Professional Documents
Culture Documents
SECTION 02001
CONCRETE WORK
1.00 GENERAL
1.01 DESCRIPTION
Furnish all materials, equipment, plant and labor for construction of concrete
work in strict accordance with this section of the specification and the
applicable drawings.
A. Reference Specifications
C. Tolerances
1. Concrete
02001-1
2. Reinforcement
(1) 180Bend four bar diameters but not less than 7 cm.
(3) Stirrup and tie bend 90 and 135 Bends Six bar diameters
but not less than 7 cm.
d. Splicing
3. Formwork
Floor Surfaces:
In 3 m. - 1/2 cm.
In 6 m. - 1 cm.
1.03 SUBMITTALS
02001-2
3. One half pint for each type liquid admixture used.
6. One complete mesh across each roll and each size of welded wire
mesh.
2. Special formwork.
C. Test specimens of three cylinders shall be submitted for each strength class
for each day’s placement.
D. Form lumber and plywood shall be handled properly to avoid damage and
shall be stored above ground on framework or blocking for adequate
ventilation.
E. Form oil, coatings and concrete agents shall be delivered and stored in
sealed containers to prevent contamination with other materials deleterious to
concrete. Container’s labels or marks for identification and intended use shall
be kept intact.
Concrete shall not be poured during hot weather over 90 F in direct sunlight and
during rainstorms unless protection is provided.
02001-3
2.00 PRODUCTS
2.01 MATERIALS
A. Concrete
2. Coarse aggregate shall have a maximum size smaller than 1/5 narrowest
dimension between form sides, but not larger than 3/4 of the minimum clear
spacing between reinforcing bars. Coarse aggregate shall have less than
50% weight loss in Los Angeles abrasion test and less than 5% by weight of
clay lumps or friable particles. Coarse aggregate shall be free of shale, oil,
and organic impurities and other substances deleteriously reactive with
cement alkalies.
a. Gradation:
PERCENT PASSING
LISTED SIEVES
3. Fine aggregate shall be free of oil and organic impurities and substances
deleteriously reactive with cement alkalies. Fine aggregate shall have less
than 3% clay lumps by weight.
7. Joint fillers shall be either cold applied concrete joint sealer conforming to
ASTM D1850 or hot poured elastic concrete joint sealer conforming to ASTM
D119.
8. Preformed expansion joint filler shall be bituminous or resilient as required
and directed by the Architect
02001-4
B. Reinforcements:
2. Welded wire fabric shall conform to ASTMA 185 of size as shown. Where the
size, mesh and weight of the fabric are not indicated, the fabric shall
be six inch by six mesh, #10 gage wire.
3. Hanger bars, chairs, spacers, supports and other devices necessary to install
and secure the reinforcing properly shall be as indicated on the drawings.
C. Form Materials
2. Plain footings, sub-structure walls - one inch min., four inches max.
3. Reinforced slabs, beams, walls, and columns - three inches min., six
inches max.
2.02 MIXES
02001-5
Drainage structures 4,000 psi
Curb and gutter and walkways 4,000 psi
Footings 4,000 psi
Columns 4,000 psi
Concrete above grade 4,000 psi
Post-tensioned member 4,000 psi
Slab on fill 4,000 psi
3.00 EXECUTION
3.01 INSPECTION
3.02 INSTALLATION
1. Fabrication shall be per approved shop drawings. All reinforcing bars shall be
bent cold, unless otherwise directed by the Architect and shall not be bent
after being partially embedded in hardened concrete. Cutting of
reinforcement shall be by mechanical methods.
B. Placing of Reinforcement
1. Bars shall be placed accurately and securely as shown on the drawings. Mats
or grids be wired together at the intersections. Intersections shall be wired
alternately with a maximum of 24 inches on center wire to prevent
displacement by construction loads before and during placing or concrete.
