Professional Documents
Culture Documents
Contents
1 Prologue...................................................................................1
Detailed Contents
1 Prologue...................................................................................1
1.1 Back Drop .......................................................................................................................... 1
1.2 Terms of Reference ............................................................................................................ 3
4.6 Locating Commuter Rail Terminals: Enter City Core or Terminate at Outskirts ................... 28
4.6.1 Commuter Needs ............................................................................................................ 28
4.6.1.1 Passenger Travel Patterns ................................................................................................ 29
4.6.1.2 Provision of alternate Public Transport ............................................................................ 30
4.6.1.3 Impact of forced transfers on service patronage .............................................................. 30
4.6.1.4 Development of BMR ...................................................................................................... 30
4.6.1.5 Indian Railways Considerations ........................................................................................ 31
4.6.2 RITES Recommends ......................................................................................................... 31
Tables
Table: 1.1 Population of Bangalore Metropolitan Region ........................................................................ 1
Table: 1.2 Modal Splits Comparison with Mumbai .................................................................................. 2
Table: 1.3 Past studies on CRS - Bangalore............................................................................................. 3
Table: 1.4 Terms of Reference ................................................................................................................ 3
Table: 2.1 Authorities functioning within BMR....................................................................................... 5
Table: 2.2 Population projections and allocations ................................................................................. 11
Table: 2.3 Share of various modes of transport ...................................................................................... 12
Table: 2.4 Phasing of Investments (WSA recommendations) ................................................................. 13
Table: 2.5 Total investment program for long term scheme (WSA recommendations) ............................ 13
Table: 2.6 Phasing of total investments (WSA recommendations) ......................................................... 13
Table: 2.7 Corridors suggested by RITES (2011) .................................................................................. 14
Table: 2.8 Section overlap of other modes of transport with CRS .......................................................... 14
Table: 2.9 Value of Overlap .................................................................................................................. 15
Table: 3.1 Capacity comparison of different modes ............................................................................... 18
Table: 3.2 Average Trip Lengths of different modes .............................................................................. 22
Table: 4.1 CRS Network in Bangalore .................................................................................................. 25
Table: 4.2 Other modes of transport parallel to IR Network within 1 Km ............................................... 25
Table: 4.3 Other modes of transport parallel to IR Network within 2 Km ............................................... 26
Table: 4.4 Other modes of transport parallel to IR Network within 5 Km ............................................... 26
Table: 4.5 IR Network parallel to other modes of transport .................................................................... 26
Table: 4.6 Consultant suggestions for Hyderabad MMTS ...................................................................... 27
Table: 4.7 Existing travel pattern of Bangalore rail commuters .............................................................. 29
Table: 5.1 Population density in 2011 ................................................................................................... 35
Table: 5.2 Assumed decadal growth rate of population ......................................................................... 35
Table: 5.3 Split of each section district wise .......................................................................................... 35
Table: 5.4 Modal split of commuter traffic in Mumbai .......................................................................... 36
Table: 5.5 Per Capita Trip Rate ............................................................................................................. 36
Table: 5.6 Modal share Vs trip lengths .................................................................................................. 37
Table: 5.7 The three scenarios ............................................................................................................... 38
Table: 5.8 Assessed Commuter Rail Trips (Scenario: Low) ................................................................... 38
Table: 5.9 Assessed Commuter Rail Trips (Scenario: Medium) ............................................................. 39
Table: 5.10 Assessed Commuter Rail Trips (Scenario: High)................................................................. 39
Table: 5.11 Suburban rail services – Supply position ............................................................................. 40
Table: 5.12 Historical trend of passenger growth ................................................................................... 41
Table: 5.13 Traffic Projections for various commuter system in India .................................................... 42
Table: 5.14 Assessment of additional services required to bridge demand supply gap ............................ 44
Table: 6.1 Major rail projects in Bangalore area in the past .................................................................... 45
Table: 6.2 Rakes lie over at SBC........................................................................................................... 49
Table: 6.3 Lines length of SBC yard ..................................................................................................... 50
Table: 6.4 Interconnectivity of running lines at SBC ............................................................................. 51
Table: 6.5 Trains being terminated short of SBC ................................................................................... 52
Table: 6.6 Scenario of SBC yard after suggested remodelling ................................................................ 54
Table: 6.7 Likely scenario of BYPL (N) 3rd coaching terminal.............................................................. 58
Figures
Figure: 2.1BBMP, BDA and BMR Boundaries ........................................................................................... 5
Figure: 2.2 LPAs in BMR .......................................................................................................................... 5
Figure: 2.3 Preferred Scenario Map......................................................................................................... 8
Figure: 2.4 Land utilisation zoning ........................................................................................................... 9
Figure: 2.5 Transport Network .............................................................................................................. 10
Figure: 6.1 Binny Mill land towards Mysore end.................................................................................... 48
Figure: 6.2 Connecting MYS line to grid one .......................................................................................... 53
Figure: 6.3 Utilisation of Binny Mill Land for Commuter terminal .......................................................... 56
Figure: 6.4 Baiyyappanahalli (North) maintenance terminal .................................................................. 58
Figure: 6.5 Hejjala 4th coaching terminal ............................................................................................... 62
