PRODUCTIVITY ASSIGNMENT
Compute the multifactor productivity measure for each of the weeks shown. Assume 40-hour weeks and
hourly wages of Php 50. Overhead is 1.2 times weekly labor cost. Material cost is Php 300 per pound.
1 40000 5 420
2 45000 6 490
3 50000 6 480
4 55000 6 500
Answer here--------
Wee Outpu Labor Cost Material Cost Overhead Total Cost Productivity
k t Cost
(4Ohrs.*Ph (300*MATERIAL (LC+MC+O (OUTPUT/TOT
p 50*#OF S) (LABOR C) AL COST)
WORKER COST*1.
S) 2)