Bars shall be supported by approved chairs, or spacers, or by metal hangers
and on the ground by concrete blocks or other approved non-corrodible
material. Welded wire fabric shall be accurately and securely supported
similar to bar support, and shall be lifted during placing of concrete, to insure
proper position. Fabrics shall be continuous through contraction joints and
construction joints butt shall not be extended through expansion joints in slabs
on ground. Adjustment of reinforcements shall be within the allowable
tolerances to avoid interference with other reinforcing steel, conduits, or
embedded items. Bars No. 11 and smaller
02001-6
2. shall be securely wire-tied to prevent displacement of splices during
placement of concrete and bars larger than No. 11 shall be butt spliced in
accordance with specification AWS D12...1. Bars shall not be spliced except
at locations shown on drawings. Exposed bars intended for bonding with
future work shall be protected by wrapping with rag felt and coating with a
bituminous coating.
C. Form Construction
1. Portland Cement
2. Fine Aggregate
b. All sand to be used shall have the local designation of S-1 or first
class washed sand with greenish exterior color tone, sharp, fine and
hard.
3. Coarse Aggregate
4. Water used in mixing concrete shall be clean and free from injurious amounts
of oils, acids, alkalis, salts, organic matters or other substances that may be
deleterious to concrete or steel.
02001-7
5. The mixing water for pre-stressed concrete or for concrete which will contain
aluminum embediments, shall not contain deleterious amounts of chloride
ion.
7. Trial Design Batches : Trial design batches for various classes required shall
be the responsibility of the Contractor. Trial mixtures having proportions,
consistencies and air contents suitable for the work shall be made based on
ACI 211.1 using at least three (3) different water cement ratios which will
produce a range of strength encompassing those required for the work. Trial
mixtures shall be designed for maximum permitted lump and air content. The
temperature of concrete in each trial batch shall be reported. For each water-
cement ratio at least three be determined by ACI 301, Chapter3, Paragraph
3.8 Method 1or 2.
Vapor barrier shall be provided beneath the concrete floor slabs as shown in
the drawings. The material shall be placed in the greatest width and lengths
practicable so as to eliminate joints wherever possible; where joints are
necessary, the material shall be tapped not less than 6 inches side and end
laps, and sealed with approved adhesive. Torn, punctured, or damaged
vapor barrier
02001-8
material shall be removed and replaced as directed, prior to the placing of
concrete. Concrete shall be placed in a manner to prelude damage to the
vapor barrier material.
F. Concrete Placement
Mixer shall be primed with neat cement prior to initial use and conveying
equipment shall be thoroughly cleaned before each run, with waste material
and flushing water discharged outside from. All earth excavations shall be
free of mud and excess water and earth and fill surfaces shall be properly
wetted, but not muddy, before depositing. The Contractor shall see to it that
all runways shall not be supported on reinforcement. Before depositing new
concrete against set concrete, existing surfaces shall be cleaned of laitance
and loose particles; shall retighten forms against existing surfaces of neat
cement grout, and shall place new concrete before grout attains initial set.
Vibrators are required for all concrete work except for slab less than 4 inches
thick. When vibration is required, the contractor shall have to maintain at
least one spare mechanical vibrator on site at all times. Conveying concrete
from mixer to forms shall be done as rapidly as practicable by proper by
proper methods which will not cause segregation or loss of ingredients. For
vertically formed members exceeding six feet drops, tremie method, elephant
trunk hoppers, rubber or metal drops, chutes shall be used at the option of
the contractor. Splashing forms and reinforcement with concrete in advance
of depositing shall be avoided. Concrete shall be deposited after evidence of
initial set or after containing joints shall be keyed and dowelled, and shall be
located as shown. Application of concrete agents such as bonding, caulking,
fillers, sealers shall be done in strict accordance with the manufacturer’s
printed instructions and recommendations.