Figure: 6.6 Flyovers at BYPL area........................................................................................................... 66
Figure: 6.7 Connecting Dodballapur line with Chikballapur line ............................................................. 72
Figure: 6.8 EMU rake of MRVC .............................................................................................................. 83
Figure: 8.1 CRS Implementation Phases .............................................................................................. 108
Figure: 8.2 CRS Implementation Phases .............................................................................................. 111
Annexures
Annexure: 1 Lie-Over at SBC yard........................................................................................................ 148
Annexure: 2 Criss-Cross movements that can be made seamless by Flyovers ...................................... 152
Annexure: 3 Additional Halts suggested by voluntary organisations .................................................... 153
Annexure: 4 Trains presently serving Bangalore commuters and enhancing their capacities ................ 156
Annexure: 5 Cost Estimates in a Nutshell ............................................................................................ 160
Annexure: 6 EMU Rakes requirement for New Services....................................................................... 161
Annexure: 7 Hourly Distribution of total scheduled trains running in CRS network at present .............. 163
Annexure: 8 Hourly distribution of commuter trains running at present .............................................. 164
Annexure: 9 Hourly distribution of assessed potential for introducing additional services after proposed
investments..................................................................................................................... 165
Annexure: 10 ROBs with TVUs more than 50000 ................................................................................. 167
List of Abbreviations
BBMP Bruhat Bangalore Maha Palike
BCRC Bangalore Commuter Rail Corporation
BDA Bangalore Development Authority
BEML Bharath Earth Movers Limited
BIAL Bangalore International Airport Limited
BMR Bangalore Metro Railway
BMR RSP Bangalore Metro Railway Revised Structure Plan
BMRDA Bangalore Metro Regional Development Authority
BMTC Bangalore Metro Transport Corporation
CIDCO City and Industrial Development Corporation
CRS Commuter Rail System
DEMU Diesel Electrical Multiple Unit
EMU Electrical Multiple Unit
FOB Foot Over Bridge
GoAP Government of Andhra Pradesh
GoI Government of India
GoK Government of Karnataka
GoM Government of Maharashtra
GPS Global Positioning System
HMDA Hyderabad Metro Development Authority
IB Intermittent Block
ICF Integral Coach Factory
IR Indian Railways
KRCL Konkan Railway Corporation Limited
LCs Level Crossings
LPA Local Planning Authority
MEMU Mainline Electrical Multiple Unit
MMTS Multi Model Transport System
MoR Ministry of Railways
MoU Memorandum of Understanding
MRVC Mumbai Rail Vikas Corporation
NICE Nandi Infrastructure Corridor Enterprises
O&M Operations and Maintenance
ROB Road Over Bridge
RUB Road Under Bridge
SPV Special Purpose Vehicle
SWR South Western Railway
TVUs Train Vehicle Units
WSA Wilbur Smith Associates
1 Prologue
1.1 Back Drop
Bangalore, the capital of south Indian state Karnataka is India‟s fifth largest and
a rapidly growing metropolis. It is known world over as India‟s Garden City and
Silicon Valley. What started as a pensioner‟s paradise in post independent
India transformed itself into a metropolis with presence of large public sector
companies and educational institutions. Emergence of IT sector however,
overshadowed other areas and metamorphosed the city into a global IT hub. It
continues to attract India‟s best and brightest human capital given its
undisputed status as the knowledge capital of India. In the last decade or so, a
genial small city, dotted with breathtakingly beautiful gardens and dominated by
large defence establishments and government funded labs transformed quickly
in to a teeming metropolis which struggled to cope with its explosive growth. Its
inadequate road infrastructure, exponential growth of personal vehicles due to
raise in income levels all have combined to make local commute a nightmare.
about 4.5 million trips by public transport. BMTC daily ridership is about 4.5
million1. Ridership of metro is presently about 25000 and ridership of Railways
is about 150000. Thus, public transport commuting needs of Bangalore are met
virtually by BMTC alone as on today!
With the kind of traffic congestion in Bangalore city today, BMTC can hardly
increase its ridership any further (except on account of extensions to new
geographical areas). Metro and Monorail which are being considered seriously
by GOK are certainly going to provide some relief. But the relief is limited
because of their limited spread in the city. The growth of demand is so huge
that dependence on a particular mode of commuting will grossly under serve
the public.
Bangalore has not yet actively involved in tapping the huge potential of the
Railway system like in case of Mumbai. Mumbai‟s modal share of its public
transport can be seen as under:
Mumbai Bangalore
Mode
Share Share
Rail (including Metro) 46% 1.5%
Bangalore (for that matter any growing urban agglomeration) should take
Mumbai as its role model and integrate the rail system into its commuter
system.
Towards this objective, many studies were conducted in the past as under:
1
source: http:// www.bmtcinfo.com/ site/ BSBmtc At Glance.jsp
None of the above studies were comprehensive. The studies analysed the
system at macro level and did not lay stress on workable and implementation
aspects. There were no enough detailing to convince the IR. With the result, IR
did not agree the recommendations. The rail system in Bangalore did not
undergo any major revamp so far towards serving commuters despite many
studies since 1983. It has been growing at its natural pace which is not
targeted or intended for meeting urban transport needs.
No Description
1 Review City and Transport Plans
Review of city master plans and future projections of growth
Review of city transport plans
2 Assessment of current Rail traffic and projections for the next 20 years
Review the demands for long and medium distance trains
Assess the current freight traffic and potential for future freight traffic
under different scenarios
Assess the future demand for each stream of traffic for the next 20 years
3 Assessment of Infrastructure requirements: Sectional and terminal
requirements
Assess the current capacity utilization over different sections
Review the current terminal availability and problems associated with the
terminal operations
Assess the future capacity needs for the terminals
No Description
Suggest suitable measures to enhance the terminal capacity
4 Suburban Rail traffic: Assessment of potential and evaluation of options
Assess the demand for suburban commuter trains in consultation with
various state government bodies and SWR
Projection of demand for the next 20 years
Evaluation of the services provided by SWR for suburban system
compared to alternate options for the government of Karnataka.
Assess the feasibility of providing services and the infrastructure
developments required to provide the services.
5 Identification of optimal infrastructure utilization
Assess the section capacity needs over different time periods by deploying
Line Capacity Simulator jointly developed by IIT Bombay and RITES Ltd.
Identify possible combination of train running on different sections and
identify suitable criterion for evaluating them
Assess the optimal combination for running trains by deploying the line
capacity simulator developed by IIT Bombay.
6 Infrastructure investment requirements
Provide a phased plan for an estimate of broad costs for developing the
infrastructure
7 Institutional Management
The Management, Operations and Maintenance of the Commuter Rail
System
Identification of fare structure
As a number of base studies were completed earlier, present study has been
limited to analysis of the secondary data.
The Bangalore Metropolitan Region (BMR), the area of this study contains
within itself, different planning and development units such as the BBMP, BDA,
and many LPAs (Local Planning Areas).
Figure: 2.1BBMP, BDA and BMR Boundaries Figure: 2.2 LPAs in BMR
Area in
No Authorities functioning within Bangalore Metropolitan Region [BMR]
Sq. Km.
