received
satisfactory final evaluation.
• Contractors listed in the BPI Preferred Suppliers.
However, low risk jobs that in the past experienced frequent minor
accidents or incidents will require the work risk to be classified as high
(refer to Table 2: Risk Assessment Matrix), therefore, suppliers rendering
such services must be pre-qualified. Figure 2 illustrates the pre-
qualification process. For high-risk jobs, CSMS pre-qualification must
precede any bidding activities. Only suppliers that pass the CSMS pre-
qualification will be included into the bidder list for further bidding process.
In general, the pre-qualification process is to provide basic information
about the suppliers, such as:
• Contractors commitment and leadership regarding HSE;
• Policy and strategic objectives;
• HSE communication, training, management of sub- contractors,
performance standards;
• Hazards and effects management;
• Planning and procedures;
• Implementation and performance monitoring;
• Audit and review procedures;
• Other additional features
Risk
Assesment
Yes
High?
Prequalification
No Yes
required
Candidates complete
HSE pre-qualification
questionnaire
Review &
clarification by BP
Indonesia
Disqualify
Required HSE Mgmt
No
Pass? No No & provide
standard (all bidders approval
feedback
<64)
Yes
Inspection and
audit Inspection and
processes audit
processes
Yes
Conditional
acceptance
The objective of the selection phase is to assess whether the HSE Plan
and the bid evaluation criteria have been met and to select, where
necessary on the basis of clarification meetings, the successful bidder.
This CSMS Selection step is parallel with the bid evaluation process
within the procurement process framework and is considered part of the
technical evaluation.
BPI should assure that the mobilization and demobilization phases are
adequately covered in the HSE Plan. The importance of the CSMS
requirements must be communicated to all suppliers during pre-bid
clarification meetings.
Figure 3: Selection Process
SELECTION
bid
document
Conduct public
announcement (if
necessary)
Coordinate Procurement
Committee review and
approval
Participate in expediting
Coordinate BPPKA/
BPPKA/BAPPENAS
BAPPENAS approval
approval
Award
The objectives here are to ensure that the relevant aspects of the
contract risk assessment and any other HSE aspects of the contract are
communicated and understood by all parties prior to implementation of
the contract.
2.1. Pre-mobilization
2.2. Mobilization
During the initial part of the mobilization phase, all key personnel
assigned to the work must attend an HSE orientation program that
should be used to communicate the HSE Plan and any other
significant HSE aspects of the contract. Progress meetings should
then be used as a formal method of reviewing HSE implementation,
along with frequent walk-through by BPI personnel, in this case the
Asset Managers, Delivery Unit Manager, Team Leaders and/or the
HSE Project Officer.
VISIO CORPORATION
Contract Award
No
Complete?
Yes
Mobilize
Communicate HSE
Plans, audit,
Finalize HSE issues,
HSE briefings
Contract execution
The objectives of this phase are to assure that the work performed is
conducted according to the agreed upon HSE Plan, and that additional
HSE needs, identified during the work, are properly addressed.
Apart from the safety visits previously mentioned, the respective Delivery
Unit Manager or Team Leader shall also conduct periodic or spot
inspections to ensure that all HSE obligations are met.
Where responsibility for supervision rests with the contractor, BPI’s role
should be to monitor compliance to contractual terms and systems
defined within the contract. Unless the contract holder has a permanent
presence on site a Man In Charge (MIC), the respective Asset or Line
Manager must monitor and verify that all HSE obligations are being met.
Advice from HSE Project Officers can be sought where needed, however,
accountability for contract HSE lies with the contract holder.
Competence Assurance
Start up
DUM/TL HSE
visits
Yes
Work scope
changes, additional
hazards
No
Interim Evaluations:
Inspection Checklist,
Audit, HSE Program
Checklist
Contractor HSE
Interim Evaluation Accident/Incident
Performance
Reports Reports
Report
No
Corective Action
Taken?
Yes No
Job
Completed?
Yes
Final Evaluation
Diciplinary Action
HSE Plan
The contract holder and the contractor are jointly responsible for the
implementation and improvement of the HSE Plan. Successful
implementation of the HSE Plan will be determined by the achievement of
monitoring, evaluating, and conducting corrective actions, for example:
HSE Meetings
BPI and the contractor shall jointly conduct HSE meetings on a regular
basis, attended by all contractor’s and BPI representatives. This meeting
is intended to provide ongoing training and communication of HSE issues
and shall be recorded and documented.
HSE Promotion
Summarize Final
Evaluation Report
Obtain electronic
approvals from Asset/
Line Manager and
DUM/TL
Issue reprimand or
appreciation letters for
work below or over
expectations
Contract
A formal business agreement detailing the terms and conditions for the supply of
goods or the provisions of services.
Contract Holder
The person in a management level who owns the work, project or contract performed
by a contractor.
Contractor
A firm that has entered into a legal contract to supply the goods or services to BPI.
Documentation
Observations that are recorded in writing.
HSE
Health, Safety and Environment
Hazard
A potential source of serious harm to people, property, or the environment.
Incident
A specific event or sequence of events that resulted in or could have resulted
significant unwanted and unintended impact on health or safety of people, on
property, or on the environment.
Industrial Hygiene
Practices conducive to maintaining health, i.e. proper handling of chemicals, and
equipment that may have negative impact on health.
Interim Evaluation
Evaluation on contractor’s HSE performance during contract period.
Near Misses
Serious incidents that does not result in any injuries or damages, but potentially
become if not corrected.
Originator
The authorized personnel who originated the request to contract a certain work and
to conduct a CSMS process. See also User.
Subcontractor
A contractor employed by another contractor, usually the main or prime contractor,
who works for BPI. For the purpose of this document, the term contractor and
subcontractor are synonymous.