Professional Documents
Culture Documents
Malonia
C'nojee mamagemot: Deals uwh 1 Mampoe
2. Humam taals
3. Machinexy| quipmails
Obecliues o a Pouuja
m minimum ime wth muniumum Coputal
. s h u l d . be complolod
inueamomu.
aualabte mampowe & Ch JOJowLOg opumall
e 9t should e
FEATURES
4. I t o a piclotial chait.
. Ithas uod co-ctudimato ais;
houolal aris opoets elapaedume
Olicol acis the job otadiutto be pouotumod.
3. Jhe beinmima & emd on ench kat
oposemia doding&
inihimg ime o o poieulat aluity naspaaliue
JUn b L a ,
LTmITATIONS
A. Lock o eoe o slail
em majdu aluitios a a shmwn in ba Chadamd eubactiiuitis
com t be siponaiTod out.
Hemce, eHechue coribroe ourihe ndluiias in biR puokcta cant
he achiedu.
. A boou .dhad doeSMob Shou p 0 3 oh wotk & hence cam t b
Used. ab a Conhot deuuce
nablo to dopict unodagomdemcies ounisus actiilias dReae..
4. Nol sekul, in the projecb uhethea oe ncTa irilios im
ddumimaliom o esimolim o ime MOq\uod 1o compkoem
wouos ocuutios" Such 0s im R&D pedib.
blw itical & mon-culical adtuitiha
5. Badhaus can't ditimguish
Cam't be done..
&fence NODUNCA Imodlhertng& JAJDMCe LaeWing
MILESTONE CHART
I t is a mpditicadin olo b a t Chab.
ba.
ORosonos ko euonls OL maim Aõinitios epro20ods b
aje
NETWORk ME THOD
Aulcome o ho mphuovemonts in the mileslone chats.
Seme Nawotk Mahods at: PERT, CPM, UNETACS, LESs, ToPs
& SCANS,
-3
2)
-
Fig.1.7 Successor Events
Do you know? It should be noted there can be only one tail event and one head event in a project.
1.5.2 Activity
Activity is actual performance of a job. It requires time and resources for its completion.
Following are examplesofan activity:
1. Excavate trench 2. Mix Concrete 3. Prepare budget
Do
InA-O-Asystem (ActivityOnArrow network system), activity is represented by arrows between
events while in A-O-N (Activity On Node system), activities are represented by nodes. In
You A-O-N system, events have no places.
Know
2 B 3)
AAONB
A-O-A
Fig. 1.8 Fig. 1.9
1.5.3 Dummy
A dummy is a type of operation which neither requires time nor any resource, but it denotes
dependency among the activities.
It is represented by dashed arrow.
In the figure shown below, a dummy activity is shown.
3
Dummy activity
D
(
B
B
Dummies are used to show predecessor relation but if that relation is already established
Do in the network, then that dummy is redundant and has to be removed.
You
If dummy is only incoming/outgoing arrow to/from a node then it can be remove provided
Know there is no logical or grammatical error.
Errors in Network
1. Looping error: Loops should not be formed.
C
Wrong Right
P S
(2)
R
TRE EAS
Fig. 1.13 Dangling Erof Cations
To avoid dangling error, the network must be examined in such a manner that all events exceptinitial
and final events must have at least one activity entering and one activity leaving them.
3. Wagon wheelerror: As shown in figure, each of the activities P, Qand Rcannot start until all the
3.
threeactivities A, B and Care completed. But in reality, this may not be the situation. There is no
error visible in the construction of diagram but logical error has crept intoit.
B Q
R
C