Sr/No Description of Work No L (ft) W (ft) H (ft) Qty (cft) Qty (Cum)
A Basement
1 UGWT
Raft 1 73.58 20.75 1.5 2290.1775 64.8408125708
Walls 2 70.58 1.5 7 1482.18 41.9643261608
2 17.75 1.5 7 372.75 10.5535107588
Columns in walls 10 1.75 0.25 7 30.625 0.86707248018
Slab 1 73.58 20.75 0.5 763.3925 21.6136041903
2 Sump
Raft 1 15.5 7.75 1.5 180.1875 5.10157134768
Walls 2 12.5 1.5 4 150 4.24688561721
2 4.75 1.5 4 57 1.61381653454
Slab 1 15.5 7.75 0.66 79.2825 2.24469139298
3 Raft
Grid G to N/ Line 1 A to 10 1 142.75 144.75 1.66 34300.68375 971.140536523
Grid B to F/Line 1 A to 8 1 73.67 110.75 1.66 13543.86115 383.461527463
Raft Deductions
UGWT Slab 1 73.58 20.75 0.5 763.3925 21.6136041903
Sump Slab 1 15.5 7.75 0.66 79.2825 2.24469139298
4 Footing Beams
Grid G to N / Line 1A to 10 6 144.75 1.75 0.83 1261.49625 35.7162018686
Grid G/ Line 8 to 10 1 34.75 1.75 0.83 50.474375 1.42905931484
Grid F & G /Line 1Ato 8 1 110.75 3.58 0.83 329.08255 9.31717298981
Grid B to F/Line 1 A to 8 4 110.75 1.75 0.83 643.4575 18.2179360136
Grid B to N/ Line 1 to 8 7 216.42 1.75 0.83 2200.45035 62.3004062854
Grid G toN / Line 9 to 10 2 142.75 1.75 0.83 414.68875 11.7409045866
5 Ramp
Grid M to N/ Line 4 to 10 1 110.75 24.75 0.66 1809.10125 51.2203071914
Ram Beams
Grid M to N/ Line 4 to 10 6 24.75 1.25 1.5 278.4375 7.88328142695
Grid M to N/ Line 4 to 10 1 110.75 1.25 1.5 207.65625 5.87928227633
6 Basement Columns
Square Columns
Grid L and M/ Line 2 to 9 8 1.75 1.75 9.75 238.875 6.76316534541
Grid K/ Line 8 and 9 2 1.75 1.75 9.75 59.71875 1.69079133635
Grid C/ Line 2 to 8 5 1.75 1.75 9.75 149.296875 4.22697834088
Circular Columns
Grid H to M/ Line 2 to 9 27 4.9 1 9.75 1289.925 36.5210928652
Grid D to G/ Line 2 to 7 20 4.9 1 9.75 955.5 27.0526613817
9 Slab
Grid G to N / Line 1A to 10 1 142.75 144.75 0.58 11984.57625 339.314163364
Beams
Grid G to N/ Line 1A to 10 7 144.75 1 1.16 1175.37 33.2777463194
Grid G to N / Line 1A to 10 8 132 1 1.16 1224.96 34.6817667044
Grid K to L/ Line 3 to 4 1 20 1 1.16 23.2 0.65685164213
Deduction Of Slab & beams
Grid K to N/ Line 5 to 10 1 95.75 46.75 0.58 2596.26125 73.5068304077
Grid K to N / Line 6 to 9 4 46.75 1 1.16 216.92 6.14156285391
Lift Well 1 15 10 0.58 87 2.46319365798
Grid K to M / Line 5 to 6 1 22 20 0.58 255.2 7.22536806342
10 Panoramic Lift
Raft 1 16.25 10 1.66 269.75 7.63731596829
Basement walls 1 43.5 1 15.66 681.21 19.286806342
11 Stair Case 1 8
B Ground Floor
1 Columns
Grid B / Line 1 to 8 6 1.75 1.75 12.5 229.6875 6.50304360136
Grid C to F/ Line 1 to 8 20 1.75 1.75 12.5 765.625 21.6768120045
Grid G to N /Line 1 to 10 26 1.75 1.75 12.5 995.3125 28.1798556059
4 Slab
Grid A to B / Line 1 to 8 1 19.75 121.75 0.58 1394.64625 39.4860206682
Grid C to F / Line 1 to 8 1 71.75 121.75 0.58 5066.62625 143.449214326
Grid G to N / Line 1 to 8 1 142.75 155.75 0.58 12895.32125 365.09969564
Slab Beams
Grid A to B / Line 1 to 8 7 19.75 1 1.16 160.37 4.54048697622
Grid A to B / Line 1 to 8 2 114.75 1 1.16 266.22 7.53737259343