Area in
No Authorities functioning within Bangalore Metropolitan Region [BMR]
Sq. Km.
Total 8005.00
1. IMPs (Intermediate Master Plans) for horizon year 2012 for the six
LPAs (Local Planning Areas)
2. RMP (Revised Master Plan) 2015, Bangalore Development Authority,
2007 for the BDA Area
3. CDP (City Development Plan) for the BBMP in 2006
In the introductory text, the BMR Revised Structure Plan (RSP), 2031 reviews
the other plans for the different planning and development units in the area and
concludes thus:
“An analysis of the various plans operational in this region reflects not only
contrary development strategies but also certain inherent contradictions, and a
lack of coordination and acceptance of the overall policy framework laid out by
the BMR SP (Structure Plan) 2011. Rationalizing these contradictions emerged
as the main objective of the BMR RSP 2031.”
The above four scenario maps are illustrated in the images shown. These are
followed by the map indicating the “preferred scenario” formulated in the RSP
2031, and which forms the basis for the proposed Structure Plan.
Finally the land use zoning, transport plan and the growth clusters converge to
the population projections and allocations detailed in the BMR RSP, 2031.
The RSP discusses three alternate scenarios for the population allocation in the
BMR, with respect to the proportion of the population in the core and the rest of
BMR. These three scenarios are for the 75:25; 70:30; and 60:40 proportions of
population in the core and rest of BMR. The RSP states that the second
alternative that is 70:30 share is the preferred population allocation. This
particular table showing the population projections and allocation to different
areas within the BMR is reproduced here.
Table: 2.2 Population projections and allocations
The Travel patterns of the city and the BMRDA region are analysed by various
bodies based on various reports and the latest is the one prepared by WSA
associates for the BMRDA. The share of various modes of transport is given in
the Table: 2.3.
Keeping the growing importance of the city, various projects were taken up the
by different development agencies. Among this the important projects under
execution is phase 1 of Bangalore metro project. In addition, the following
projects are under different stages of sanction:
In addition, two master plans were prepared; one by RITES limited in 2011 and
the other by Wilbur Smith Associates (WSA) in 2011. The RTIES report covers
only the Bangalore Development Authority area and that of WSA covers the
entire Bangalore Metropolitan Region (BMR). Since the CRS is in BMR, we
review the WSA plans in greater detail.
Table: 2.5 Total investment program for long term scheme (WSA recommendations)
Assumed
Amount
Unit Rate
Item Unit Quantity (Rs. In
(Rs. In
crores)
crores)
Metro Km 250 95.7 23930
Mono Rail Km 150 213.1 31964
BRT /High Density Dedicated
Km 15 393.315 5900
Bus
Bus Corridor Km 0.1 324.4 32.44
Road Up gradation Km/lane 1.5 341.25 1507.35
New Roads Km/lane 1.5 515.8 4642
Missing Links Km/lane 1.5 529.1 1587
Transfer Stations No. 25 17 425
Intermodal Transit Centers No. 45 15 675
Truck Terminals No. 10 8 80
Bus Terminals No. 4 12 48
Total→ 70791
due to inherent advantages and large potential that has, rail system just cannot
be ignored by any urban/suburban transport system. Potential of rail system is
discussed in greater detail in subsequent chapters. The RITES report (2011)
covers commuter rail system and suggested to develop following corridors:
Estimated Cost
S.No Corridor Length Km
(in Rs. Crores)
1 Kengeri – Ramanagaram 32.0 480
2 Baiyyappanahalli – Hosur 41.0 615
3 Yeshvantpur – Tumkur 64.0 960
4 Yelahanka – Dodballapur 24.0 360
Total 161.0 2415
Present study relooked the whole gambit of Rail Service in detail i.e. not only
doubling costs, but also terminal facilities, rolling stock procurement,
maintenance and provision of additional halts etc.
Now, many other modes are being developed parallel to CRS network in
Bangalore.
Costs being incurred (or planning to incur) on other modes to replicate the
services that otherwise can be provided by Railways is assumed as
under:
From the above, it can be seen that about Rs.10,000 crores is being spent (or
planning to spend) to replicate service which can be easily provided by rail
network.
In fact, Indian Railways, the pride of the Nation runs un-interrupted services to
move more than 30 million passengers and about 3 million tons of freight
every day. It is an excellent rail operator and probably one of the world‟s best
systems to run such a massive network without any hitch. Disaster
management and crisis management systems of the Indian Railways are the
best India can ever think of. Very big bridges washed out during floods are
constructed in just a few hours or at the most a few days and such disasters are
hardly felt by the travelling public.
IR has been enhancing capacity continuously with its limited resources. But
such enhancement is very marginal and cannot match the ever growing
demand. If the inability of IR to enhance capacity is supplemented by other
means, IR‟s strengths can be well leveraged to cater to ever growing demand to
a very large extent at much lesser costs.
The above table gives the case where the CRS system runs only sub-urban
trains. However, a normal CRS system has to allocate paths between different
types of trains. In this scenario, it is presented in subsequent paragraphs how
CRS capacity would compare with a metro in capacity and cost dimensions.
Metro is chosen for comparison as it has the second highest capacity and it is a
rail based system.
The present commuter rail system of Bangalore runs at average speed more or
less at its potential. But the present throughput is far below its potential ( about
2000 per hour – Taking 1 train of about 10 coaches per hour and 200 passengers per coach) and can
be exploited fully to its potential to serve the public. Capacity is high mainly
because of the train length. Train length can go virtually up to 28 coaches
which is just not possible with Metro or any other mode.
As CRS will share space with other types of trains, frequency of trains would
necessarily be lower than metro and thus most people assume that CRS will
have lesser capacity. However, conventional rail systems can be designed to
have the same capacity as metro systems being introduced in the country and,
they could still have scope for running other trains in the same system.
