Professional Documents
Culture Documents
TABLE OF CONTENTS
1. INTRODUCTION...................................................................................................................................1
2. COMPOSITION AND CONTENTS OF F/S REPORT..................................................................................1
2.1 Composition of F/S......................................................................................................................1
2.1.1 Volume 1A...........................................................................................................................1
2.1.2 Volume 1B............................................................................................................................1
2.1.3 Volume 2..............................................................................................................................2
2.1.4 Volume 3..............................................................................................................................2
2.1.5 Volume 4..............................................................................................................................2
2.1.6 Drawings..............................................................................................................................2
2.2 Objectives of the F/S Study..........................................................................................................2
2.3 Scope of Work.............................................................................................................................3
2.3.1 Traffic Survey and Demand Forecast...................................................................................3
2.3.2 Selection of Alignment and Preliminary Designs..................................................................3
2.3.3 Rolling Stock and System Studies.........................................................................................4
2.3.4 Specification for the Project.................................................................................................4
2.3.5 Preliminary Cost Estimate....................................................................................................5
2.3.6 Environmental and Social studies........................................................................................5
2.3.7 Financial and Economic Studies...........................................................................................5
2.3.8 Institutional Capacity Studies...............................................................................................6
3. DETAILED REVIEW RESULTS OF F/S......................................................................................................6
3.1 Railway Alignment.......................................................................................................................6
3.1.1 Review Results of Design Criteria.........................................................................................6
3.1.2 Review Result of Trackbed...................................................................................................7
3.1.3 Railway Route Status...........................................................................................................9
3.1.4 F/S Route Status Comparison............................................................................................10
3.1.5 F/S Route Comparison (Recommended Route vs. Alternative Route)...............................11
3.1.6 Review Result (F/S Recommended Route vs. F/S Alternate Route)...................................12
3.1.7 F/S Alignment Evaluation...................................................................................................13
3.1.8 F/S Alignment Review and Improvement Measures..........................................................15
3.1.9 Comprehensive Review Result...........................................................................................25
3.2 Bridge........................................................................................................................................26
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV i
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV ii
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV iii
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
LIST OF TABLES
Table 1 Salient Features and Description of the Project.........................................................2
Table 2 Comparison Results for Design Criteria of Railway..................................................6
Table 3 Earthwork of Banking Cross Section.........................................................................7
Table 4 Earthwork of Cutting Cross Section...........................................................................8
Table 5 Type of Retaining Wall..............................................................................................9
Table 6 Application in Banking Area......................................................................................9
Table 7 Application in Cutting Area.......................................................................................9
Table 8 F/S Route Comparison (1).......................................................................................11
Table 9 F/S Route Comparison (2)........................................................................................12
Table 10 Composition of Trackbed.......................................................................................12
Table 11 Horizontal Alignment Status..................................................................................14
Table 12 Vertical Alignment Status......................................................................................15
Table 13 Comparison F/S Alignment....................................................................................16
Table 14 Salient Features of Koshi Tappu Wildlife Reserve and Buffer Zone....................17
Table 15 Bardibas Station Section (106km000~118km000(L=12km000))..........................23
Table 16 Sta.118km000~197km000(L=79km000)...............................................................23
Table 17 Sta.197km000~243km000(L=46km000)...............................................................25
Table 18 Comparison of Alignment......................................................................................26
Table 19 Major Design Criteria.............................................................................................27
Table 20 Standard Type of Superstructure............................................................................28
Table 21 Statement of Road Under Bridge...........................................................................29
Table 22 Statement of Minor Bridge.....................................................................................30
Table 23 Statement of Major Bridge.....................................................................................30
Table 24 Application of Structure.........................................................................................31
Table 25 Application of Substructure...................................................................................32
Table 26 Application of Foundation.....................................................................................32
Table 27 Statement of Major Bridge (on the F/S Report).....................................................33
Table 28 Statement of Minor Bridge (On the F/S Report)....................................................34
Table 29 Statement of Road Under Bridges (RUB's) (On the F/S Report)..........................37
Table 30 HFL at crossings of Bardibas-Inaruwa Alignment................................................42
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV iv
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV v
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
TABLE OF FIGURES
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV vi
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1. INTRODUCTION
This Review Report has been prepared as per the agreement signed between Government of
Nepal (GoN), Ministry of Physical Infrastructure and Transport, Department of Railways,
Railway and Monorail Development Project and Yooshin Engineering Corporation
(YOOSHIN), Korea in JV with Korea Rail Network Authority (KRNA), Balaji Railway
System Limited (BARSYL) India, Korea Railroad Technical Corporation (KRTC), Korea,
Full Bright Consultancy (Pvt. Ltd) (FBC), Nepal in association with Birat Infrastructure
Development (P) Ltd. (BID), Nepal on July 6, 2016 in accordance with the Terms of
Reference (ToR) provided to the Consultant for carrying out Detailed Survey and Design of
Electrified Railway Line (HSR) of Bardibas-Inaruwa Sector of Mechi-Mahakali
Railway(Package-1).
The Consultant has reviewed the findings and recommendations made in the Feasibility
Study Report (F/S Report) prepared by RITES Ltd. in association with SILT Consultants
for Feasibility Study of Mechi - Mahakali and Pokhara – Kathmandu Electrified Railway.
The final Feasibility Study Report was submitted in August 2010 to the Railway
Construction Project under MoPIT of the Government of Nepal. This report has further
recommended revision/update on some findings and recommendations made in the
Feasibility Report considering both suitability and latest technology available in the railway
sector.
2.1.1 Volume 1A
Volume 1A contains Executive Summary and a part of the main report, which includes
general description, objectives of study, scope of works along with technical component like
traffic and demand forecast, selection of alignment, general design specifications and
preliminary design specifications for civil structures and signaling and telecommunications.
2.1.2 Volume 1B
Volume 1B contains a part of the main Report and deals with preliminary design
specifications of overhead electrical equipment, power supply and selection of electric
locomotives, selection of wagons, coaches and shunting engines, train operation and
maintenance organisation and maintenance methodology, abstract cost estimates,
construction schedule and institutional framework for construction, financial and economic
appraisal.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 1
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
2.1.3 Volume 2
Volume 2 of the Report describes geological studies and construction material investigation,
hydrological studies, environmental and social impact study.
2.1.4 Volume 3
Volume 3 of the Report depicts the main features of the project giving summary of salient
features of Nepal Railway Project. It has included the salient features of the following eight
sections of the project, together with four connections as given in Table 1
2.1.5 Volume 4
Volume 4 of Report contains the cost estimate of the Project, which includes the cost of total
Project along with separate cost estimate for each section. Further, it also contains the unit
rate analysis of various items of works as required to come up with the Project.