Grid C to F / Line 1 to 8 7 71.75 1 1.16 582.61 16.495186863
Grid C to F / Line 1 to 8 4 114.75 1 1.16 532.44 15.0747451869
Grid G to N / Line 1 to 8 9 142.75 1 1.16 1490.31 42.1945073613
Grid G to N / Line 1 to 8 6 146.75 1 1.16 1021.38 28.9178935447
Deductions 0 0
Grid K to M / Line 5 to 6 1 22 20 0.58 255.2 7.22536806342
Grid G to M/ Line 8 to 10 1 118.875 34 0.58 2344.215 66.3707531144
Grid G to H/ Line 6 to 8 1 24 41.75 0.58 581.16 16.4541336353
Grid G to M / Line 8 to 9 4 34 1 1.16 157.76 4.46659116648
Grid G to M / Line 8 to 10 1 118.88 1 1.16 137.9008 3.90432616082
Grid G to H/ Line 7 to 8 2 24 1 1.16 55.68 1.57644394111
Lift Well 1 15 10 0.58 87 2.46319365798
5 Raft
Grid A to N/ Line 1 to 1A 1 234.42 10 1.66 3891.372 110.174745187
Grid A to B / Line 1A to 8 1 110.75 10 1.66 1838.45 52.0512457531
6 Footing Beams
Grid A/ Line 1 to 1A 1 10 1.75 0.83 14.525 0.4112400906
Grid B and C/ Line 1 to 1 A 1 10 3.58 0.83 29.714 0.8412797282
Grid D to E/ Line 1 to 1A 2 10 1.75 0.83 29.05 0.8224801812
Grid F to G/ Line 1 to 1A 1 10 3.58 0.83 29.714 0.8412797282
Grid H to N/ Line 1 to 1A 6 10 1.75 0.83 87.15 2.4674405436
Grid A to B/ Line 1 to 8 7 18 1.75 0.83 183.015 5.18162514156
0 0
7 Panoramic Lift 0 0
Outer walls 2 5 0.75 12 90 2.54813137033
Inner Walls 1 5 1 12 60 1.69875424689
8 Stair Case 1 8
2 Retaining Wall
Grid A / Line 1 to 8 1 121.75 1 12.5 1521.875 43.088193658
Columns 7 1.75 0.75 12.5 114.84375 3.25152180068
4 Slab
Grid G to N / Line 1 to 10 1 142.75 155.75 0.58 12895.32125 365.09969564
Grid C to F/ Line 1 to 8 1 72 121.75 0.58 5084.28 143.949037373
Grid A to B / Line 1 to 8 1 19.75 121.75 0.58 1394.64625 39.4860206682
Grid K to M/ Line 5 to 6 1 23.75 21.75 0.58 299.60625 8.48262315968
Lift Well 1 15 10 0.58 87 2.46319365798
5 Beam
Grid G to N/ Line 1 to 10 9 142.75 1 1.16 1490.31 42.1945073613
Grid G to N/ Line 1 to 10 7 140 1 1.16 1136.8 32.1857304643
Grid K to L/ Line 3 to 5 1 20 1 1.16 23.2 0.65685164213
Grid C to F/ Line 1 to 8 7 72 1 1.16 584.64 16.5526613817
Grid C to F/ Line 1 to 8 4 108.5 1 1.16 503.44 14.2536806342
Grid A to B/ Line 1 to 8 2 120.75 1 1.16 280.14 7.93148357871
Grid A to B/ Line 1 to 8 7 18.75 1 1.16 152.25 4.31058890147
6 Stair Case 1 8
D 1st Floor
1 Column
Grid G to N/ Line 1 to 10 64 1.75 1.75 10.25 2009 56.8799546999
Grid C to F/ Line 1 to 8 28 1.75 1.75 10.25 878.9375 24.8849801812
2 Slab
Grid C to F/ Line 1 to 8 1 121.75 71.75 0.58 5066.62625 143.449214326
Grid G to N/ Line 1 to 10 1 155.75 142.75 0.58 12895.32125 365.09969564
Lift Well 1 15 10 0.58 87 2.46319365798
3 Beams (FB 2)
Grid C to F / Line 1 to 8 4 121.75 1 1.16 564.92 15.9943374858
Grid G to N/ Line 1 to 10 7 155.75 1 1.16 1264.69 35.8066251416
FB 1
Grid C to N/ Line 1 to 8 7 195.33 1 1.16 1586.0796 44.90599094
Grid G to N / Line 9 to 10 2 130.5 1 1.16 302.76 8.57191392978
4 Stair Case 1 8
5490.88997
5255.48756
Deduction
21.6136
2.244691
1.274066
1.698754
73.50683
6.141563
2.463194
7.22
1.698754
7.22
66.37
16.45
4.46
3.9
1.57
2.463194
1.698754