Length of metro coaches is fixed as 6 coaches in all the metro systems being
built in the country. This limitation arises as elevated platforms are very costly
and the increase of coach lengths increases the cost of the system
disproportionately. However, on IR, as conventional trains run with 26 coaches,
many of the station‟s mainline platforms are designed to accommodate trains of
this length. In Mumbai suburban system, a historical legacy, progressively 12
coach trains have become the norm and a few services are run with 15 coaches
also. Currently, suburban trains in Mumbai, Chennai and Hyderabad are run in
9 car rakes. In new suburban systems, as stations and platforms can be
located relatively more flexibly compared to legacy systems, introduction of 15
coach trains would not be difficult. Thus, Capacity of a CRS train is 2.5 (15/6)
times of a metro train on account of number of coaches.
WSA (Draft final report Jun „2010 of M/s Wilbur Smith Associates on Comprehensive Traffic and
Transportation Study for Bangalore Metropolitan Region for BMRDA) provides plans for
25 x 440 x 15 x 200
𝑃𝑎𝑠𝑠𝑒𝑛𝑔𝑒𝑟𝑠 𝑡ℎ𝑎𝑡 𝑐𝑎𝑛 𝑏𝑒 ℎ𝑎𝑛𝑑𝑙𝑒𝑑 = x 2 = 2.2 Millions / day
30
Costs are as per block cost estimates given in “Cost Estimates and
Phasing of Investments” chapter.
25 commuter trains per direction in the entire CRS network of about 440
Km.
Each train consists of 15 coaches with carrying capacity of 200 each.
Average lead of each passenger is : 30 Km.
Calculation is done for both directions (multiplied by 2).
The 2.2 million passengers capacity is about half of the present day public
transport commuter demand of 4.5 million trips per day.
In fact, the 25 trains per direction taken in above calculation can be increased
substantially with marginal additional investment. Train lengths also need not
be 15 cars. It can be even more in future.
Metro Rail costs about 12000 Cr for 42.3 Km to serve about 1 million
passengers per day (as per phase-I of Namma Metro). Investment per
passenger Km of rail will be much less than metro as seen above.
Thus, a CRS system for the same capacity as Metro (plus additional capacity
for long distance passenger trains and freight trains) can be developed at much
lesser cost than Metro.
This clearly shows that commuter rail is the most economical mode of public
transport and it needs to be made an integral component of any commuting
system.
Cost of construction of a metro system per kilometre is around Rs. 250 Crores
for an elevated system (as per WSA reports) and Rs. 350 – 400 Crores for an
underground system. Compared to this, upgrading a conventional rail system to
suburban needs would cost around Rs 15-20 crores per kilometre.
Namma Metro, Mono Rail, High Speed Rail to BIAL, rejuvenated BMTC
services etc. which are top priority agenda items of GoK‟s transport plan cannot
really address the key problem of commuters. A commuter should be able to
travel a distance of about 70 Km (or even 100 Km) in about an hour or so.
Then only growth centres like Hosur, Tumkur, Mandya, Bangarapet etc. get
developed fast and pressure on main hub Bangalore will be eased. The said
agenda items (Namma Metro, Mono Rail etc.) shall at the most give some relief
within the highly urbanized Bangalore city area leaving the larger commuter
problem unaddressed because trip lengths of Metro are much less than the
public needs.
IR is able to disperse the commuter traffic much effectively as its average trip
length of suburban travel is 33.8 Km which is much higher than trip lengths
possible by any other mode. With increase in trip lengths only suburban areas
like Hosur etc. can be integrated with city core.
From the above, it can be seen that IR has got potential to bring up the average
trip length of Bangalore public transport system from the present 10.8 Km to as
high as 33.8 Km. Such dispersion by Metro or Monorail or BMTC are nearly
impossible because it is prohibitively expensive to extend Metro or Monorail to
cover more locations.
From the above, it can be appreciated that IR has very huge potential:
With such a huge potential and advantages associated with it, no commuter
system can be claimed to be “complete” or “satisfactory” without the appropriate
mix of commuter rail.
It is only the Mumbai (Chennai and Kolkata also to some extent) that have
tapped the potential to their maximum practicable levels and benefited
immensely. They have been still tapping the potential further. Hyderabad also
is now joining the league of coveted commuter rail systems of India with its
MMTS. Bangalore should now take a leap forward to exploit the Railway‟s
potential and integrate the rail system with the city‟s commuter system to satisfy
the public needs.
No single mode of commuting (say it rail or road or metro or mono rail or so)
can fully satisfy the commuting needs of any city. Bus, rail, metro, mono rail
etc. have got different applications associated with them. They are meant for
different sections of commuters and for different trip lengths. An optimal mix of
different modes of public transport is normally the strategy for any urban
transport planning.
As already discussed in Para 3.5, due to more trip lengths associated with it,
CRS can be designed to reach both city core and suburbs seamlessly. The city
has a network of about 440 Kms (brought out in next paragraph) serving the city
in 7 directions. It serves satellite towns of Mandya towards Mysore,
Dodballapur towards Hindupur, Chikballapur towards new Airport, Tumkur
towards Hubli, Bangarapet towards Jolarpettai, Hosur towards Salem and
Kunigal towards Hassan direction.
Creating metro network of this extent and reach would be a difficult proposition.
CRS will be only viable option to cover BMRDA area.
From the trend of commuter ticket sales at various stations in and around
Bangalore, and from interaction with various officials of South Western Railway
and Government of Karnataka, IR network that can serve Bangalore commuters
is identified as under:
2
Draft final report Jun ‘2010 of M/s Wilbur Smith Associates on Comprehensive Traffic and Transportation Study for
Bangalore Metropolitan Region for BMRDA
From the above, it can be seen that about 25% of commuter rail network is
along the identified commuter corridors of different modes. This clearly gives
an indication that the existing rail network is well in tune with the city‟s
commuting needs and commuting plans.
But, even much before the receipt of consultant‟s report (Feb ‟04), major part of
priority-III (Lingampalli - Nampalli) section was commissioned (Aug ‟03). The
reason behind giving priority III for this section by the consultant was clearly
reflected in the poor patronage of the section initially. However, the patronage
has shot up tremendously in this section and the real estate business in these
sections also shot up and resulted in many new housing projects in this section.
The priority II and III projects were subsequently sanctioned in MMTS phase-II.