2.1.6 Drawings
A compilation of drawing were submitted covering all aspects of the Project as required for
the feasibility study.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 2
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 3
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 4
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 5
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 6
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Feasibility
Study
Detail Design
Review
Height Slope
Roadbed Width : min. more than
8.0m H<3.0m 1:1.8
Install 1.5m of berm every 6.0m 3.0m≤H<9.0m 1:1.8
Berm side ditch inclination 5% 9.0m≤H<15.0m 1:2.0
Banking slope inclination
H≥10.0m 1:2.3
Feasibility report has applied, banking trackbed width as 6.85m.
Trackbed width will have the width for at least securing safe train
operation, maintenance and stabilizing the ballast.
So, the trackbed width will be at least 8.0 m or wider.
The slope inclination will be uniformly set as 1:2, which will be compensation
for land and earthwork quantity etc.
Review The final inclination will be determined
Opinion based on the reviewed option,
considering the form and strength of
the banked area's supporting
foundation.
Considering the poor ground condition,
risk of erosion by torrential rain, ballast
settlement and train operation safety,
the reinforced trackbed is to be installed.
*Design Criteria related matters can be changed based on ground conditions.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 7
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
b) Cutting Section
Feasibility
Study
Detail Design
Review
Height Slope
Roadbed width : min. more than
8.0m Sand 1:1.5 & over
Install 1.5m of berm every 5.0m Weathered rock 1:1.2 & over
Berm side ditch inclination 5% Soft rock 1:0.7
Slope inclination
Hard rock 1:0.5
Feasibility study has applied, cutting trackbed width as 6.25m. Cutting
trackbed width will considered to be at least 8.0m.
The cutting slope inclination is uniformly set as 1:1, which will be
Review economically unfeasible.
Opinion Therefore, the final inclination will be determined based on the form and
strength of the soil/rock layer and interpretations of the stability of the
slope.
If necessary, slope stability analysis will be performed.
*Design Criteria related matters can be changed based on ground conditions.
2. Retaining Wall
Retaining wall should be of proper design, height and width and form to prevent water
infiltration on existing roads, or to decrease banking and excavation volume. Retaining wall
shape should be as shown below. Height is typical in railway retaining wall. But, if
construction materials (ex. Concrete, Steel bar) will allow the resistance of strength,
maximum application height should be changed as high as possible
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 8
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Buttress type retaining wall will be avoided as much as possible due to difficulty in
construction as well as expensive.
ⅰ) Application Plan
Cross
Section
Cross
Section
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 9
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
In Section 6, the initial Feasibility Study Report (F/S Report), comparative studies have been
made between two alternatives – the line parallel to Koshi barrage at about 500m upstream
and the other one bypassing Koshi Tappu Wildlife Reserve from northern side and the F/S
Report has recommended the line parallel to Koshi Barrage.
The F/S Report has evaluated that the alternative with the border-city crossing line would
have advantages of generating earnings and expanding services. Therefore, the F/S Report
recommended the railway route the line running parallel to the East-West Highway (EWH)
and crossing upstream of Koshi Barrage.
The railway route map is shown below:
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 10
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1) Alternative Route
The route departing from Bardibas Station, passing through Lahan and Phattepur along the
EWH by passing Koshi Barrage and Koshi Tappu Wildlife Reserve, connects to Itahari. This
option has a social benefit as it minimizes interaction with the Koshi Barrage, and the
Mohanpur~Phattepur~Itahari section can be used to connect northern part and Dharan areas
which will serve the residents of those areas.
The drawback is that the line is elongated by 11km717 compared to the other option,
entailing system construction cost increase and as there is restriction on operation speed due
to topographic conditions, this option is deemed competitively inferior.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 11
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Tunnel - - -
3.1.6 Review Result (F/S Recommended Route vs. F/S Alternate Route)
F/S recommended route is deemed more plausible than the option route in every respect.
The review shows that F/S recommended route for the Bardibas~Mohanpur~Inaruwa section
is more beneficial than the F/S Alternate route (Bardibas-Mohanpur-Chatara-Ithari) in terms
of economic efficiency, and operability.
In the F/S Alternate case,
Extension (about 11km717) of alignment length.
Low operating speed and delayed operation time due to the unfavorable alignment
condition as follows
- Increase in running time of the train because of number of curves with the
minimum curve radius (R=350m) and extended long alignment length.
- Increase in total construction cost and future operation and maintenance cost
A review of the routes shows that F/S's recommended route is more feasible than the
alternative route. Therefore, the recommended route is chosen, but the Consultant plans to
analyze the alignment of this option, deduce improvement measures in terms of economic
efficiency and operability and reflect the result in the detail design.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 12
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Section 5: Bardibas~Lahan
- Line Length : 66km130 (53km000~119km130)
- Line Length of TOR : 63km130(56km000~119km130)
Section 6: Lahan~Inaruwa
- Line Length : 73km870 (0km000~73km870)
Bardibas~Inaruwa
- Total Line Length : 140km000 (53km000~193km000)
- Total Line Length of TOR : 137km000(56km000~193km000)
Note: The starting point of Bardibas-Inaruwa Sector in the TOR and the end point of Detail Survey
and Design of Electrified Railway Line of Simara-Bardibas are different.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 13
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Number of station is 14
This review Report was based on the endpoint (Sta.106km000) of Project section (Simara ~
Bardibas) of which Detail Survey and Design was carried out in 2012-13.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 14
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 15
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 16
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Most of the north residents of Koshi Tappu Wildlife Reserve and Dharan area
cannot be avail the railway facility because it does not pass through their
village/city.
Therefore, detail design will be conducted based on F/S recommended alignment through
consultations, meetings and presentations to the Client and other concerned stakeholders.
2. Factors to be considered as selecting alignment:
i) Factors to be considered
There are many factors for choosing optimal alignments like economic feasibility,
constructability, train operation, passenger’s convenience including minimal effect to
environment and wildlife.
ii) Status on wildlife in Koshi Tappu area
According to the meeting with warden office officials in Koshi Tappu Wildlife Reserve,
there are many precious plants and animals including wild buffalo and elephant, gharial
crocodile, dolphin, etc. The background and status of major flora and fauna in Koshi Tappu
is shown below:
Table 14 Salient Features of Koshi Tappu Wildlife Reserve and Buffer Zone
Wildlife Reserve Gazetted 86°55’15” - 87°05’02” E
1976 AD Location
year 26°33’57” - 26°43’40” N
Reserve Area 175㎢ Climate Tropical monsoon climate
Buffer Zone Area 173㎢ Districts Sunsari, Saptari and Udayapur
Buffer Zone declared year 2004 AD VDCs 16
IUCN Category Ⅳ Physiographic region Terai
Ramsar Site declared year 1978AD Biogeographical region Indo-Malayan
Landscape Large floodplain made by Koshi and Trijuga Rivers
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 17
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 18
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 19
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
A narrow gauge line was running by the Government of Nepal (GoN) from Jaynagar
Station (India) and Janakpur (Nepal). The GoN desires to expand the gauge and is
planning to construct a new railway line in the same section under the financial
assistance of its Indian counterpart.
