CCS-0-010-0-M-ET-003_Rev0

Febrero 2010
TABLE OF CONTENTS

CHUTES AND HOPPERS

A. APLICATION

B. DESIGN

C. WEAR PLATE

D. FLANGES

E. SIZING AND SLOPE

F. SUPPORTS.
CHUTES AND HOPPERS

Various configurations of chutes and hoppers are used in plant design. The
configuration of chutes and hoppers shall be sufficiently large for gravity flow.

• All chutes, covered skirt-boards, and hoods shall be designed for


effective dust control and shall be provided with dust exhaust
connections terminating at a duct flange. A rubber dust curtain shall be
provided at the entrance of conveyor discharge chutes and shaft seals
shall also be provided.
• Chute connections shall be flanged and bolted to facilitate field erection
and service.

A. Application

1. Chutes are used to contain materials as they flow by gravity. Hoppers,


as referred to in this document are small material surge hoppers, spill
hoppers and hoppers fed by a front-end loader.

B. Design

B-1 Chutes design guidelines.


1. Load the material on the belt at a uniform rate.

2. Load it on the belt centrally.

3. Deliver material in the direction of belt travel. See drawing 500

4. Maintain a minimum angle of inclination of the belt at the loading point.

5. Provide adequate belt edge space to allow sealing.

6. Provide adequate space and access to allow inspection and service on


both sides of the conveyor.

B-2 General specifications

1. All chutes and hoppers shall be constructed of minimum 1/4” (7mm)


thick A.S.T.M. A-36 steel, and shall be dust and weather tight.

2. Chute and hopper configurations shall be square or rectangular in


cross-section. In addition, consideration shall be given for the material
handled, such as particle size, moisture content, flow characteristics
and abrasiveness. The section of the chute must be at least 3 times
larger than the largest piece of material expected to handle.
.
3. Stone boxes shall be used wherever material flow velocity is such that
the material impact could cause damage.
4. Chutes having long vertical drops shall be "laddered" down in order to
control momentum.
5. Chutes containing wet materials or materials that may hang-up shall be
constructed with poke holes, doors or removable panels accessible
locations per owner’s agreement.

6. The chutes and hopper walls inclination shall be according to slope


angles indicates in Table II for different materials.
7. Minimums duct plate thickness:

• Pulverized coal and pet-coke: ducts 10 mm (3/8")


• Process duct: 5 mm (3/16").
• Refractory lines duct: 6 mm (1/4")
• Vent ducts straight runs: 3 mm (10 ga.)
• Vent hoods, elbows, branches, transitions, enlargements and
contractions:
5 mm (3/16”) abrasive
10 ga. (3 mm, 1/8”) non-abrasive.

B-3 Clinker chutes

1. Stepped chutes shall be used for highly abrasive materials such as


clinker,

• The clinker chute bottom plate shall be designed to form clinker


stone boxes

• Free fall of clinker within chutes shall be limited to 4'-0" before


impacting a "Stone Box" where possible. Shown in drawing 600.

• The clinker chute bottom plate in clinker chutes shall be


reinforced with 1-1/2 inch square steel bars for wear resistance.
These bars shall be welded continuously around the discharge
opening. The discharge flange opening shall be, as a minimum,
2 inches larger all around than the opening formed by the wear
bars, shown in drawing 600.

2. Maintenance doors and removable panels shall be provided for


inspection and/or replacement of liners.

C. Wear Plate

1. Chutes and hoppers which handle abrasive materials shall be lined with
abrasive resistant wear plate. Chutes shall have lining on the bottom
surface and two-thirds the height of the sides.

2. Chutes and hoppers shall be lined as follows:


• For raw material, coal, pet coke and additives handling, Wear
plates shall be 1/2” (14mm) thick abrasion resistant steel plate
with a minimum 400 BHN hardness, Ryerson AR400 or equal in
lateral walls or an owner approved equal, with countersunk holes
for bolts and nuts connection to lateral walls. Shown in drawing
601
• Chutes for raw meal and cement handling, do not require any
lining.
• For clinker handling, Wear plates shall be ceramic or ½” thick
Triten or an owner approved equal, with countersunk holes for
bolts and nuts connection to lateral walls. Shown in drawing 601
3. Liners shall be designed to weigh no more than 50 pounds and shall be
sized to be easily replaced.

4. Wear plates shall be installed using 5/8” (16mm) diameter bolts on a


maximum of 12” (300mm) center to center distance with a maximum 3”
(76mm) edge distance. All holes for bolting wear plate to be 11/16”
(18mm) diameter and counter sunk on wear plate side so head is flush
with liner surface. Access will be provided for removal and replacement
of wear plates.

D. Flanges

1. Flanges shall be fabricated of the same material and shall have a


minimum of 10 mm. (3/8”) thickness to which they are welded unless
structural considerations dictate otherwise. See flanges dimensions
shown in drawing 1100

2. Adjustable flanges shall be provided in each direction of the chute run to


allow for installation. These flanges shall be constructed of angles that
are tack welded for shipment, but allow the contractor to break, adjust
as required and reweld in the field. Approximate location of adjustable
flanges will be indicated on the drawings.

3. Bolt holes for all flanges shall be in accordance with A.I.S.C. See bolt
holes and bolts dimensions shown in drawing 1100

4. The exception to the above shall be those flanges which connect to


purchased equipment. These flanges shall be detailed on the drawings
and shall match the equipment flange.

5. Flanged connections shall be supplied and installed with gaskets that


are suitable for the pressure and temperature of the material contained
in the chute or hopper.

E. Sizing and Slopes

1. For slopes of chutes and hoppers see TABLE II

F. Supports

1. Whenever possible, chutes shall be supported from above rather than


from the floor to facilitate plant clean-up and access. Chute supports
shall be designed for the chute filled with material.
TABLA II - ANGULOS PARA PAREDES DE CHUTES Y TOLVAS

Material Angulo de chute Angulo de tolvas y


(Mínimo) chutes con flujo lleno

Cemento 60° 60°


Arcilla Húmeda 75° 75° A 90° ó Angulo
Invertido
Arcilla seca 60° 60°
Clinker 50° 60°
Coque en trozos 65° 70°
Coque Molido 70° 75°
Carbón en trozos 65° 70°
Carbón molido 70° 75°
Polvo de Harina cruda 60° 60°
Polvo de retorno de 60° 60°
Colectores
Caliza y Marl 50° 60°
Arena húmeda 75° 75° A 90°
Shale Húmeda 75° 75° A 90°
Shale seca 60° 60°
Typ.
Typ. Typ.

Typ.