Sectors
To →
Estimated
Originating SBC YPR BYPL BWT HEB TK MYA HSRA DBU CBP
From↓
Commuters per
Day ↓
SBC 31500 21% 0% 1% 1% 30% 0% 33% 32% 1% 1% 1%
YPR sector 12000 8% 6% 1% 0% 2% 1% 75% 6% 3% 4% 2%
BYPL sector 12000 8% 9% 0% 3% 76% 0% 0% 4% 6% 0% 1%
BWT sector 34500 23% 24% 0% 10% 64% 0% 0% 1% 0% 0% 0%
HEB sector 1500 1% 11% 0% 0% 0% 0% 0% 0% 60% 29% 0%
TK sector 24000 16% 64% 13% 1% 1% 0% 21% 1% 0% 0% 0%
MYA sector 25500 17% 39% 2% 2% 2% 0% 2% 54% 0% 0% 0%
HSRA sector 4500 3% 26% 25% 14% 0% 15% 0% 0% 19% 0% 1%
DBU sector 3000 2% 35% 34% 0% 1% 11% 1% 3% 0% 15% 0%
CBP sector 1500 1% 44% 33% 17% 0% 0% 0% 0% 0% 0% 0%
Total 150000 100%
YPR Sector: Yesvantpur and Malleswaram
BYPL Sector: Bangalore Cantt, Bangalore East, Baiyyappanahalli.
BWT Sector: Krishnarajapuram, Satellite Goods Terminal, Whitefield, Devangonthi, Malur, Byatrayanahalli,
Tyakal and Bangarapet.
HEB Sector: Kodigehalli, Lottegollahalli, Hebbal, Banaswadi, and Channasandra.
TK Sector: Tumkur, Kyatsandra, Hirehalli, Dobbspet, Nidvanda, Muddalinganahalli, Dodbele,
Bhairanayakanahallli, Gollahalli, Kunigal, Soldevanahalli, and Chikbanavar.
MYA Sector: Mandya, Hanakere, Maddur, Nidaghatta, Settihalli, Channapatna, Ramanagaram, Ketohalli,
Bidadi, Hejjala, Kengeri, Jnana Bharthi, and Nayandahalli.
HSRA Sector: Hosur, Anekal Road, Heelalige, Karmelaram and Belandur Road.
DBU Sector: Dodballapur, Rajankunti and Yelahanka.
CBP Sector: Chikballapur, Nandi, Venkatagiri Kota, Avatihalli, Devenahalli, Dodjala and Betthalsoor.
Source: Actual Tickets sales data that could be collected has been modelled into this matrix.
From the above, it can be seen that demand pattern is not supporting the
proposition of locating commuter terminals short of Bangalore. From
every sector, the demand pattern is to touch Bangalore.
It can be seen from the above that the traffic has two distinct patterns.
First is the traffic within the sector. This traffic is expected to be high as
people would be moving to nearby places more frequently. This traffic,
however, would not be influenced by the location of terminals as they
terminate their journeys short of the terminals.
Another is the cross sector traffic. This traffic moves across the sectors
and thus terminating traffic at suburban terminals will force a major
transhipment. It can be observed from the above table that major portion
of commuters move towards Bangalore terminal indicating predominant
preference for it.
Therefore, any attempt to locate terminals short of SBC is likely to result
in artificial transhipment of commuters on big scale. To manage this level
of avoidable transhipment, good amount of money need to be invested
apart from causing inconvenience to commuting public.
Terminating trains would reduce the system capacity as trains are run for
shorter distances.
Extensive infrastructure needs to be developed to handle the trains and
passengers at these terminals. At many of these stations, required
facilities are not available and difficult to develop.
Such proposition becomes unavoidable only when no solution exists for
enhancing capacity of rail network in Bangalore city core area. But as
discussed in subsequent chapters, the core Bangalore area has got
tremendous scope for additional capacity.
Commuters changing from one mode to another mode during the course of their
trip is a big challenge in urban transport planning. All stations on CRS network
act as modal transit locations because commuters normally come to station by
If the overlap of CRS with other modes is very high, it only duplicates the
service and is not desirable. If the overlap is too less, it is like a standalone
system and serves only some captive commuters. If rail system crosses other
modes just at few locations, pressure on those inter modal transit hubs shall be
very heavy and difficult to manage. Moderate overlap as seen above facilitates
transhipment of commuters from one mode to other mode at different places
and serves greater population in a meaningful way.
4.8 Conclusions
Conventional rail system has grown to its present stage over a very very long
period and is a part and parcel of common man‟s life whether for long distance
travel or commuting. Unintentionally, it has become itself integrated into the
commuting system of the city. It can itself become a mass rapid transport
system and also it can act as feeder system to other modes of transport.
Therefore, exploiting its full potential gets automatically (and so naturally)
integrated into the transport needs of the city. Such exploiting should be a
continuous process (like in the case of MRVC) rather than discrete.
Demand for traffic for each of these streams is different and projected
separately. As the CRS capacity created has to be shared between 3 streams,
the demand assessment will help in optimally configuring the share of different
types of traffic.
However due to the unique layout of the rail network within the central city area,
and the many „hubs‟ and the resultant „routes‟ between the hubs and
destinations in the metropolitan region, the CRS rail network of 440.8 Km
belonging to the above seven corridors were identified for the study.
Accordingly, the macro estimates in brief:
1 Km, 2 Km and 5 Km on both sides of the rail lines have been taken as
the catchment areas of the commuter rail sections for which the
populations are estimated.
Within BBMP area, only 1 Km catchment is considered, since there would
be many other competing modes within this area. Outside BBMP, 3
catchment areas have been considered. However, the 5 Km catchment
area has been considered beyond 40 Km from the city hubs. This
assumes good connectivity to the commuter rail sections.
Population on either side of rail network (within 1 Km, 2 Km and 5 Km
catchment) is assessed based on geographical area and population
densities. For this purpose, the catchment areas in the CRS sections
3
Wilbur Smith’s Draft Final Report, Comprehensive Traffic and Transportation Study for the BMR)
were identified into districts they came under and the population density
of the districts as per census 2011 is taken:
Wilbur Smith’s Draft Final Report, Comprehensive Traffic and Transportation Study for the BMR)
Bangalore
Distance
Mandya
Tumkur
BBMP
(Kms)
Kolar
Rural
Total
No From To
Ramanagara
Bangalore
Bangalore
Distance
Mandya
Tumkur
BBMP
(Kms)
Kolar
Rural
Total
No From To
Modal shares are highly influenced by trip lengths. RITES (2011) data for
BDA area, given in Table below is used as a basis to assume appropriate
modal shares:
4
Source: http:// essay 535. blogspot.in / 2008/03/some-reflections-on-transport-problems.html
Trip lengths that can attract CRS are normally beyond about 10 to 15
Kms. Thus, CRS mostly captures the traffic from Bus.