- Jayanagar - Janakpur Section: Gauge expansion (narrow → broad gauge)
- Janakpur – Bardibas Section: New railway (broad gauge) construction
According to the FS, the Jayanagar-Janakpur-Bardibas Railway Line is planned to be
connected to the Bardibas Station. In the detailed design stage, the Consultant will
extensively sought out feasible means to reduce the bridge construction cost or even
alternative routes in case the curve radius increases (1,000m→3,100m). The
Bardibas Station will be reviewed from the perspective of accessibility with from
adjacent cities (See above Figure).
The Jayanagar (India)-Janakpur-Bardibas Railway Line will be modified following
potential changes in the starting point and/or the Bardibas Station.
The Consultant deems it necessary to consider changes regarding the aforementioned
criteria with applicable agencies and stakeholders
The alternative alignment sectors during the presentation discussed were Alternative
Alignment A1 and A2
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 20
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
The main section will be designed in accordance to the high speed railway operation
standards and guidelines described in the TOR. For a design speed of 250Km/hr, the
minimum curvature radius will be 3,100m or greater.
The operational speed can only be determined based on the minimum curvature
radius. If the minimum radius of curvature becomes larger, the operational speed
can also increase. In such the scenario, the construction cost is likely to increase as
well. On the other hand, if the minimum radius of curvature becomes smaller, the
construction cost might decrease but operational speed will suffer.
The new railway will be constructed in the project section where the land is mostly
leveled and flat. This implies that the difference in the construction cost will be
minimal regardless of designing the track with a minimum radius of curvature
R=3,100m for a design speed of 250km/hr. Especially, since the roadbed structure is
almost permanent once it has been constructed, Accordingly, the Consultant will
consider any future speed increase at sections with curve radius of 3,100m or larger.
The FS alignment will be modified to minimize any geographical overlap with
existing obstacles while meeting high-speed railway operational conditions (i.e.,
minimum radius of curvature). (See the table in above figure)
c) Section C: Koshi Tappu Area (Wildlife Reserve Area, Buffer zone, Koshi
Barrage)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 21
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
The Consultant will work out a better solutions for crossing the Sapta Koshi River.
According to the F/S, alternative alignments are designed with a bridge over the
Koshi River by detouring the Koshi Tappu Wildlife Reserve Area; or the railway line
will be linked to the Inaruwa Station in the shortest distance by partially overlapping
the Koshi Tappu Wildlife Reserve Protected Area with a bridge upstream of the
Koshi Barrage (about 500m).
The Consultant suggests that the alignment of the F/S alternative routes be modified
to meet HSR operational conditions (V=250km/hr) as per the provisions in the TOR.
Alignment No. 1: As a detour route avoiding passing through the Koshi Tappu
Wildlife Reserve area, the route crosses the Koshi Barrage upstream (about
3.4~6.4km) with the Sapta Koshi River. However, this alignment will increase the
minimum required bridge length. In addition, this alternative is highly likely to affect
the residential and commercial areas in Bhantabari, adjacent to the national border
with India
Alignment No. 2: As a northern detour of the Koshi Tappu Wildlife Reserve
Protected Area, the route crosses the Sapta Koshi River (about 28 km) from the
Koshi Barrage area. Compared to Alignment No. 1, this alternative is clearly
preferable in terms of alignment conditions, total distance, and operation. However,
this alternative will increase the length of the bridge leading to increase in
construction costs. Accessibility for the residents of Bhardaha, Bhantabari, Haripur
Chowk, Laukahi, and Inaruwa will be worse affected than the above alternative.
Alignment No. 3: As a complementary alignment for the problem of track
improvement for the operation of high speed railway and review of alignment No.1,
it is necessary to consult with related government agency due to conflict with Koshi
Tappu Wildlife Reserve protected area.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 22
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 23
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
d) Sta.118km000~197km000(L=79km000)
Kusumbisauna ~ Mohanpur is paralled with the east-west highway, and generally pass
through the small towns and rivers, mainly in plain area.
The Consultant will modify the F/S route in detail in consideration of obstacles such as
highways, cannels, power transmission lines, towns, factories, etc.
Figure 16 Sta.118km000~197km000(L=79km000)
Table 16 Sta.118km000~197km000(L=79km000)
SN F/S Report Improvement Review Alignment
Line Length 63km410~144km129(80km719) 118km000~197km000(79km000)
Number of Stations 8 8
Min. Curve Radius 2,000m 3,500m
Number of Curves 22 5
Curve Length 23km533 13km237
Compared to F/S alignment, there might be cost saving by shortening of
route length (L=1km719). And the efficiency of train operation will be
Detail Design
better through increased radius and straightened alignment.
Review
Also reasonable size of station will be planned in consideration of traffic
demand and operation pattern.
e) Sta.197km000~243km000(L=46km000)
Mohanpur ~ Itahari section crosses Koshi River detouring Koshi Tappu Wildlife Reserve
area and the Koshi Barrage.
In the F/S, the alignment was recommended upstream of the Koshi Barrage (500m).
The optimal route will be selected by the comparison of pros and corns of Alt.1, 2 and 3.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 24
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Figure 17 Sta197km000~243km000(L=46km000)
Table 17 Sta.197km000~243km000(L=46km000)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 25
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Number of Stations 5 5
Min. Curve Radius 1,500m 3,100m
Number of Curves 16 6
Curve Length 20km042 12km410
Compared to F/S alignment, there might be cost saving by shortening of
route length (L=3km000). And the efficiency of train operation will be
better through increased radius and straightened alignment.
Detail Design The construction cost will be saved by deleting 10 curves, enlarging min.
Review radius (R=1,500m⇒ R=3,100m), planning straight station.
Also train operation speed will be increased.
Also train operation will be more efficient accordingly to the train speed
will be faster.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 26
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Review Result 1) This review Report was based on the start point(Sta. 106km 000)
of the project section (Simara ~ Bardibas)
2) New Alignment(ALT.1) has the following advantages:
Alignment improvement through reduction of curves
Shorten 6.15km in length
Minimal environmental damage
Improvement of straight alignment
Installation of the linear station
Efficient train operation
Improvement of workability
3) The Consultant recommends new Alignment (ALT.1) because of
the advantages above.
3.2 BRIDGE
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 27
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 28
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
For railway bridge, general type of superstructures used are prestressed concrete T beam and
slab, prestressed concrete rigid frame, prestressed concrete box girder, and for larger spans
steel bridges. Simply supported span are preferred for railway bridges.
After reviewing the F/S Report, it is found that the following types of superstructures are
used for different bridges.
The summary of standard type and spans available are given below.