G. Removal of forms
(2) Slabs
H. Finishing
1. Concrete shall struck smooth at top of forms and shall be floated to texture
comparable to formed surfaces. Formed surfaces shall be as-cast finish, and
all finish, and all holes and defects shall be patched and fins removed after
form
02001-9
2. shall be tamped with jitterbug if not vibration used, and shall be floated an
disappearance of water sheen. Use dry cement to absorb excess water shall
be strictly prohibited. In the existence of water ponds, the contractor shall
screed the water off with a hose or blot with non-straining absorbent material.
Steel trowelling shall continue until concrete does not adhere to trowel, and a
slight ringing sound shall be produced. Broom, belt, or brush finish as shown or
as required by the Architect. Proper mason tools shall be used to form joints,
corners and edges.
2. Finishes for floors and slabs: For floors in which drains occur, special care
shall be exercised to slope the floors uniformly to all areas, where ceramic tile
are to be overload, the concrete base slab shall be depressed as indicated to
provide a finish floor at the same elevation as the surrounding areas. All floor
slabs where finish is not indicated or specified shall receive a single steel
trowelling. Broomed finishing shall be provided for walks, and slabs to receive
ceramic and mosaic tiles. Steel trowelled finish shall be provided for floors to
receive vinyl asbestos tile carpet, and elastomeric waterproofing.
I. Curing
1. Concrete shall be kept moist by using one of the following curing methods as
approved by the Architect.
2. Concrete Samples. Throughout the period that concrete is being poured into
the forms and while spading operations are being done, sets of test samples
in the cylinder be taken from fresh concrete from the forms. After the samples
have been prepared, they should be marked and placed where the
Architect’s Representative or Engineer-in-Charge may designate and shall be
protected from damages and kept moist for a period of sixteen (16) days.
3. At least one set, six (6) pieces of samples shall be taken from each fifty (50)
cubic meters of Class 4000psi, 3000 psi, and 2500 psi concrete deposited.
Each sample, six (6) inches in diameter by twelve (12) inches long.
02001-10
5. The testing of all samples shall be taken only by the Division of Materials
testing and Physical Researchers Laboratory, B.P.H., Manila/USC/GEO
Analytic, Cebu.
For strength of concrete obtained on test specimens less than those required above
on required minimum compressive strength, the Contractor shall pay the Owner as
liquidated damages and not as a penalty on forfeiture, the following percentages of
the unit bid prices per cubic meter for the quantity of defective concrete:
a. For concrete less than 100% strength as required but greater than 90% of the
specified strengths, 10% of unit price.
b. For concrete less than 90% but greater than 80% of the specified strengths
payment of 25% of unit bid price.
c. For concrete less than 80% but greater than 70% of the specified strengths,
payments of 455 of unit bid price.
02001-11
END OF SECTION
SECTION 02002
1.0 GENERAL
1.01 DESCRIPTION
Furnish all materials, equipment and labor for the installation of concrete
masonry unit work in strict accordance with this section of the specification
and the applicable drawings.
A. Reference Specification
1. Reinforcement
2. Masonry
a. Masonry units shall be set plumb and true-to line with level
horizontal joints within the following tolerances.
02002-1
2. Variation of the linear building lines from established
positions in the plan and related portions of columns,
walls and partitions:
1.03 SUBMITTALS
Submit ten pieces for each type of masonry unit and three pieces of 1 m long
for each size or reinforcement.
A. Masonry Units
B. Reinforcing Bars
The Contractor shall construct at least two square meters of the CHB and
have it approved by the Architect, before proceeding with the rest of the work.
This approved sample of work will be the basis of inspection. Any work with
lesser quality of workmanship than the sample will be rejected.
2.0 PRODUCTS
02002-2
(1) Average of five tests - 600 psi
(2) Individual test- 500 psi
(3) 4 & 6” CHB (.10x.20x.40 & .15x.20x.40) = 500 psi
(4) Paving blocks –(.05x.10x.20) = 3,500 psi
2. Material Uses
a. Hollow load bearing units shall be used for all exterior and
foundation walls and all other load bearing walls.
