Professional Documents
Culture Documents
1. Ensure that all the pre-commissioning checks are carried out successfully.
2. The Fire Fighting system shall be completed tested for proper sequence of operation
as defined below.
System Description
1. The Fire fighting system comprises of 3nos. (2 main & 1 standby) single suction,
horizontal multi stage, multi outlet pumps & 2nos. vertical multi-stage type jockey
pumps (one for low zone and other for high zone) to supply firewater to sprinkler and
fire hose systems. All the pumps have dedicated control panel & pressure switches.
2. The Sprinkler system in the Tower H and J are divided into two zones, low zone and
high zone. Low zone includes Car park and Ground floor to 15th floor of Towers &
the High zone includes 16th floor to roof of Towers.
Page 1 of 3
3. The Wet riser piping, which supplies firewater to all hose reels and hose racks, is
classified as high zone for the complete project with PRV for all cabinets. The
precommissioning & commissioning of Hose racks & Hose reels shall be in line with
the approved procedure
Sequence of operation
1. System pressure will be maintained always at 6.9 bar (min). In the event of water
consumption in the fire protection system zone-1&2 areas due to any reasons, the
pressure in the zone-1&2 system piping will fall down.
2. Once the pressure reaches below the minimum value the flow switch give signal to
the fire alarm system zone wise.
3. Pressure prop in the main line in Alarm check valve will activate Water Alarm Gang
at 4bar pressure
4. Firefighting system will continue to run till the pressure reaches 6.9 bar (min).
5. While the Main Fire Fighting pump (FP-UG-01) is in operation and if the pressure
drops further to cut in pressure of HZPS2 (13.00 bar), then Main Fire Fighting pump
(FP-UG-02) will start and both the main pumps will run. Main Fire Fighting pumps
(FP-UG-02 and FP-UG-03) will continue to run till the pressure reaches the cut out
pressure of HZPS1 and HZPS2 (16.0 bar).
6. While both the Main Fire Fighting pumps (FP-UG-01 and FP-UG-02) are in operation
and due to any reasons any one of the main pump fails to work, if the pressure drops
further to cut in pressure of HZPS3 (12.50 bar), then the Standby Fire Fighting pump
(FP-UG-03) will start and both the Main Fire Fighting pump and Standby Fire
Fighting pump will continue to run till the pressure reaches the cut out pressure 16.0
bar.
Page 2 of 3
Fighting pump will continue to run till the pressure reaches the cut out pressure 10.0
bar.
Demonstration procedure
High Zone
1. The water in the system shall be allowed to drain vide the high zone Alarm Control
Valve. This will reduce the pressure in the system & the jockey pump will start.
2. More water shall be allowed to drain to further drop the pressure, then the Duty pump
FP-UG-01will start, the jockey pump will stop.
3. Upon confirming the start of the main pump, the discharge valve shall be throttled &
the pump FP-UG-01 will not be able to cater to the pressure drop in the system & the
other duty pump FP-UG-02 will start.
4. The discharge of the pump FP-UG-02 will also be throttled, which will initiate the
starting of the stand-by pump FP-UG-03.
5. The start & stop of the pumps shall be as per the pressure settings.
Low Zone
The low zone shall be tested in the same way as high zone, but by using the Alarm Control
Valve for the low zone.
Sprinkler System
1. The sprinkler system will be tested using the Sectional Control Assembly. The test &
drain valve shall be opened in each zone and the following shall be verified.
a. Flow switch will activate & give signal to Fire Alarm System
b. Fire Alarm System will induce an audible alarm.
c. Jockey pump will start automatically.
ATTACHMENTS
Page 3 of 3