3 Plate Girder 12.2m ,18.3m and 24.4m Steel I Girder without Deck Slab
4 Composite Girder 12.2m, 18.3m and 30.5m etc Steel Girder with Deck Slab
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 29
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
This type of foundation is easier to construct, maintenance is easy and is cheaper than pile or
well foundations.
5) F/S Bridge Status
After reviewing the types of superstructures proposed in the feasibility Report, the proposal
by the design Consultants is shown on the tables below. As per the site condition,
considering the structure on the East-West Highway, and international practice the following
superstructure types are proposed by the design Consultant in the statement of Major
Bridges. However, at present, no suggestion has been made for minor bridges and road
under bridges, they are similar as proposed in the F/S Report.
Detailed status of bridges in F/S Report are shown on Table 21 and Table 22.
The bridges in F/S Report are summarized in table below
ⅰ) Statement of Road Under Bridge
The span length is the distance from the front of the pier to the next pier's front.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 30
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 31
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Composite Steel Girder with Not Recommending (if possible) because of difficulty
4 Deck Slab (12.2m, 18.3m and in construction and maintenance considering the
30.5m) situation in Nepal
1) Application of Substructure
We considered optimum pier type by reviewing the superstructure type, spans and of 1 st
stage project
The selected pier type minimizes the impact on water flow in river sections.
Pier
Solid circular type Solid circular type
(up to 20m)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 32
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Semi-gravity Type
(Height 3~7m)
Abutment No recommendation
Reverse T Type
(Height 6~20m)
2) Application of Foundation
Open foundation are sited in a location where rock or Use open spread foundation
1
firm founding soil is available at a willow depth. available
Pile foundation are suitable to use in cohesive soils Use in situ concrete pile
2
and beds subject to minimum scour foundation
Use in situ concrete pile
Well foundations are more suitable for larger spans
3 foundation
and high scourable rivers.
(Larger diameter bored piles)
3) Summary
After detail survey, geotechnical and hydrological investigation, the location, types of
foundation, substructures, superstructures of the bridges and crossings will be determined
more precisely and accordingly the changes in foundation, substructure, and superstructure
and the their construction materials will be made to achieve economy and safety of the
structures during design.
Name of
Classificatio Chainage
Road/River/Khol Type of Bridge Span(m) Remarks
n (km) a
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 33
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
103.24
20 Mainawati Khola PSC Girder 8×12.2
3
106.76
21 Gagan Khola PSC Girder 10×18.3
5
115.91
22 Canal PSC Girder 1×18.3
3
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 34
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Mahuli Dhar
39 48.430 PSC Girder 3×12.2
Khola
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 35
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 36
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Table 29 Statement of Road Under Bridges (RUB's) (On the F/S Report)
Name of
Classif Chainage
Road/River/Khol Type of Bridge Span(m) Remarks
ication (km)
a
SEC. 1 58.380 Unmetalled Road RCC Box 1×5×5
2 59.666 Unmetalled Road RCC Box 1×5×5
5
3 62.150 Unmetalled Road RCC Box 1×5×5
Metalled Road
4 62.904 RCC Box 2×6.25×5.5
Highwayay
5 63.817 Unmetalled Road RCC Box 1×5×5
6 64.909 Unmetalled Road RCC Box 1×5×5
7 66.686 Unmetalled Road RCC Box 1×5×5
8 77.219 Unmetalled Road RCC Box 1×5×5
9 78.758 Unmetalled Road RCC Box 1×5×5
10 80.514 Unmetalled Road RCC Box 1×5×5
11 81.126 Unmetalled Road RCC Box 1×5×5
12 82.417 Metalled Road RCC Box 1×5×5
13 85.776 Unmetalled Road RCC Box 1×5×5
14 86.812 Unmetalled Road RCC Box 1×5×5
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 37
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 38
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
The monsoon period is from the end of June to the middle of August. About 80 percent of
the rain falls during that period, so the remainder of the year is dry. Spring and autumn are
the most pleasant seasons; winter temperatures drop to freezing level with a high level of
snowfall in the mountains. Maximum summer and late spring temperatures range from 28ºC
(83ºF) in the hill regions to more than 40ºC (104ºF) in the Terai. In winter, average
minimum and maximum temperatures in the Terai range from 7ºC (45ºF) to a mild 23ºC
(74ºF). Much colder temperatures prevail at higher elevations. The Kathmandu Valley, at an
altitude of 1310m (4297ft), has a mild climate, ranging from 19-27ºC (67-81ºF) in summer,
and 2-20ºC (36-68ºF) in winter.
Rainfall
In Nepal, the intensity and pattern of monsoon is governed by the topography of the
Himalayas. It usually moves to the north and later on to the west, causing maximum
precipitation in the southern Terai belt, and diminishing gradually while moving towards the
north. The annual precipitation is 2200 - 2500 mm in the Terai and Siwaliks range, 1500 -
2500 mm in the Mahabharata range, and less than 1000 mm in the Himalayan range.
Beginning from the end of June to the middle of August, the monsoon occurs first in the east
and progressively moves along the Himalayan chain, into the west covering the entire stretch
of the country.
The months between October and May are mainly dry, though a winter monsoon which
travels eastward from the Mediterranean Sea occasionally brings rain. The winter monsoon
has more influence in the west than east. Precipitation in the form of hail may occur during
February and March.
2) Flood characteristics of Nepalese rivers
Based on an average annual rainfall of about 1400 mm in Nepal, 174 billion cubic meters of
water per year is assumed to be surface run-off. The total run-off of Nepal, including run-off
from the Tibetan catchments, is estimated at about 200 billion cubic meters per annum. Due
to high concentration and intensity of precipitation during the monsoon period, about 72% of
the total run-off is instantaneous, while the rest is conserved as snow and ground water
which drain into the rivers during the dry season.
All major river basins except those of the southern rivers originate in the Himalaya or the
Tibetan Plateau. These river basins are partly snow or glacier fed. During the Monsoon,
these rivers receive abundant runoff due to heavy rainfall, which results in Floods. The
effect of the snowmelt factor becomes insignificant as they move from north to south. Rivers
originating south of the Mahabharata and flowing towards the Terai belt through the Siwalik
Hills are categorized as southern rivers and they depend entirely on rainfall for their runoff.
The hydrograph of these catchments show no rise in flow until the first monsoon rains. In
Nepal, monsoon rains and snowmelt contribute to river flow. Depending on the altitude
some catchments are influenced by monsoon and some by snow melt. On catchments that
are entirely below 3000 m, there is no significant contribution from snowmelt. On
catchments that are above 5000 m, snow melting is major source for stream flow.
Catchments lying between 3000 and 5000 m are influenced by both monsoon and snowmelt.
As the meteorology and hydrology both are very specific due to varying topography and
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 39
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
altitude of Nepal, the hydro-meteorological data also varies largely in space as well as in
time. At the same time, the database is very poor for most of the river basins. In most of the
rivers hydrometric stations have been established by Department of Hydrology and
Meteorology (DHM). Maximum instantaneous flood data have been collected for these
stations. A relationship between catchment area and 100 years flood has been presented in
Figure 18 with the help of data provided.