02002-3
shall be used before the initial setting of the cement
has taken place, re-tempering of the mortar in which cement
has started to set will not be permitted.
3. Mixes:
3.0 EXECUTION
3.01 INSPECTION
Proper handling and storage of materials shall be verified and test reports
and certificates shall be checked before the start of concrete masonry unit
work. During installation, cracked or broken units shall be rejected. Bond
pattern and layout shall be checked to insure minimum cutting and breaking
of bond units. Critical details such as control or expansion joints, and
reinforcing bars shall be verified for proper installation. Proper procedures
shall be utilized during work stoppages or between work days. All finished
wall surfaces shall be cleared and ready for further protective coating.
3.02 INSTALLATION
A. Only dry masonry units shall be laid and unless a different pattern is
indicated, units shall be laid in running bond pattern with vertical joints
breaking on the center of units in course below. Masonry saws shall be
used to cut and fit masonry units, and whenever possible, full units of the
proper size shall be used I lieu of cut units. Cutting and fitting where
required to accommodate the work by others shall be done by masonry
mechanics using power masonry saws. Units shall be wet cut. All cut
02002-4
edges shall be neat, true and sharp as possible. Units shall be laid
with full mortar coverage on horizontal and vertical face shells except
that webs shall also be bedded in all starting courses on footings and
around cells that are to be reinforced and filled with grout. One
section of any wall shall not be carried up in advance of the others.
Horizontal reinforcement shall be deformed reinforcing bars. Step
back unfinished work for joining with new work. Toothing shall not be
permitted. Bolts, inserts, anchors and other built-in items shall be
installed as work progresses. All cells shall be solid grouted.
B. Reinforced Masonry
1. Units shall be laid with full head and bed joints in running bond and laying
shall be done so as to preserve the unobstructed vertical continuity of
cores
to be filled. Cross webs adjacent to vertical cores to be filled with grout
shall be fully embedded in mortar to prevent leakage of grout. Reinforcing
shall be positioned accurately as indicated and horizontal reinforcing
shall be embedded in grout as laying proceeds. Only masonry units free
from chipped edges or other imperfections shall be laid for all exposed
masonry surfaces. All wall openings shall be provided with an additional
reinforcing bar around the opening. Rebar shall be 12mm. diameter when
not indicated I the plans. All mortar protruding into grout spaces shall be
removed prior to grouting. Clean-out holes shall be provided at the
bottom of every containing vertical reinforcement when grouting height
exceeds 24 inches. Clean-outs shall be plugged after reinforcement and
final cleaning of the grout spaces have been completed. Backfill
foundation walls seven days after grouting of cells have been completed.
C. Jointing
1. Lintel and bond beams shall consist of beam units reinforced as indicated
by with not less than two of 12mm. diameter bars where not indicated,
and shall be filled with grout. When laying open bottom type bond beam
units over cells not to be filled with grout, a wire mexh or small mexh
metal lath shall be placed under bond beam units contain grout within the
spaces. Structural bond beams shall be continuous at control
discontinuous at seismic and expansion joints. Sill shall be set with only
the ends bedded in mortar; remainder of sill joint shall be left open until
painting. Slip type sill shall be set in full mortar bed. Vertical joints in sill
shall have drip grooves on underside where units overhang the walls.
02002-5
E. Control Joints
A. All holes in exposed masonry surfaces shall be pointed. All defective joints
shall be cut tuck point solid with mortar. Excess loose mortar shall be
removed from all exposed masonry and finished masonry surfaces shall be
left free from loose mortar and stains. All exposed surfaces of masonry shall
be cleaned from the top down with either a solution of tri-sodium phosphate
and household detergent or muriatic acid and clean water. Surfaces shall be
free from mortar stain, drippings, efflorescence and other foreign substances.
