Testing and Commissioning of Fire Fighting System Hose

Reel and Sprinkler System


The purpose of this procedure is to define the step by step method to implement the
correct practices for the precommissioning & commissioning of “Fire Fighting System”
through the guidelines contained herein so as to ensure that the job execution complies with
the project requirements and serves the intended function to satisfactory level.

Pre Commissioning Procedure for Fire Fighting System


1. Ensure that the system installation is complete and mechanical completion is
approved.
2. Ensure that no damage has occurred between mechanical completion & pre-
commissioning.
3. Repair all damages to the equipment & piping.
4. Check that the Fire Fighting piping network is complete with fire hose reel, cabinet,
pressure gauge, fire extinguishers proper valves, drains vents strainers pressure
switches instruments & sprinklers drains, vents, strainers, switches, in place as per
final approved shop drawing.
5. Ensure that the Fire Fighting network is hydraulically pressure tested and approved.
6. Ensure that the entire system is cleaned internally & externally.
7. Ensure that the Fire Fighting pumps are pre-commissioned & commissioned as per
approved procedure.
8. Ensure all the pressure switches are installed & wired properly.
9. Ensure that all supervisory isolation valves & sectional control assembly valves are
installed & wired.
10. Ensure that all drain valves & vents are installed.
11. Ensure that the identification of all valves & pipework is complete.
12. Ensure the wiring to the Fire Alarm from the pump panel is complete.
13. Ensure that the BMS connections are complete.
14. Ensure that the wiring diagram of pump set controls & schematic piping drawings are
displayed near or inside the pump panel.

Commissioning Procedure for Fire Fighting System

1. Ensure that all the pre-commissioning checks are carried out successfully.
2. The Fire Fighting system shall be completed tested for proper sequence of operation
as defined below.

System Description

1. The Fire fighting system comprises of 3nos. (2 main & 1 standby) single suction,
horizontal multi stage, multi outlet pumps & 2nos. vertical multi-stage type jockey
pumps (one for low zone and other for high zone) to supply firewater to sprinkler and
fire hose systems. All the pumps have dedicated control panel & pressure switches.
2. The Sprinkler system in the Tower H and J are divided into two zones, low zone and
high zone. Low zone includes Car park and Ground floor to 15th floor of Towers &
the High zone includes 16th floor to roof of Towers.

Page 1 of 3
3. The Wet riser piping, which supplies firewater to all hose reels and hose racks, is
classified as high zone for the complete project with PRV for all cabinets. The
precommissioning & commissioning of Hose racks & Hose reels shall be in line with
the approved procedure

Sequence of operation

High Zone – 16th floor to Roof

1. System pressure will be maintained always at 6.9 bar (min). In the event of water
consumption in the fire protection system zone-1&2 areas due to any reasons, the
pressure in the zone-1&2 system piping will fall down.
2. Once the pressure reaches below the minimum value the flow switch give signal to
the fire alarm system zone wise.
3. Pressure prop in the main line in Alarm check valve will activate Water Alarm Gang
at 4bar pressure
4. Firefighting system will continue to run till the pressure reaches 6.9 bar (min).
5. While the Main Fire Fighting pump (FP-UG-01) is in operation and if the pressure
drops further to cut in pressure of HZPS2 (13.00 bar), then Main Fire Fighting pump
(FP-UG-02) will start and both the main pumps will run. Main Fire Fighting pumps
(FP-UG-02 and FP-UG-03) will continue to run till the pressure reaches the cut out
pressure of HZPS1 and HZPS2 (16.0 bar).
6. While both the Main Fire Fighting pumps (FP-UG-01 and FP-UG-02) are in operation
and due to any reasons any one of the main pump fails to work, if the pressure drops
further to cut in pressure of HZPS3 (12.50 bar), then the Standby Fire Fighting pump
(FP-UG-03) will start and both the Main Fire Fighting pump and Standby Fire
Fighting pump will continue to run till the pressure reaches the cut out pressure 16.0
bar.

Low Zone – Ground Floor, carpark to 15th floor

1. System pressure will be maintained always at 10 bar. In the event of water


consumption in the fire protection system low zone areas due to any reasons, the
pressure in the low zone system piping will fall down. When the pressure reaches 9.00
bar, Pr. Switch LZPS4 will cut in and the low zone Jockey pump (FP-UG-05) will
start. If pressure in the system piping reaches to the cut out pressure of LZPS4 (10
bar), then the low zone Jockey pump will stop.
2. While the low zone Jockey pump is in operation, if the pressure drops further to cut in
pressure of LZPS1 (8.00 bar), then Main Fire fighting pump (FP-UG-01) will start
and jockey will stop. Main Fire Fighting pump will continue to run till the pressure
reaches the cut out pressure of LZPS1 (10.0 bar).
3. While the Main Fire Fighting pump (FP-UG-01) is in operation and if the pressure
drops further to cut in pressure of LZPS2 (7.00 bar), then Main Fire Fighting pump
(FP-UG-02) will start and both the main pumps
will run. Main Fire Fighting pumps (FP-UG-02 and FP-UG-03) will continue to run
till the pressure reaches the cut out pressure of LZPS1 and LZPS2 (10.0 bar).
4. While both the Main Fire Fighting pumps (FP-UG-01 and FP-UG-02) are in operation
and due to any reasons any one of the main pump fails to work, if the pressure drops
further to cut in pressure of LZPS3 (6.50 bar), then the Standby Fire Fighting pump
(FP-UG-03) will start and both the Main Fire Fighting pump and Standby Fire

Page 2 of 3
Fighting pump will continue to run till the pressure reaches the cut out pressure 10.0
bar.

Demonstration procedure

High Zone

1. The water in the system shall be allowed to drain vide the high zone Alarm Control
Valve. This will reduce the pressure in the system & the jockey pump will start.
2. More water shall be allowed to drain to further drop the pressure, then the Duty pump
FP-UG-01will start, the jockey pump will stop.
3. Upon confirming the start of the main pump, the discharge valve shall be throttled &
the pump FP-UG-01 will not be able to cater to the pressure drop in the system & the
other duty pump FP-UG-02 will start.
4. The discharge of the pump FP-UG-02 will also be throttled, which will initiate the
starting of the stand-by pump FP-UG-03.
5. The start & stop of the pumps shall be as per the pressure settings.

Low Zone

The low zone shall be tested in the same way as high zone, but by using the Alarm Control
Valve for the low zone.

Sprinkler System

1. The sprinkler system will be tested using the Sectional Control Assembly. The test &
drain valve shall be opened in each zone and the following shall be verified.
a. Flow switch will activate & give signal to Fire Alarm System
b. Fire Alarm System will induce an audible alarm.
c. Jockey pump will start automatically.

SIGNALS TO BMS PANEL

1) Pumping running status.

2) Pump trip status

ATTACHMENTS

 Pre-commissioning check sheet for Fire Fighting System


 Commissioning check sheet for Fire Fighting System
 Risk Assesment