Figure 18 Relation between catchment area and 100 years flood of Nepalese rivers
(a)Upstream of Kamala with East-West Highway br. (b) Downstream of Kamala with East-West Highway br.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 40
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Sapta Koshi River is trans-boundary river flowing through Nepal and India. Some of the
rivers of the Koshi system, such as Arun, Sun Koshi and Bhote Koshi, originate in the Tibet,
an Autonomous Region of China. It is one of the largest tributaries of the Ganges. The river,
along with its tributaries, drains 29,400 km² in China (mainly the upper Arun basin north of
the Mount Everest region), 30,700 km² in Nepal (the eastern third of the country) and 9,200
km² in India.
The Koshi has an average discharge of 1,564 m³/s. During floods, it increases to as much as
18 times the average. The greatest recorded flood was 24,200 m³/s on Aug. 24, 1954. The
Koshi Barrage has been designed for a peak flood of 27 014 m³/s. Shift in course is a regular
feature of Koshi. It has moved westwards by 120 km in the past 250 years through more
than 12 distinct channels [Figure 20(a)]. [Figure 20(b)] shows the silt deposition and shifting
process by Koshi. [Figure 20(c)] shows the upstream from Koshi Barrage.
(a) Course shifting (b) Silt deposition and meandering (c)Upstream of Barrage
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 41
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 42
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 43
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 44
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1) Hydrological Analysis
Hydrologic and hydraulic analysis should be conducted to suggest proper river width, HFL,
protections for major rivers on the railway alignment and design box culverts for small
streams with site visits, data collection. To calculate discharges for each basin, specific
parameters and several methods will be applied with HEC-HMS (Hydrologic Modeling
System).
River basin by GIS and field investigation
Rainfall analysis and distribution for each river
CN values by NRCS for estimating surface runoff
Estimation of Time of concentration, Lag time and Storage coefficient.
1) Hydraulic analysis
For major rivers, steady flow analysis is essential to decide the height of each bridge. After
investigating site and calculating river width by the formulae on the bridge section, river
width for each river will be decided with consideration of discharge, shape of basins and
current velocity by flood.
2) Vertical and horizontal clearance for bridge
For deciding vertical clearance (Free board), the minimum values have to be decided
according to the ‘Nepal Bridges Standards-2067’.
3) Field Investigations and Verifications
Most of the rivers are unconfined or braided having large flood plains in plain areas of the
proposed railway alignment which may require longer span of bridges. However, following
requirements were taken into consideration while selecting the bridge sites.
Suitability of foundation
Straight approaches having free from flood damages
Straight reach with well-defined banks on upstream and downstream
Minimum width and right angle crossing
Availability of construction materials
Most designs involving hydrologic analyses utilize a design or critical flood that imitates
some severe future or historical event. If runoff data are available, the design flood
hydrograph can be synthesized from available storm records using rainfall-runoff (Unit
Hydrograph) procedures.
Based on international practices, guidelines, type and size of the structures, impounded
volume and preliminary assessment of the extent of likely damage in the event of worst
failure, the design frequency of HFL was decided equal to 100 years for whole railway
alignment.
4) Design of bridge protections
Thickness for scour protection will be decided according to ‘Improvement of Technical
Manuals for River Training Works, Volume 1(Ministry of Water Resources in Nepal).’
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 45
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Also, a lateral extent of scour protection at pier will be decided according to ‘Evaluating
Scour at Bridges 5th Edition, U.S. Department of Transportation‘.
5) River training
The orientation, length, height, top width and side slope of guide bank will be decided by
site visits, results of hydraulic simulation, surveyed data, Nepal and Korean standards.
S
Items Purpose
N
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 46
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 47
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Auger boring will be usually applied to the unconsolidated ground without gravels such as
soft soil, fine grained soil with medium density and adhesive wet sand.
Collecting representative samples consecutively with the configuration status of the soft
ground should be conducted to confirm the presence of soft ground.
d) Sampling
In the process of standard penetration test, disturbed samples will be collected and
undisturbed samples will be taken from the soft ground, when boring rock that will be
recovered during excavation using rock core samples, laboratory tests will be performed.
e) Sounding
Sounding test such as SPT(standard penetration test)/DCPT(dynamic cone penetration test)
will be a method for measuring soil characteristics of relative density and strength simply
and quickly by penetrating, rotating resistance into the ground and pulling out it onto the
ground.
SPT/DCPT will be executed with whole strata except rock bed. Sounding will be used to
estimate soil strength parameter, subsoil distribution and possible existence of soft layer.
f) Permeability Test and Lugeon Test
The Consultant will carry out field permeability tests in overburden, at specified depths or as
directed by the Client, as variable head (rising or falling head) and/or constant head method
in every interval down to the depth during the drilling against all boreholes.
Permeability test in rock, at depths specified, will be carried out as a Packer Test. Single or
double packer, as required, will be used. A complete record of all observations will be
presented in lugeons.
g) Test Pit and Sampling
1m × 1m × 2m (deep) sized open test pit will be excavated to observe and log the general
characteristics of material deposit. From the excavated material representative test sample
will be collected and transport to the laboratory for further test.
7) Material Survey
Investigations for sources of construction materials for embankment filling, retaining
structure, pavement and drainage structures etc. will be carried out and suitable material
sources will be surveyed and shown in the plans. This will involve study of the already
known / used borrow areas and quarries, discussions with knowledgeable local people
regarding potential sources and appraisal of geology. Samples from the promising sources
will be evaluated for properties through laboratory tests.
8) Laboratory Test
The laboratory soil tests and rock testing will be performed for undisturbed samples,
disturbed samples and rock samples to get the physical characteristics and mechanical
properties.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 48
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
3.5 STATION
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 49
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Bardibas and Lahan Stations are the station that processes passenger and freight in this
project section. It serves as a junction station for connecting to the INDIA~NEPAL Railway
line in the future. Rajbiraj Station is the station that processes passenger. Eleven stations
including Hathimoda Station are to be signal stations.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 50
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 51
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Station plan, as shown in Table 33, is the result of reviewing the satellite
photos and topography maps but the consultant plans to review the possibility
after studying the topography and surveying rivers.
Station structures will be reduced with change in station location, like straight
station against curved station.
Need to check the adequacy of station location through detailed review.
With the suggestion of train operation expert, EIA and SIA report, train
operation plan may need to be changed.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 52
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
a) Problem
Two-way departure from all tracks - increase of facility(signal, track, Trackbed, etc.)
construction cost
Excessive platform facility considering the passenger demand - increase of
construction cost
The platform is too far from the station - longer passenger movement trail,
undermines passenger comfort
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 53
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Reduce transshipment time and transit distance in connection area to save operation
cost.