02002-6
END OF SECTION
DIVISION- IV - ROOFING AND MOISTURE CONTROL
SECTION- 04001
1.0 GENERAL
1.01 DESCRIPTION
A. Reference Specifications
1.03 SUBMITTALS
A. Samples
B. Shop Drawings
04001-1
2.0 PRODUCTS
2.01 Materials
A. Anchor bolts, toggle bolts, and sag rods shall conform to the latest
edition of American Standard for Testing and Materials (ASTM
A307), Low Carbon Steel Externally and Internally Threaded
Standards Fasteners.
E. Expansion shields shall be of style, type, class and group suited for
the purpose or as indicated. Shields shall be accurately recessed and
unless otherwise indicated shall not be less than 2 inches into
concrete or masonry.
G. Trench and vent covers and frames shall be furnished and installed
where shown and as on the drawings. Frames shall be steel angles
of sizes shown on the drawings, anchored into concrete with bar
anchors welded to the angle at not more than 2 foot centers. Angles
shall have welded-on bar plates stops of the same thickness as the
cover plates. Covers shall be as indicated on the drawings. Covers
shall be cut accurately to required sizes with all edges ground
smooth to straight lines and fitted to frames and to each other with a
tolerance of not more than 1/16-inch. Covers shall be provided with
slots for fitting. Covers shall be fitted in frames without fasteners, or
where indicated in the drawings, be held to frames with countersunk-
bend screws at 12-inch centers. Countersunk screw holes in cover
plates shall be drilled in the shop. Holes in edge frame angles shall
be drilled and threaded in place, using the cover plates for templates.
H. Welding electrodes and rods for manual arc welding. Electrodes shall
conform to American Welding Society (AWS) A5.1 B60 or A5.50 E70
entitled “Mild Steel Covered Arc Welding Electrodes and Low Alloy
Steel Covered Arc-Welding Electrodes respectively.
3.01 Inspections
04001-2
B. Verify correctness of anchor bolt locations and alignment.
3.03 Workmanship and finish shall be equal to the best practice and modern shops for the
respective work. Exposed surfaces shall have a smooth finish and sharp, well defined
lines and arises. Section shall be well framed to shape and size with sharp lines and
angles; curved work shall be sprung evenly to curves. All necessary rabbets, lags and
brackets shall be provided so that the work can be assembled in a neat and
substantial manner. Holes for bolts and screws shall be drilled. Fastening shall be
concealed where practicable. Thickness of metals, and details of assembly and
supports, shall provide ample strength and stiffness. Joints exposed to the weather
shall be formed to exclude water. metal work shall be provided with the proper bevels
and clearances. Work shall be fabricated and installed in a manner that will provide
for expansion and contractions, prevent the shearing of bolts, screws and other
fastening, insure rigidity, and provide close fitting of sections.
3.04 Anchors and bolts shall be provided where indicated and where necessary for
fastening work place; they shall be embedded in the concrete and masonry as the
work progress, and shall be spaced about 2 feet on centers unless indicated or
specified otherwise. Sizes, kinds and spacings of anchors not indicated or specified
shall be as necessary for their purposes. All anchors and anchor bolts in exterior
walls and exposed to weather, shall be zinc-coated, all those in other locations shall
be coated heavily with bituminous paint.
3.05 Shop painting. All miscellaneous metal works except for galvanized surfaces and
items and steel work to be embedded in concrete, shall be shop primed and site
finished. Painting shall be as specified in Section: FIELD PAINTING.
04001-3
END OF SECTION
SECTION- 04002
ROOFING & SHEET METAL
1.0 GENERAL
1.01 DESCRIPTION
B. Test
1. Prior to acceptance of the completed work watertight test
shall be make as follows:
B. Stocks shall be kept covered and protected from the weather and
from contact with soil.