Considering all the above, CRS is assumed to attract up to 30% of
commuters within 1 to 5 Km catchment on either side of the railway line.
Depending on its success, this can be increased to cover population
even beyond 5 Km catchment on either side of railway line and also up to
50% of commuters in future as in case of Mumbai. However, demand in
city core area will be less and also catchment will be less due to presence
of competing modes like Metro etc.
Accordingly, Demand for urban/suburban rail traffic is assessed in 3
scenarios:
Catchment
Catchment
Catchment
Catchment
Catchment
Trip Rate $
Per Capita
Share of
Share of
Share of
Share of
Share of
Share of
Modal
Modal
Modal
Modal
Modal
Modal
Year
CRS
CRS
CRS
CRS
CRS
CRS
2011 1.00 1 Km 10% 1 Km 10% 1 Km 10% 2 Km 20% 1 Km 10% 5 Km 30%
After studying the Travel Pattern of existing commuter train services and
after detailed deliberations with S W Railway and GoK, 440.8 Km is
identified as potential CRS network. Demand is assessed in this network
as under:
From the above tables, it can be seen that most important sections from
commuter‟s consideration are:
But all these sections are non-electrified sections and/or mostly single line
sections. For introducing CRS, these sections need to be made double line
electrified sections with automatic signalling.
Passengers
Capacity
(@ 150 per
Distance (Km)
coach in No of
No of @ Total
case of Passenger passeng
Commuter Coaches
S.No Sector From To passenger Km being er trips
Services at being run
coach and Run being
present at present
200 in case served #
of DEMU/
MEMU
coach)
1 MYA SBC MYA 92.88 10 114 17100 1588248 46990
2 YPR SBC YPR 5.35 18 204 30600 163710 4843
3 TK YPR TK 64 14 164 24600 1574400 46580
4 HEB YPR YNK 12.45 6 62 9300 115785 3426
5 HEB YNK BYPL 19.23 2 16 3200 61536 1821
7 DBU YNK DBU 20.72 4 48 7200 149184 4414
8 CBP YNK CBP 46.05 4 30 5300 244065 7221
9 HSRA BYPL HSRA 48.59 6 62 10100 490759 14519
10 BYPL SBC BYPL 12 24 242 40000 480000 14201
11 BWT BYPL BWT 58 20 198 34600 2006800 59373
Total → 108 1140 182000 6874487 203388$
#
Assuming average trip length as 33.8 Km as taken from Indian Railways Year Book 10-11
$
This tallies with the ridership assessment of 150000 made from ticket sales analysis.
@
List of present commuter services is at Annexure - 4
From the above table, it can be seen that present supply is able to cater for
about 30% of commuter demand (medium scenario) of 2011.
The demand for non-suburban passenger trains is based on the long term
growth trends of non-suburban passenger traffic on IR. Historical trend of
passenger and passenger kilometre growth of non-suburban passengers is
given in the Table below.
Business as usual
Aggressive Market capture
In the business as usual scenario, the freight is limited to bulk cargo like cement
and steel, and Exim container cargo. Then freight growth would be at historical
trend – around 1-2 trains per annum.
handled. However, higher freight trains load (per day) on the system are
assumed in the above discussion.
Before introducing any long distance train, Indian Railways assesses the
capacity of the system. If there is need to enhance certain facilities, Railways
themselves plan such facilities and allot necessary funds. Similarly, for
enhancing the freight capacity also, necessary facilities are developed by Indian
Railways with their own funds depending on the requirement.
Measures suggested in various phases of this report are aimed at running trains
at about 10 minutes frequency. These phases are very much enough to take
care of the above cited quantum of increase in long distance trains and freight
trains apart from meeting the commuter requirement.
Therefore, long term growth of long distance passenger trains and freight trains
should not be a cause of concern while planning the commuter services.
Recent commuter systems in India are found to have been falling short of the
initial traffic projections as seen under.
Therefore, to have some idea of the reliability of traffic projections made for
CRS, these projections are compared with BMRCL projections as under:
But, as seen in Table 5.10, CRS demand in 2021 for high scenario is estimated
as 13.52 Lacs which is far less than 34 Lacs projected based on BMRCL
methodology.
Table: 5.14 Assessment of additional services required to bridge demand supply gap
Commuter
Assessed Balance
Commuter Trips after
No of Commuter requiremen Additional
Trips upgrading Additional
Distance Commuter trips (2021) t to be met Services
From To generated present Services
(Km) Services at for Demand by $ rounded
by existing services to Required
present High additional off &
Services @ EMUs /
Scenario Services
MEMUs $
1 SBC MYA 92.88 10 175851 46992 82710 93141 9.415 10
The existing rail network in Bangalore area got developed over a period of time.
The recent major rail projects for Bangalore area:
Project Year
Each of the above projects substantially altered the rail network scenario of
Bangalore. But, the thrust in every project was to complete the project and give
some connection to Bangalore. Scope of none of these projects had any
means or provision to study the rail network in Bangalore area in a holistic and
integrated view. With the result, Bangalore rail system became a cluster of
small piecemeal systems rather than any holistic system. It is due to this
legacy, the system is not geared up for suburban operations. This leaves lot of
potential and opportunity to study and upgrade the system to serve larger public
needs specially commuting needs. In fact, the system needs complete overhaul
and redesign (but not incremental up gradations) to serve as good suburban rail
system apart from serving long distance passenger traffic and freight traffic.
with the system to improve capacity throughout the system. For the purpose of
the analysis, components of the rail system are considered as under:
This is the main hub of Bangalore city. Almost every commuter of Bangalore
wants to have direct link to this station from his/her place. Therefore, maximum
number of trains should pass through this station for better service to the public.
