STRUCTURE - REINFORCEMENT 1 ton = 1000

BARS 2,754.00 /ton by grade


RM /Ton RM / Kg
1) Material Qty Rate
Y10 1 2,754.00 /ton = 2,754.00 ton 2.75 / Kg
Tie Wire 0.02 2,754.00 /ton = 55.08 ton 0.06 / Kg

2) Labour (1S + 3GL) 30 60 /day = 225.00 ton 0.23 / Kg


8 ton/day

3) Machine Qty Rate Total = 56.25 ton 0.06 / Kg


Crane 1 400 /day 400 /day
Cutting & Bending 2 25 /day 50 /day
8 ton/day 450 /day
4) Fuel Qty Rate RM 1.8 /lit = 20.25 ton 0.02 / Kg
Crane 1 50 lit/day 50 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day
8 ton/day 162 /day 3,110.58 ton 3.11 / Kg
5) Wastage & 5% 155.53 ton 0.16 / Kg
Unefficencies
6) Design & Fluctuation 0% - ton
Elements RAW COST 3,266.11 ton 3.27 / Kg

7) Profit 10% 326.61 ton 0.33 / Kg


3,592.72 ton 3.59 / Kg
SAY 3,593.00 ton 3.59 / Kg
STRUCTURE - REINFORCEMENT
BRC A4 4.10 m2 BRC A5 6.31 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC A4 1 4.10 m2 = 4.10 m2 BRC A5 1 6.31 m2 = 6.31 m2
Tie Wire (per ton) 0.01 4.10 m2 = 0.04 m2 Tie Wire (per ton) 0.01 6.31 m2 = 0.06 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 5.29 m2 2112 m2/day 141.8 7.52 m2
5) Wastage & 5% 0.26 m2 5) Wastage & 5% 0.38 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 0% - m2 6) Design & Fluctuati 0% - m2
Elements RAW COST 5.55 m2 Elements RAW COST 7.89 m2

7) Profit 10% 0.56 m2 7) Profit 10% 0.79 m2


I m2 0.05 20 m2 6.00 m2 6.11 m2 I m2 0.05 20 m2 9.00 m2 8.68 m2
SAY 6.00 m2 SAY 9.00 m2
BRC A6 8.20 m2 BRC A7 11.15 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC A6 1 8.20 m2 = 8.20 m2 BRC A7 1 11.15 m2 = 11.15 m2
Tie Wire (per ton) 0.01 8.20 m2 = 0.08 m2 Tie Wire (per ton) 0.01 11.15 m2 = 0.11 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 9.43 m2 2112 m2/day 141.8 12.41 m2
5) Wastage & 5% 0.47 m2 5) Wastage & 5% 0.62 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 0% - m2 6) Design & Fluctuati 0% - m2
Elements RAW COST 9.90 m2 Elements RAW COST 13.03 m2

7) Profit 10% 0.99 m2 7) Profit 10% 1.30 m2


I m2 0.05 20 m2 11.00 m2 10.89 m2 I m2 0.05 20 m2 14.00 m2 14.33 m2
SAY 11.00 m2 SAY 14.00 m2

DTP/MMCG/N4/RB/1 09/04/2020
STRUCTURE - REINFORCEMENT
BRC A8 14.60 m2 BRC A9 18.45 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC A8 1 14.60 m2 = 14.60 m2 BRC A9 1 18.45 m2 = 18.45 m2
Tie Wire (per ton) 0.01 14.60 m2 = 0.15 m2 Tie Wire (per ton) 0.01 18.45 m2 = 0.18 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 15.89 m2 2112 m2/day 141.8 19.78 m2
5) Wastage & 3% 0.48 m2 5) Wastage & 3% 0.59 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 1.59 m2 6) Design & Fluctuati 10% 1.98 m2
Elements RAW COST 17.96 m2 Elements RAW COST 22.35 m2

7) Profit 10% 1.80 m2 7) Profit 10% 2.24 m2


I m2 0.05 20 m2 20.00 m2 19.75 m2 I m2 0.05 20 m2 25.00 m2 24.59 m2
SAY 20.00 m2 SAY 25.00 m2
BRC A10 22.80 m2 BRC A11 27.55 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC A10 1 22.80 m2 = 22.80 m2 BRC A11 1 27.55 m2 = 27.55 m2
Tie Wire (per ton) 0.01 22.80 m2 = 0.23 m2 Tie Wire (per ton) 0.01 27.55 m2 = 0.28 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 24.17 m2 2112 m2/day 141.8 28.97 m2
5) Wastage & 3% 0.73 m2 5) Wastage & 3% 0.87 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 2.42 m2 6) Design & Fluctuati 10% 2.90 m2
Elements RAW COST 27.32 m2 Elements RAW COST 32.74 m2

7) Profit 10% 2.73 m2 7) Profit 10% 3.27 m2


I m2 0.05 20 m2 30.00 m2 30.05 m2 I m2 0.05 20 m2 36.00 m2 36.01 m2
SAY 30.00 m2 SAY 36.00 m2

DTP/MMCG/N4/RB/1 09/04/2020
STRUCTURE - REINFORCEMENT
BRC A12 36.41 m2 BRC A13 42.72 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC A12 1 36.41 m2 = 36.41 m2 BRC A13 1 42.72 m2 = 42.72 m2
Tie Wire (per ton) 0.01 36.41 m2 = 0.36 m2 Tie Wire (per ton) 0.01 42.72 m2 = 0.43 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 37.92 m2 2112 m2/day 141.8 44.29 m2
5) Wastage & 3% 1.14 m2 5) Wastage & 3% 1.33 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 3.79 m2 6) Design & Fluctuati 10% 4.43 m2
Elements RAW COST 42.85 m2 Elements RAW COST 50.05 m2