8.482623
2.463194
2.463194
235.40241
Concrete Record as Old Drawing
Sr/No Description of Work No L (ft) W (ft) H (ft) Qty (cft)
A Basement
1 UGWT
Raft 1 73.58 20.75 1.5 2290.178
Walls 2 70.58 1.5 7 1482.18
2 17.75 1.5 7 372.75
Columns in walls 10 1.75 0.25 7 30.625
Slab 1 73.58 20.75 0.5 763.3925
2 Sump
Raft 1 15.5 7.75 1.5 180.1875
Walls 2 12.5 1.5 4 150
2 4.75 1.5 4 57
Slab 1 15.5 7.75 0.66 79.2825
3 Raft
Grid 6A to 12 / Line J to A 1 142.75 155.75 1.66 36907.3
Grid 1 to 6/ Line J to C 1 103.6 110.75 1.66 19046.34
Raft Deductions
UGWT Slab 1 73.58 20.75 0.5 763.3925
Sump Slab 1 15.5 7.75 0.66 79.2825
4 Footing Beams
Grid 6A to 12/ Line J to A 6 155.75 1.75 0.83 1357.361
Grid 6A/ Line C to A 1 34.75 1.75 0.83 50.47438
Grid 1 to 6/ Line J to C 1 110.75 3.58 0.83 329.0826
Grid 4 to 5/ Line J to C 2 110.75 1.75 0.83 321.7288
Grid 3 and 3A/ Line J to C 1 110.75 3.58 0.83 329.0826
Grid 1 to 2/ Line J to C 2 110.75 1.75 0.83 321.7288
Grid 1 to 12/ Line J to C 7 246.42 1.75 0.83 2505.475
Grid 6A to 12/ Line C to A 2 142.75 1.75 0.83 414.6888
5 Ramp
Grid 11 to 12/ Line G to A 1 110.75 24.75 0.66 1809.101
Ramp Beams
Grid 11 to 12/ Line G to A 6 24.75 1.25 1.5 278.4375
6 Basement Columns
Square Columns
Grid 10 to 11/ Line G to B 9 1.75 1.75 9.75 268.7344
Grid 2 to 3/ Line H to D 15 1.75 1.75 9.75 447.8906
Circular Columns
Grid 6A to 11/ Line H to B 27 2.4 1 9.75 631.8
Grid 4 to 6A/ Line H to D 20 2.4 1 9.75 468
7 Basement Retaining Wall
Grid J/ Line 1 to 12 1 246.42 1 9.75 2402.595
Columns 14 1.75 0.75 9.75 179.1563
8 Stair Case 1
10 Slab
Grid 6A to 12/ Line J to A 1 142.75 155.75 0.58 12895.32
Grid 3A to 6/ Line J to C 1 83.92 121.75 0.58 5926.011
Grid 1 to 3/ Line J to C 1 19.75 121.75 0.58 1394.646
Slab Deductions
Grid K to N/ Line 5 to 10 (New) 1 95.75 46.75 0.58 2596.261
Lift Well 1 15 10 0.58 87
Grid K to M / Line 5 to 6 (New) 1 22 20 0.58 255.2
Beams
Grid 6A to 12/ Line J to C 7 155.75 1 1.16 1264.69
Grid 6A to 12/ Line J to C 8 132 1 1.16 1224.96
Grid K to L/ Line 3 to 4 1 20 1 1.16 23.2
Deduction Of Slab & beams
Grid K to N/ Line 5 to 10 1 95.75 46.75 0.58 2596.261
Grid K to N / Line 6 to 9 4 46.75 1 1.16 216.92
B Ground Floor 0
1 Columns
Grid 1 to 6/ Line J to C 49 1.75 1.75 12.5 1875.781
Grid 6A to 12/ Line J to A 64 1.75 1.75 12.5 2450
0
2 Ground Floor Retaining wall
Grid 1 to 12/ Line J 1 246.42 1 12.5 3080.25
Columns 14 1.75 0.75 12.5 229.6875
Grid 12/ Line J to A 1 155.75 1 12.5 1946.875
Columns 9 1.75 0.75 12.5 147.6563
4 Slab
Grid 1 to 3/ Line J to C 1 121.75 31.75 0.58 2242.026
Grid 3A to 6/ Line J to C 1 121.75 71.92 0.58 5078.631
Grid 6A to 12/ Line J to A 1 155.75 142.75 0.58 12895.32
Slab Beams
Grid 1 to 3/ Line J to C 7 31.75 1 1.16 257.81
Grid 1 to 3/ Line J to C 3 114.75 1 1.16 399.33
Grid 3A to 6/ Line J to C 4 114.75 1 1.16 532.44
Grid 3A to 6/ Line J to C 7 71.92 1 1.16 583.9904
Grid 6A to 12/ Line J to A 7 155.75 1 1.16 1264.69
Grid 6A to 12/ Line J to A 9 135.75 1 1.16 1417.23
Slab Deduction