Promote convenience by reducing the circulation of the passengers when they get on
and off trains.
Secure the user's convenience by shortening passenger's moving distance.
a) Problem
Two-way departure from all tracks (Including the main track) - Increase of facility
(Signal, Track, Trackbed, etc.) construction cost.
Excessive land for station site - Increase of land purchase cost, economically
infeasible.
Excessive platform facility scale - Increase of construction cost.
i) Review Result of Track Layout (Intermediate Station)
The Consultant recommends applying Type 1 (Passenger Station) and Type 2 (Signal
Station), comprehensively considering the construction cost, facility site, and the prospect of
building the double track line in the future.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 54
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
3.6 TRACK
3.6.1 Gauge
1) Review Opinion
Broad gauge has been originally suggested by F/S considering connectivity to India and
easier availability of rolling stock and technology from neighboring country.
Design speed for this section is 250km/h. In this case standard gauge (1435mm) is
preferable to broad gauge (1676mm) as most of the high-speed rail lines are standard gauge.
3.6.2 Ballast
Classificati
Gravel Ballast Ballastless
on
Front View
of
Constructio
n
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 55
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Application Tunnel
Earthwork, Bridge
Plan (Not Applicable in this project)
1) Review Opinion
Ballasted track will be applied to the earthworks and bridges. Ballast less track will be
applied to tunnel sections, but there is no tunnel for this section of the project.
3.6.3 Rail
1) Review Opinion
The rail of 60kg 90 UTS has been suggested by F/S study, 60kg 90 UTS rail on main line
and 52kg/m rail on side line will be suggested and applied at the detail design considering
economy and future maintenance of the rails.
3.6.4 Sleeper
1) Review Opinion
Concrete sleepers are 10~25% cheaper than wooden sleepers. PSC sleepers have lots of
advantages and are echo-environment friendly particularly during installation. The number
of sleepers per Km will be determined to be appropriate for the installation. Rail track will
be decided after reviewing the plans for the maintenance and stability.
3.6.5 Fastening
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 56
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1) Review Opinion
Elastic rail fastening has been recommended with e-clip on F/S Report. ERC has been
usually used with a fastening device. The fastener will be considered and decided with
superiorities for good maintenance, easiness of material supply, stability of fastening and
economical advantage in future.
1) Review Opinion
LWR gives lots of merits compared to SWR. It gives one-third longer rail and sleeper
life, better-quality ride, cuts on track maintenance, reduces noise and breakages of
rolling stock spring, and it permits higher speed and formation and ballast life etc.
So, LWR rail for main line and SWR for sidings are recommended. For welding
method, Falsh Butt for plant welding and thermite welding for site welding is
suggested. Where mobile Flash Butt welding is available and preferred, mobile Flash
Butt welding can be considered for site welding.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 57
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1) Review Opinion
F/S report suggests F12 to main line and F8.5 to loop lines and non-running lines. It
also suggests F16 or F20 in main line at some locations where site constraints occurs.
F12 for main line and F8.5 for loop lines and non-running lines should be installed. At
some locations the other number turnouts can be considered. Higher number turnouts
for the locations where operational train speed is high or site constraints occur.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 58
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
- Multi aspect colour light signals (MACLS) AC LED signal lighting units.
- Junction type route indicators
- Calling ON signals
- Shunt signal (dependent & independent)
Interlocking
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 59
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Data logger
Power supply
- 2 diesel generator
- DC track circuits
- Multi Section Digital Axle Counters
- Location boxes
- Signaling cables of different corage
- Station master
- Operating panel/ computer workstation
- Train Controller
- Deputy Control
- Traction Power Control
- Traction Loco Control Engineering Control
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 60
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
- S & T Control
- Remote Control
Three-position system: Signal indication system wherein stop (Red), caution (Yellow)
and proceed (Green) color lights are turned on: three-aspect, four -aspect, and five-
aspect signals fall under the category of this three-position system.
In case of LED type, extinction detection is activated when extinction rate is not less
than 30 %. In case of LED type, LEDs are replaced when extinction rate is not less
than 50 %. LED signals with home, starter, outer, advanced starter signals, and
shunting indicator are deemed most suitable for this project as their recognition
distance is more than 800m and they consume less power (12W), can be used semi-
permanently, and require less maintenance.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 61
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
For the Electronic Interlocking System (EIS), the centralized type is applied, which is
configured in such a manner that all the relays, electronic cards or modules are installed at a
Signal Equipment Room (SER) of each station.
EIS is redundantly configured with CPU section, an interlocking logic section, a display
section, a communication section, a monitoring section and power supplies. The display
section of EIS uses an LCD monitor.
There are two types of EIS. One is a centralized type and the other one is a distributed type.
The centralized type is configured in such a manner that all the relays, electronic cards or
modules are installed at a Signal Equipment Room (SER). The distributed type controls site
signaling equipment remotely by using relays, electronic cards or modules at an enclosure
adjacent to a starting signal or a home signal.
26) Block System
To operate trains safely and rapidly, a preceding train and a following train should be
operated by maintaining a regular distance. For this purpose, a fixed zone is set up and
allows only one train to run within the zone. This zone is called as a block section and this
system is referred to as a block system. Inter-locked block systems are used when train
operations are less frequent.
Inter-locked block system is a system unifying signal aspects and block handling by
interlocking block controllers, which are installed at both stations of a block section with
signals. As the relevant signals are inter-locked to a block system, a train cannot depart if
any of the conditions are not satisfied. Train drivers do not need to pick up token from the
station and can proceed to the next station according to the aspects of the signals.
Provision of digital axle counters is also installed at the same points of Outer signals and
Advanced Starter Signals in each station for detecting the complete departure and arrival of
trains.
27) CTC (Centralized Traffic Control) System
The CTC consists of a state-of-the-art computer system and fiber-optic communication
network. The major components for the CTC are as follows:
- Large display panel
- Server/workstation
- Operator console
- Installation of dedicated power supplies
- Use current fiber-optic communication network for connection to site
equipment
Computers include a train control computer (TCC) and management support computer
(MSC). Industrial computers are redundantly configured so as to continue controlling train
operations in case equipment fails. A fault-tolerant system or a high availability system can
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 62
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
3.9 TELECOMMUNICATIONS
The Consultant reviewed and analyzed the telecommunication system recommended in the
Feasibility Study and has following remarks.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 63
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
The OFC System will serve as backbone for all other communication systems.
According to the review, general matters listed above are required during the construction of
Railway Telecommunication Systems. But instead of unconditional application of latest
technology/equipments we are plan to reflect an optimum Railway Telecommunication
Network by reviewing synthetically the local condition and extend ability, maintainability,
economics, security, efficiency, an interface with other systems, etc.
Cable will be laid at a depth of 1 meter in HDPE duct for safety & security.