2.0 PRODUCTS
2.01 MATERIALS
04002-1
D. Rivets shall be of the pan head solid type.
3.0 EXECUTION
3.01 INSPECTION
04002-2
END OF SECTION
SECTION- 04003
WATER PROOFING
1.0 GENERAL
1.01 DESCRIPTION
The work under this section shall include all materials, labor, equipment, tools
and facilities and the satisfactory performance of all work necessary for the
complete waterproofing of floor & roof slab and all other areas necessary for
the complete waterproofing of floor & roof slab and all other areas necessary
and as directed by the Architect to be waterproofed.
1.03 SUBMITTAL
1.04 MATERIALS
A. Membrane waterproofing 3 ply for floor & roof slab & others.
Any and all substitution of above specified shall be with the approval
of the Architect.
2.0 EXECUTION
2.02 APPLICATION
04003-1
2.03 PROOF TESTING
The waterproofing must be allowed to cure fully before proof testing. proof
testing maybe conducted at the option of the Architect, by gently flooding the
completed waterproofed areas. Depth of the water should not exceed 25mm
to prevent overload. this shall be done by leaving the water on the area for
three days prior to any concrete tapping.
2.04 GUARANTEE
The waterproofing Contractor shall guarantee that the work specified in this
Section shall be free from defects of materials and performance and
leakages for a period of at least 5 years from date of final acceptance.
04003-2
END OF SECTION
DIVISION III – DOORS, WINDOWS AND GLASS
SECTION – 4001
1.0 GENERAL
1.01 DESCRIPTION
A. Furnish, fabricate and Install all wood doors, frames and accessories
complete as shown in the drawings and as specified herein.
1.03 SUBMITTALS
B. No work shall be started until all shop drawings have been approved
by the Architect.
B. Doors shall be protected and kept under cover both during transit
and at the jobsite.
2.0 PRODUCTS
2.01 MATERIALS
1. Hollow core flush doors shall be the ladder type, with the
core parts uniformly spaced to provide sufficient support for
strength and durability.
2. Solid core flush doors shall have solid cores of the stile and
rail type or the vertical block type.
3.0 EXECUTION
3.01 INSPECTION
A. Doors shall be checked for warp and weave and true if necessary.
3.02 PREPARATION
A. Top and bottom edges of all interior and exterior doors shall be given
a coat of lead and oil priming paint or a coat of water-resistant spar
varnish after cutting and fitting and prior to installation in the work.
3.03 INSTALLATION
04001-2
END OF SECTION
SECTION –04002
1.0 GENERAL
1.01 DESCRIPTION
B. Protection of aluminum.
1.03 SUBMITTALS
2.0 PRODUCTS
2.01 MATERIALS
C. Doors and frames shall be cut, reinforced drilled and tapped at the
factory to receive all template hardware.
3.0 EXECUTION
3.01 INSPECTION
3.02 INSTALLATION
04002-3
END OF SECTION
SECTION – 04003
METAL WINDOWS/LOUVERS
1.0 GENERAL
1.01 DESCRIPTION
A. Furnish, fabricate and install complete all metal windows and louvers
and accessories as shown in the drawings and as specified herein.
1.03 SUBMITTALS
A. submit shop drawings of all metal windows and louvers for approval.
B. No work shall be started until all shop drawings have been approved
by the Architect.
A. Products shall be
04003-1
END OF SECTION
SECTION 4004
The work includes the supply, fabrication, delivery and install on the site all exterior
curtain wall aluminum glass (fixed and awning windows) and main entrance
aluminum doors in accordance with the plans and specifications.
2.0 MATERIALS
2.01 Glass 6mm tempered fixed clear glass ( as indicated in the plans)
6mm tempered clear glass with awning windows (as indicated in the
plans)
12mm annealed clear glass (as indicated in the plans)
12mm tempered clear glass ( for entrance doors)
2.02 Aluminum:
Frames: Tubular aluminum with a minimum thickness of 2.8/3.0 mm;
anodized and H-2000 finish (siverized or mirrorized). All in accordance
with the detailed drawing.
6.0 This works is all in accordance with the above specifications and and attached
drawing.
04004-1
End of Section