Professional Documents
Culture Documents
DATA : Materials
1 Cement : RM 18.00 / bag
2 Sand 1520 kg/ m³ : RM 25.00 / tonne
3 Diesel 1.8 litre / hour : RM 2.00 / litre
4 Lubricant 0.56 litre / day : RM 25.00 / litre
Cement Sand
5 Brick (225mm x : RM 0.25 / no 63 No./m² 1/2 B
75mm)
Clay Brick
6 : RM 0.37 / no 188 No./m² 1B
(225mm x 75mm)
PLANT
1 Hire Crane 16 Tonne (inclusive) : RM 450.00 /day
UNIT : m²
DESCRIPTION : Cement and Sand (1:3) mortar
METHOD : By Machine
DATA : Materials
1 Cement : RM 18.00 / bag
2 Sand 1520 kg/m3 : RM 25.00 / tonne
3 Diesel 1.8 litre / hour : RM 2.00 / litre
4 Lubricant 0.56 litre / day : RM 25.00 / litre
Plant
1 Concrete mixer (10/7) : RM 5,200.00
2 Economic life : 4 Years
3 Interest Rate : 10% / Annum
4 Maintenance Cost : 10% / Annum
5 Transportation Cost : 5% / Annum
6 Resale value : RM
Concrete mixer
7 : 11 Mixes / hour
working intermitantly
RM RM RM
CALCULATION :
A) Material Cost
i) 1 m³ cement x RM 18.00 / bag x 28 bag / m³ 504.00 /m³
ii) 3 m³ sand x RM 25.00 / tonne x 1520 kg / m³ 114.00 /3m³
1000 kg / tonne
618.00 / 4m³
Add : 33% Consolidate & Shrinkage 203.94
8% Wastage 49.44
Cost for 4 m³ = 871.38 / 4m³
1 m³ 217.85 /m³
B) Mixing Cost
1) Capital Cost
i) 1 Concrete mixer (10/7) 5,200.00
0.2 m³ x 11 mixes/hour
2.2 m³/hour
Plant
1 Concrete mixer (10/7) : RM 5,200.00
2 Economic life : 4 Years
3 Interest Rate : 10% / Annum
4 Maintenance Cost : 10% / Annum
5 Transportation Cost : 5% / Annum
6 Resale value : RM
Concrete mixer
7 : 11 Mixes / hour
working intermitantly
RM RM RM
CALCULATION :
A) Material Cost
i) 1 m³ cement x RM 18.00 / bag x 28 bag / m³ 504.00 /m³
ii) 6 m³ sand x RM 25.00 / tonne x 1520 kg / m³ 228.00 /3m³
1000 kg / tonne
732.00 / 4m³
Add : 33% Consolidate & Shrinkage 241.56
8% Wastage 58.56
Cost for 7 m³ = 1,032.12 / 4m³
1 m³ 147.45 /m³
B) Mixing Cost
1) Capital Cost
i) 1 Concrete mixer (10/7) 5,200.00
0.2 m³ x 11 mixes/hour
2.2 m³/hour
Plant
1 Concrete mixer (10/7) : RM 5,200.00
2 Economic life : 4 Years
3 Interest Rate : 10% / Annum
4 Maintenance Cost : 10% / Annum
5 Transportation Cost : 5% / Annum
6 Resale value : RM
Concrete mixer
7 : 11 Mixes / hour
working intermitantly
RM RM RM
CALCULATION :
A) Material Cost
i) 1 m³ cement x RM 18.00 / bag x 28 bag / m³ 504.00 /m3
ii) 1 m³ white lime x RM 2.50 / bag x 15.6 bag / m³ 39.00 /m3
iii) 6 m³ sand x RM 25.00 / tonne x 1520 kg / m³ 228.00 /3m3
1000 kg / tonne
771.00 / 8m3
Add : 33% Consolidate & Shrinkage 254.43
8% Wastage 61.68
Cost for 8 m³ = 1,087.11 / 8m3
1 m³ 135.89 /m³
B) Mixing Cost
1) Capital Cost
i) 1 Concrete mixer (10/7) 5,200.00
0.2 m³ x 11 mixes/hour
2.2 m³/hour
Brick Cement
5 sand(225mm x : / no
75mm) 63 No./m² RM 0.25
Plant
1 Hired Crane 16 tonne : RM 450.00 / day
RM RM RM
CALCULATION :
A) Material Cost
i) Cost of Bricks :
1 Bricks x RM 0.25 /m² x 63 Nos/m² 15.75 /m²
C) Labour Cost
i) 1 Bricklayer x RM 85.00 x 1 hour/m² 10.63 /m2
8 hour/day
Brick Cement
5 sand(225mm x : / no
75mm) 188 No./m² RM 0.25
Plant
1 Hired Crane 16 tonne : RM 450.00 / day
RM RM RM
CALCULATION :
A) Material Cost
i) Cost of Bricks :
1 Bricks x RM 0.25 /m² x 188 Nos/m² 47.00 /m²
C) Labour Cost
i) 1 Bricklayer x RM 85.00 x 1.75 hour/m² 18.60 /m2
8 hour/day
Plant
1 Hired Crane 16 tonne : RM 450.00 / day
RM RM RM
CALCULATION :
A) Material Cost
i) Cost of Bricks :
1 Bricks x RM 0.37 /m² x 63 Nos/m² 23.31 /m²
C) Labour Cost
i) 1 Bricklayer x RM 85.00 x 1 hour/m² 10.63 /m2
8 hour/day
Plant
1 Hired Crane 16 tonne : RM 450.00 / day
RM RM RM
CALCULATION :
A) Material Cost
i) Cost of Bricks :
1 Bricks x RM 0.37 /m² x 188 Nos/m² 69.56 /m²
C) Labour Cost
i) 1 Bricklayer x RM 85.00 x 1.75 hour/m² 18.60 /m2
8 hour/day
5 Vent Block : / no
(225mm x 75mm) 63 No./m² RM 1.80
Plant
1 Hired Crane 16 tonne : RM 450.00 / day
RM RM RM
CALCULATION :
A) Material Cost
i) Cost of Bricks :
1 Bricks x RM 1.80 /m² x 63 Nos/m² 113.40 /m²
C) Labour Cost
i) 1 Bricklayer x RM 85.00 x 1 hour/m² 10.63 /m2
8 hour/day