Each way station will have SDH (Synchronous Digital Hierarchy) with associated
equipments.
Major station will have STM-4 equipment and other station with STM-1 having
21EI card configuration with ADD Drop Mux (ADM) has been proposed.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 64
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
consider the establishment plan and extendability of additional line on the proposal of major
station with STM-4 equipment and other station with STM-1 equipment. So, it is planned to
apply Backbone network STM-16 and Station Network STM-4 but we are planning to
compose system after reviewing the traffic capacity during the progress of the detailed
design and also to compose ring topology on the Network composition with stability being
verified.
Controller in the control office is given the facility of selective as well as group
calling of the stations.
- Using quad cable, laid throughout the sections, terminated at control office,
each station and at each emergency posts provided at a distance of 1km in
the section.
It’s 25 FV electrified area and also it is not possible to erect emergency posts in
tunnels beyond the limit of infringements, so the emergency communication using
6 quad cables is not recommended.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 65
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
GSM-R system would encompass track to train and on-board voice and data
communications together with the ground based mobile communication needs to
track-side workers, station and maintenance depot staff and railway administrative
and managerial personnel. A frequency band is required for the functioning of
GSM-R.
32) Electronic Exchange Network for Administrative and Commercial
Communication.
Various administrative offices, support offices, Training center, workshops,
hospitals etc proposed at different locations require suitable and efficient
communication network.
Based on the requirement, fully digital non blocking ISDN Multimedia EPABX
exchanges of suitable capacity at the locations, detailed hereunder, are proposed to
be installed.
The exchange will be equipped with 32 bit CPU, dual bus architecture, and most
reliable flash EPROM storage.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 66
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
planning to install emergency telephone, using OFC of the track side, with a system
separated with the GSM-R Systems for the detailed design.
Design to enable speech and data communication through GSM-R system on the
entire permanent way section and to enable radio communication on locomotive
equipment, ground equipment and OCC.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 67
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 68
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 69
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
ⅱ) Requirement of Locomotive
- Freight Train Operation
- Shunting Operations
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 70
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
3 Chair Car 83 -
4 Gaddhachowki-Tamsariya 7.05
5 Kakarbita-Tamsariya 6.18
6 Tamsariya-Pokhara 3.25
7 Kathmandu-Pokhara 3.54
8 Nepalgunj-Kohalpur-Gaddhachowki 5.59
9 Lumbini-Butwal-Kohalpur 7.21
10 Bhairahawa-Butwal-Simara-Birgunj 6.05
11 Birgunj-Simara-Bardibas-Janakpur 4.31
12 Kakarbita-Itahari-Biratnagar-Janakpur 7.52
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 71
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
ⅱ) During the 2nd stage 2024-2025 onwards the utililisation of above mentioned 2 nd
sections has crossed 150% mark without maintenance block and with
maintenance block still further up to 187.9 %. In this stage yet another section
Chandranigahpur~Lahan~Mechi (Kakarbitta) section approaches 51% mark
ⅲ) During the 3rd stage for the two critical section mention above the utilization
crosses even 200% mark and for the 3rd section it approaches almost 65%.
ⅳ) During the last stage 2034-2035 onwards it almost touches 300% in respect of the
two already critical sections and around 80% in the case of 3rd section.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 72
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
As a result of trial operation, when tractive performance or run performance is too low to
make the train run at a scheduled speed, if various reasons including restricted traction force
due to the machine capacity make speed limits necessary, the standard travel time should be
re-rectified for train operation planning.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 73
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
to 500 meters distance from the Nepal- India border that has great strategic sense in the
safety and security perspective of the railway service in Nepal.
Alternative- 2
The proposed second alternative alignment that turns left from the Mohanpur Station along
the side of degraded forest and hillock like topography in the north. It passes along the side
of frontier land, it will not benefit its periphery people due to forest area in one side. It can
also affect the forest area in some extent across the section. Ultimately, it will also coincide
with the same area for crossing over the Koshi River into the third alternative alignment
section. Therefore, it is also not much significant alignment as like first alignment.
Alternative-3
The proposed third alternative which turns toward the north from the Rajbiraj Station and
crosses nearby Koshi Tappu Wildlife Reserve by 9.50 km bridge on Koshi Bridge. Though it
is the longest alignment, it has great significance due to less sedimentation and hard bed
rock. It has much better geological, hydrological features and the strategic point of view as
well. Moreover, people of long stretches will also be benefited by this alignment. It runs
from outer side of the KTWR area from the north. This alternative is accounted as the best
alternative alignment due to above mentioned reasons.
2) Due to the lowering down of the ground surface toward the south, there will be higher
possibility of conflict between the two countries people by the river lodging caused by
border side Dams that constructed by the Indian side. The ultimate reason for the river
denudation across the submerging situation in Nepal have been identified as border side
Dams. To fix the final Railway alignment, the above reasons should be considered nicely.
Therefore, it will recommend selecting the northern alignment rather than the southern one.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 74
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
3) The affected properties have been categorized as private, community and the
government. In the private properties, cultivable and residential land loss will have major
impact. Perennial and non-perennial trees and crops, houses, sheds, shops, wall, wells, tap
etc. also will be the major affected private properties. Under the community properties,
grazing land, community forest, schools, community buildings, religious sites, canals,
public water supply system, etc. will be considered. Under the government properties,
government open land, forest and building structures will be the major affected assets by
this project.
4) Social impact will be high in this long railway section where almost private land falls
under it. Changes on local movement patterns and improved access to markets and social
facilities has also envisaged. Households who are solely dependent on agriculture and lose
their maximum lands, will be more affected.
5) To address the potential losses and social impact, the social impact assessment will be
under taken as a part of resettlement plan. A census of potentially affected land owners and
other assets falling within the ROW of railway alignment will be carried out. Likewise, 20
percent of the project affected households will also be assessed in socio-economic sample
survey. The gender and local aspects will be included in the social assessments. A complete
inventory of affected persons and their assets will be prepared for the compensation
estimation of affected assets.
Unit rate of each cost estimate item in the feasibility study report, except railway
specific items, is based on standard norms for construction works in Nepal published by
the Government of Nepal, and rates for labor, materials and equipment are as per the
rates fixed by the various District Development Committees of the project area.
Likewise some rates are based on the market rates prevalent in Nepal and adopted by
the consultants and contractors working in similar ongoing projects in Nepal. Rates for
railway specific items are generally not available in Nepal and for such items the
international rates used in India have been adopted by justifying that it is the nearest
country to Nepal having a broad gauge network. The international rate has been
adjusted for local duty and transport tariffs and custom duty of 1% has been taken for
entry into Nepal. In the basic rates transport tariff is also added for final rates.
In the feasibility study report the total cost estimate has been divided into two main
groups, Capital Cost Estimate and Operation and Maintenance cost estimate. Capital
cost estimate is further divided into Fixed Infrastructure and Rolling Stocks.