7) Profit 10% 4.28 m2 7) Profit 10% 5.01 m2


I m2 0.05 20 m2 47.00 m2 47.13 m2 I m2 0.05 20 m2 55.00 m2 55.06 m2
SAY 47.00 m2 SAY 55.00 m2
BRC B5 12.51 m2 BRC B6 13.78 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC B5 1 12.51 m2 = 12.51 m2 BRC B6 1 13.78 m2 = 13.78 m2
Tie Wire (per ton) 0.01 12.51 m2 = 0.13 m2 Tie Wire (per ton) 0.01 13.78 m2 = 0.14 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 13.78 m2 2112 m2/day 141.8 15.06 m2
5) Wastage & 3% 0.41 m2 5) Wastage & 3% 0.45 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 1.38 m2 6) Design & Fluctuati 10% 1.51 m2
Elements RAW COST 15.57 m2 Elements RAW COST 17.02 m2

7) Profit 10% 1.56 m2 7) Profit 10% 1.70 m2


I m2 0.05 20 m2 17.00 m2 17.13 m2 I m2 0.05 20 m2 19.00 m2 18.72 m2
SAY 17.00 m2 SAY 19.00 m2

DTP/MMCG/N4/RB/1 09/04/2020
STRUCTURE - REINFORCEMENT
BRC B7 16.73 m2 BRC B8 21.85 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC B7 1 16.73 m2 = 16.73 m2 BRC B8 1 21.85 m2 = 21.85 m2
Tie Wire (per ton) 0.01 16.73 m2 = 0.17 m2 Tie Wire (per ton) 0.01 21.85 m2 = 0.22 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 18.04 m2 2112 m2/day 141.8 23.21 m2
5) Wastage & 3% 0.54 m2 5) Wastage & 3% 0.70 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 1.80 m2 6) Design & Fluctuati 10% 2.32 m2
Elements RAW COST 20.39 m2 Elements RAW COST 26.23 m2

7) Profit 10% 2.04 m2 7) Profit 10% 2.62 m2


I m2 0.05 20 m2 22.00 m2 22.43 m2 I m2 0.05 20 m2 29.00 m2 28.85 m2
SAY 22.00 m2 SAY 29.00 m2
BRC B9 25.71 m2 BRC B10 30.01 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC B9 1 25.71 m2 = 25.71 m2 BRC B10 1 30.01 m2 = 30.01 m2
Tie Wire (per ton) 0.01 25.71 m2 = 0.26 m2 Tie Wire (per ton) 0.01 30.01 m2 = 0.30 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 27.11 m2 2112 m2/day 141.8 31.46 m2
5) Wastage & 3% 0.81 m2 5) Wastage & 3% 0.94 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 2.71 m2 6) Design & Fluctuati 10% 3.15 m2
Elements RAW COST 30.64 m2 Elements RAW COST 35.54 m2

7) Profit 10% 3.06 m2 7) Profit 10% 3.55 m2


I m2 0.05 20 m2 34.00 m2 33.70 m2 I m2 0.05 20 m2 39.00 m2 39.10 m2
SAY 34.00 m2 SAY 39.00 m2

DTP/MMCG/N4/RB/1 09/04/2020
STRUCTURE - REINFORCEMENT
BRC B11 34.81 m2 BRC B12 44.53 m2
RM RM
1) Material Qty Rate 1) Material Qty Rate
BRC B11 1 34.81 m2 = 34.81 m2 BRC A8 1 44.53 m2 = 44.53 m2
Tie Wire (per ton) 0.01 34.81 m2 = 0.35 m2 Tie Wire (per ton) 0.01 44.53 m2 = 0.45 m2

2) Labour 2 120 /day = 0.65 m2 2) Labour 2 120 /day = 0.65 m2


184 m2 184 m2

3) Machine Qty Rate Total = 0.43 m2 3) Machine Qty Rate Total = 0.43 m2
Crane 1 800 /day 800 /day Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day 2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2 4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 36.30 m2 2112 m2/day 141.8 46.12 m2
5) Wastage & 3% 1.09 m2 5) Wastage & 3% 1.38 m2
Unefficencies Unefficencies
6) Design & Fluctuatio 10% 3.63 m2 6) Design & Fluctuati 10% 4.61 m2
Elements RAW COST 41.02 m2 Elements RAW COST 52.12 m2

7) Profit 10% 4.10 m2 7) Profit 10% 5.21 m2


I m2 0.05 20 m2 45.00 m2 45.13 m2 I m2 0.05 20 m2 57.00 m2 57.33 m2
SAY 45.00 m2 SAY 57.00 m2
BRC B13 50.84 m2
RM
1) Material Qty Rate
BRC B13 1 50.84 m2 = 50.84 m2
Tie Wire (per ton) 0.01 50.84 m2 = 0.51 m2

2) Labour 2 120 /day = 0.65 m2


184 m2

3) Machine Qty Rate Total = 0.43 m2


Crane 1 800 /day 800 /day
Cutting & Bending 2 50 /day 100 /day
2112 m2/day 900 /day
4) Fuel Qty Rate RM 1.8 /day = 0.07 m2
Crane 1 100 lit/day 100 lit/day
Cutting & Bending 2 20 lit/day 40 lit/day
2112 m2/day 141.8 52.49 m2
5) Wastage & 3% 1.57 m2
Unefficencies
6) Design & Fluctuatio 10% 5.25 m2
Elements RAW COST 59.32 m2

7) Profit 10% 5.93 m2


I m2 0.05 20 m2 65.00 m2 65.25 m2
SAY 65.00 m2