Today, SBC position is such that it cannot handle even one additional train. It is
not in a position to effectively handle a major delay in arrival or departure of
even a single train. As already brought out above, SBC has evolved
historically and needs radical redesign to serve commuters needs and
aspirations. Tinkering is not going to help.
Presently Bangalore yard has 10 platform lines, 6 pit lines (maintenance lines),
8 stabling lines and a few other lines. Platform lines are meant for entraining
and detraining passengers. Pit lines are meant for undertaking the repairs for
each rake (train). These pit lines have necessary facilities for scheduled
maintenance after each trip. Stabling lines are meant for stabling trains during
their idle time or when they are waiting for their turn onto platform line or pit line.
Number of platforms.
Number of lines (platform lines, pit lines, stabling lines, shunting lines
etc.).
Length of each line. More the length of each line, higher is the capacity of
the yard.
Interconnectivity of all these lines. Ideally all platform lines should be
universal i.e. train from/to any direction (BYPL or YPR or MYS) should be
able to enter/exit any platform line.
Connectivity of platform lines with pit lines, stabling lines and shunting
lines etc. Ideally, all platform lines should have connection to all pit lines,
shunting lines and stabling lines etc.
Lie-Over i.e. time spent by each train in the yard (Lesser the lie-over,
more is the capacity).
Requirement of Engine Reversal for the train. More the trains which need
engine reversals, lesser is the capacity of the yard.
Type of Maintenance required for the train in the yard:
6.3.1.2 Platforms:
The 10 platforms present in SBC yard today are fully occupied and there is
hardly any slot on any platform for dealing additional trains. SBC is catering to
3 directions i.e. YPR, BYPL and MYS. If commuter trains are to be dealt from 3
directions, SBC should have at least 2 platforms exclusively for commuter
trains. With the present level of platform occupation, no platform can be
exclusively earmarked for commuter trains. In fact, hardly any additional train
can be dealt on any of the existing platforms. Therefore, it is required to
construct at least 2 additional platforms.
SBC yard has got 4 pit lines sandwiched between platform lines. These 4 pit
lines can be conveniently converted into 2 platforms and they can be earmarked
for commuters. However, the pit lines need to be relocated to accommodate
platforms.
On MYS end of the yard, there is vacant land (Binny Mills Land) which can be
conveniently used for constructing exclusive commuter platforms and/or pit
lines. This is the first and foremost requirement for introducing CRS trains in
SBC.
Being in very prime location, Binny Mills Land may be difficult to get spared to
Railways. Therefore, part of this land if not full can be spared to Railways so
that possible number of platforms and/or pit lines can be constructed here. And
to that extent, SBC can be provided with additional platforms for commuter
trains.
Presently SBC yard is dealing 92 coaching trains (some of them are daily and
some of them are non-daily). Close look at the trains being dealt at SBC
shows:
Trains that need no Trains that need Trains that need Primary
Maintenance Secondary Maintenance Maintenance
(Lie-Over required : 5 Minutes) (Lie-Over required: 3 Hrs.) (Lie-Over required: 7 Hrs.)
Engine Reversal
needed? Yes No Yes No Yes No
Lie-Over ↓
≤ 30 Minutes 8 23
> 30 Mts ≤ 1 Hr 4 4
> 1 Hr ≤ 2 Hr 6
> 2 Hr ≤ 4 Hr 5
> 4 Hr ≤ 6 Hr 1 1
> 6 Hr ≤ 8 Hr
> 8 Hr ≤ 10 Hr 2 8
> 10 Hr ≤ 12 Hr 3 2 3
> 12 Hr ≤ 14 Hr 2 2 5
> 14 Hr ≤ 16 Hr 2
> 16 Hr ≤ 18 Hr 3
> 18 Hr ≤ 20 Hr 1
Total → 26 33 4 22
Details at Annexure-1
Very few trains only leave the yard within the minimum lie-over required.
Majority of the trains are lying-over for more time than required (even
more than 18 Hrs. in case of one train).
52 trains (out of 85) need engine reversals.
It is highly difficult for the yard to handle such massive lie-over and engine
reversals. It is because of this reason, many empty rakes are being taken to
Baiyyappanahalli marshalling yard, Krishnarajapuram, Whitefield and Bangalore
Cantt just for stabling during their idle time. To stable these rakes and to bring
back these rakes to SBC, light engines are also being moved. All these
unproductive movements are badly eating away the capacity of SBC as well as
If such lie-over and engine reversals are eliminated (or minimised), capacity of
the yard can be increased. The solution lies in making the SBC a pass through
station from the present state of terminal station. Or terminal activities
(maintenance of rakes) should be brought down to such a level that rakes do
not spend more time than required in the yard. Thus, all (or some) terminal
activities should be shifted away from SBC to some other convenient location
i.e. additional terminals should be developed. This creates enough capacity to
deal more commuter trains and also to handle any additional long distance
trains and freight trains.
Line No Type of Line Length (in Metres) Length (in Vehicles) Present Utilisation
1 PF-1 659 26 Coaches 63%
2 PF-2 589 24 Coaches 100%
3 PF-3 572 24 Coaches 46%
4 PF-4 598 24 Coaches 71%
5 Stabling Line 476 19 Coaches
6 Stabling Line 476 19 Coaches
7 Stabling Line 559 24 Coaches
8 PF-5 559 24 Coaches 63%
9 PF-6 495 20 Coaches 71%
10 PF-7 462 19 Coaches 45%
11 PF-8 570 23 Coaches 71%
12 PF-9 625 26 Coaches 42%
13 PF-10 602 25 Coaches 63%
85%
92%
3 Pit Lines : 24 Coaches Each
79%
Pit Lines 2 Pit Lines : 21 Coaches Each
60%
1 Pit line : 18 Coaches
75%
75%
At YPR End : 24 Coaches
Shunting Neck
At BWT End : 26 Coaches
With ever growing demand for more capacity, numbers of coaches get
increased for more and more trains. Freight trains are normally full length trains
(means 686 metres). Longer passenger trains and freight trains can be dealt
only on very few lines in SBC yard as can be seen above. Inadequate length of
lines coupled with absence of universal reception and despatch facilities for all
the lines forces number of unproductive (shunt) movements in the yard and thus
adversely affects the capacity of the SBC yard.