Grid 10 to 11/ Line F to E 1 22 20 0.58 255.2
Grid 6A to 11/ Line C to A 1 118.875 34 0.58 2344.215
Grid 4 to 7/ Line D to C 1 73.58 21.75 0.58 928.2117
Grid 7 to 10/ Line C to A 4 34 1 1.16 157.76
Grid 7 to 10/ Line C to A 1 118.88 1 1.16 137.9008
Grid 4 to 7/ Line D to C 3 24 1 1.16 83.52
Lift well Slab Deduction 1 15 10 0.58 87
5 Stair Case 1
4 Slab
Grid 6A to 12/ Line J to A 1 142.75 155.75 0.58 12895.32
Grid 3A to 6/ Line J to C 1 72 121.75 0.58 5084.28
Grid 1 to 3/ Line J to C 1 19.75 121.75 0.58 1394.646
Grid 10 to 11/ Line F to E 1 23.75 21.75 0.58 299.6063
Lift well Slab Deduction 1 15 10 0.58 87
5 Beam
Grid 6A to 12/ Line J to A 9 142.75 1 1.16 1490.31
Grid 6A to 12/ Line J to A 7 140 1 1.16 1136.8
Grid K to L/ Line 3 to 5 1 20 1 1.16 23.2
Grid 3A to 6/ Line J to C 7 72 1 1.16 584.64
Grid 3A to 6/ Line J to C 4 108.5 1 1.16 503.44
Grid 1 to 3/ Line J to C 3 120.75 1 1.16 420.21
Grid 1 to 3/ Line J to C 7 31.75 1 1.16 257.81
D 1st Floor
1 Slab
Grid 3a to 6/ Line J to C 1 121.75 71.75 0.58 5066.626
Grid 6a to 12/ Line J to A 1 155.75 142.75 0.58 12895.32
2 Beams (SB -2 )
Grid 6a to 12/ Line J to A 7 155.75 1 1.16 1264.69
Grid 3a to 6/ Line J to C 4 121.75 1 1.16 564.92
Grid 10 to 11/ Line G to H 1 19 1 1.16 22.04
SB -2
Grid 4 to 5 / Line H to D 3 23 1 1.16 80.04
Grid 7 to 10/ Line D to C 3 23 1 1.16 80.04
Grid 7 to 10/ Line D to C 3 6 1 1.16 20.88
Grid 9 to 10/ Line C to B 1 19 1 1.16 22.04
SB -1
Grid 8 to 9/ Line G to E 3 19 1 1.16 66.12
3 Lift well Deduction 1 15 10 0.58 87
Qty (Cum) Deduction
64.8408126
41.9643262
10.5535108
0.86707248
21.6136042
5.10157135
4.24688562
1.61381653
2.24469139
1044.94051
539.250906
21.6136042 21.6136
2.24469139 2.244691
38.4303865
1.42905931
9.31717299
9.10896801
9.31717299
9.10896801
70.9364482
11.7409046
51.2203072
7.88328143
7.60856101
12.680935
17.8878822
13.2502831
68.023641
5.07237401
42.9944083
3.26081186
35.3641704
2.27606526
9.59265289
1.08693729
25.6826869
2.27606526
33.3327435
2.536187
16.7565119
1.69875425 1.698754
365.099696
167.7806
39.4860207
73.5068304 73.50683
2.46319366 2.463194
7.22536806 7.22
35.8066251
34.6817667
0.65685164
73.5068304 73.50683
6.14156285 6.141563
53.1081894
69.3657984
0
87.2097961
6.5030436
55.1210362
4.18052803
50.5202435
3.2515218
12.6521801
1.39350934
32.4108154
2.32251557
43.0881937
3.2515218
19.3657984
1.69875425 1.698754
63.4775269
143.789094
365.099696
7.29926387
11.3060589
15.0747452
16.5342695
35.8066251
40.1254247
7.22536806 7.225368063
66.3707531 66.37075311
26.2800595 26.28005946
4.46659117 4.466591166
3.90432616 3.904326161
2.36466591 2.364665912
2.46319366 8.482623
53.1081894
69.3657984
43.0881937
3.2515218
19.3657984
1.69875425 1.698754
365.099696
143.949037
39.4860207
8.48262316 8.482623
2.46319366 8.482623
42.1945074
32.1857305
0.65685164
16.5526614
14.2536806
11.8972254
7.29926387
143.449214
365.099696
35.8066251
15.9943375
0.62400906
44.9059909
8.57191393
2.26613817
2.26613817
0.59116648
0.62400906
1.87202718
2.46319366 2.463193658
5853.29 330.3157965
5522.9742