The Fixed Infrastructure cost is divided in different segments. Average rates per
Kilometer calculated by the F/S Report for different segments are summarized as
follows:
Land & Associated Activities: The cost of land acquisition, compensation for
buildings, roads and other mitigation measures has been used for rate analysis as
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 75
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
per government rate. The cost does not consider forest land, river land and
government land. Total cost for land and associated activities is estimated as
NRs. 14.4 million per km.
Earthwork: Rate Analysis was carried out as per standard norms approved by the
Government of Nepal (GoN). Final cost for earthwork is estimated as NRs. 41.7
million per km.
Protection Work (Retaining Walls): Rate Analysis was carried out as per
standard norms of GoN. Final cost is estimated as NRs. 0.5 million per km.
Blanketing: Rates calculation uses norms of Government of Nepal for similar
kind of works. Final cost is estimated as NRs. 11.2 million per km.
Bridges: The quantity as per feasibility report was calculated using the
feasibility stage design as deemed good by the structure bridge engineer and
quantity survey expert. Final cost of bridges in feasibility report is estimated as
NRs. 55.3 million per km.
Permanent Way (Tracks items including ballast and Permanent Way
Machinery): The Indian rate for these items adjusting for custom duty and
transport tariff has been used. Ballast rate is worked out in feasibility study as
per norms for similar item in Nepal. Final cost is estimated as NRs. 38.6 million
per km.
Station, Buildings, Sheds, and Offices etc: In the feasibility study rate used is as
per prevailing market rates in Nepal and as per standard norms of GoN. Final
cost estimated is NRs. 5.3 million per km.
Electrical Engineering Works: Rate of similar items used in India at the study
time has been used with transport tariff and duties etc. Final cost estimated is
NRs. 12.2 million per km.
Signaling, Train Control and Telecommunication Works: The unit rates of the
items taken in the cost estimates are derived from the latest accepted unit rates
for these items from the contracts awarded for similar work in India. These unit
rates are also inclusive of transportation and duties etc. Final cost estimated is
NRs. 17.1 million per km.
Maintenance Facilities for Rolling Stock: Final estimated cost is NRs. 7.2
million per km.
Preliminary Expenditure like DPR, Detailed Engineering and Supervision etc. :
The rate taken for Detailed Project Report is 2% of total cost and Detailed
Engineering and Supervision includes 8% of total cost. The total cost per km
estimated is NRs. 20.4 million.
Contingencies: 5% of the total project cost is used as contingencies. The total
cost per km estimated is NRs. 10.2 million per km.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 76
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
Rolling Stock cost includes the cost of wagon, coaches, shunting (diesel) locomotives
and accident relief crane, and electrical locomotives. The F/S Report provides the
estimated total cost of rolling stock for different horizon years. The total cost for rolling
stock for the nearest coming year 2019-2020 as used in feasibility report is NRs. 53.26
billion.
The Operation and Maintenance cost is divided into different head as Operation and
Commercial Activity Cost, Operation and Maintenance Cost of Electrical Locomotives,
Maintenance Cost of Civil Engineering Structures, Maintenance Cost of Signaling,
Train Control and Telecommunication works, Maintenance Cost of Electrical
Engineering Works, Maintenance Cost of Coaches, and Operation & Maintenance Cost
of Shunting (Diesel) Locomotives. The total estimated cost is projected for different
years. The total cost for the nearest coming year 2019-2020 as used in feasibility report
is NRs. 5.57 billion.
The feasibility study has provided the fixed infrastructure capital cost estimate for each
section of railway. For instance above cost of each segment from 1 to 13 is based on the
cost estimate of section 4, Chandranigahapur-Lahan. But the cost estimate for rolling
stock and operation and maintenance is for total project of Mechi–Mahakali Railway.
Based on above rates the total Fixed Infrastructure capital cost of Bardibas-Inaruwa
section of MMR is summarized as NRs. 32,061.5 million assuming that the project
length is 137 Km. Brief breakdown is presented in Table 46.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 77
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
1 Maintenance 137
7.2 986.40
1 Facilities
Total 27,879.50
1 1,394.0
Contingencies @ 5% of total cost
3 0
32,061.
Grand Total
50
Though the unit rates are calculated on the basis of Government norms and rates
fixed by the respective District Development Committees, some of the unit rates
such as earthwork, collection of local construction materials could be compared
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 78
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
with equipment based norms. Such comparison may optimize the total cost of
the project.
Lead is one of the main factors, which affect the unit rate substantially. Though
it is very difficult to ascertain all details about the lead of each and every item
for each section in such a huge project, it is necessary to analyze in more detail
during the detailed design period.
Presently rate of some construction materials has gone up sharply in comparison
to the rates of feasibility period. For instance fuel (diesel, petrol etc),
reinforcement, labor charges etc. have been increased considerably.
Subsequently the transportation cost, equipment hire charge, locally available
construction materials will automatically increase.
During the detail design period all parameters considered by the feasibility study
will be once more analyzed in detail and more pragmatic unit rates and cost
estimate will be produced.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 79
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
one field survey team will carry out the survey works starting from Bardibas side and
proceed eastward and other field survey team will start from Talaha and proceed eastward.
The third field survey team will start from Koshi River and proceed eastward up to the
endpoint. In each of the field survey team, sub-teams will consist for setting of
monumentation, bench marks, detailing and leveling. After the conclusion of the field
survey works, the same team will prepare the topographic map. The map will be verified in
the field and a final topographic map will be produced. The detail design team will
periodically verify and monitor the field survey team's work.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 80
Detail Survey and Design of Electrified Railway Line (HSR) for
Feasibility Study Review Report
Bardibas-Inaruwa Sector of Mechi-Mahakali Railway (Package-1)
5. CONCLUSION
Feasibility Study Review Report is prepared based on TOR of Detail Survey and Design of
Electrified Railway Line (HSR) for Bardibas-Inaruwa Sector of Mechi-Mahakali Railway
(Package-1).
Current status of alignment, structure (earthwork, bridges etc.) plan, railway system, etc. are
reviewed and examined through the feasibility study review while critical issues and
direction of detail design are established. The direction of detail design is as follows:
Detail design to reduce construction costs with
- Minimum length of alignment
- Minimum length of structure (bridges)
- Minimum interference of utilities and obstructions (houses, power
transmission lines, canals, highways and roads and factories, etc.)
Minimum civil complaints
- Civil complaints are resolved by minimizing interference with residential
areas
Combined operation (HSR, Local and Freight trains)
Design of alignment and structures in consideration of constructability
The Consultant would exert its best efforts to deliver an optimal alignment plan, structure
and system designs in consideration of economic efficiency, constructability, safety, etc. The
Client's guidance, suggestions and close cooperation are necessary for successful
implementation of the service.
YOOSHIN-KRNA-BARSYSL-KRTC-FBC-BID JV 81