Thus, SBC needs to offload some of its terminal activities and also needs to
increase in length of lines.
From the above, it can be seen that majority of the trains enter into SBC yard
from BYPL side. They can come only onto PFs 1 to 7. Out of these platforms,
4 platforms have no exit to other directions. Trains received onto these 4
platforms cannot go anywhere. Presently, trains received from BYPL are being
disposed by:
All the above disposal schemes except the last one consume lot of time.
Engine also needs to be reversed. A few shunt movements (movements from
one line to another within the yard) are also required. These shunt movements
have to wait in between to give way for trains entering and leaving the yard
from/to different directions. In shunt movements alone, each train may need to
spend a couple of hours bringing down the capacity of the yard drastically.
For the trains entering SBC from MYS or YPR, the situation is not this much
critical. Trains from MYS can go either towards BYPL or YPR as seen from
above table. Trains from YPR also can go towards MYS. However, if they are
terminated at SBC, they are to be taken onto stabling lines or pit lines. Such
terminal activities need lot of shunt movements and take away substantial
capacity of SBC.
Due to above cited constraints coupled with heavy lie-over and inadequate line
lengths, SBC is not able to use the platforms and pit lines to the full extent as
seen in above tables.
It is for this reason, any new train announced by Ministry of Railways shall
either run short of Bangalore (like YPR, BYPL or so) or it is accommodated by
making some other existing train to terminate short of Bangalore. Trains which
are ideally required to come to SBC but are presently terminated short of SBC
are:
Terminated
Train No From To
Station Time
66533 BWT KJM KJM 19:10:00
66534 KJM BWT KJM 19:30:00
76506 KQZ BNC BNC 09:40:00
76507 BNC BWT BNC 11:00:00
76508 BWT BNC BNC 17:20:00
76505 BNC KQZ BNC 17:55:00
These trains are during peak commuter timings and they can serve commuters
better if these trains can be brought up to SBC.
Trains coming from MYS side and getting terminated here should be able
to go to pit lines or to BYPL side easily.
Terminating trains should be taken onto stabling lines or pit lines without
reversing the engine and without any shunt movements. This way, the
terminating train shall leave the yard within about 10 minutes.
To achieve these objectives, all the lines of SBC should have entry/exit to MYS
side. However, this connection needs some Binny Mills land. Image showing
typical arrangement of connection to MYS side is shown in figure 5.2 above.
Normally, trains move with 15 Kmph in yards. But with latest improvements in
turnouts and signalling technology, speed in yard can be enhanced to 30 Kmph
while redesigning the yard.
All lines have universal R&D facilities from all directions (BYPL, YPR and
MYS directions).
All lines shall be of full length (i.e. full length freight train or coaching
train).
Other lines like shunting necks, pit lines (if provided) etc. also should be
of full length.
Speed in SBC yard is 30 Kmph
To make all these options feasible, a very meticulous and innovative detailing is
required while redesigning the SBC yard.
Likely to be
Present (if above cited measures are
implemented)
10 14 or 15
Platforms (different lengths and (More or less full length
without universal R&D) and universal R&D)
Capacity
60 pairs of trains per day 150 pairs of trains per day
(commuters, long distance and freight)
Some terminating trains are waiting in stabling lines for their turn onto pit lines.
This necessitates shunt movements and eats away some yard capacity.
Therefore, additional pit lines are required at YPR for increasing the yard
capacity. Work is presently in progress for providing 1 additional pit line. If 3
more pit lines are constructed, terminal capacity of YPR increases to about 60
pairs from the present 37 pairs of trains. Pit lines can be constructed by
converting some of the existing stabling lines into pit lines. Normally, 2 stabling
lines go away for 1 pit line. Therefore, S W Rly should critically analyse the
operational implications of retaining stabling lines as it is and/or replacing a few
of them into pit lines and plan for optimum number of additional pit lines.
Possibility of acquiring military land for Railway operations at YPR also need to
be explored so that additional pit lines can be constructed without any difficulty.
Presently, there are only 2 passenger terminals in Bangalore (SBC and YPR)
as brought out above. These 2 terminals are fully busy with long distance trains
and hardly can deal any more trains (commuter or otherwise). If at all CRS
need to be introduced in Bangalore meaningfully, these 2 terminals are grossly
inadequate and additional terminals need to be developed as already brought
out in above paragraphs. For locating additional terminals, the major criteria
are:
More the terminals, the better it is. More terminals facilitate more dispersion of
congestion and also reduces load on any particular terminal. Thus, more
capacity to run commuter trains. As per the preliminary studies and as per
In fact, this is not a new terminal; But an extension of SBC terminal. As already
discussed in above paragraphs, this area can be provided with a few platforms
and/or pit lines so that these additional platforms can be earmarked exclusively
for commuter trains. The above image shows the typical arrangement of
platforms etc. in Binny Mill Land. This arrangement can accommodate about 12
lines (pit lines or platform lines or any other line). Feeder roads also can be
developed easily for this terminal as this area is well connected by road
network. This is also nearer to the metro station coming up nearby. Therefore,
this proposition is very ideal and most of the problems of SBC can be solved in
one go with this terminal. This arrangement needs full Binny Mill Land. This
land shall make an excellent suburban terminal at SBC to deal commuter trains
from all directions.
Binny Mill land is in very prime location and has lot of commercial value. In
case it is not practicable to give this whole land to Railways, part of the land can
also be spared to Railways so that just a few facilities can be constructed
instead of full-fledged coaching facilities. Binny Mills land issue should be
deliberated with open mind along with all stake holders. Depending on the
extent of land that can be spared, facilities can be planned here. Issue of Binny
Mill land is discussed in detail in Para 7.4.
Mumbai has got many terminals like CSTM, Dadar, LTT, Kalyan, BCT and
Thane etc. Unless so many terminals are planned like this, dispersion of traffic
shall be a big problem.
Number of trains getting terminated at SBC do not need any maintenance i.e.
they do not need any terminal facilities like pit lines etc. These trains are lying
over at SBC for durations as high as 11:55 hours (Details at Annexure-1).
Good number of such trains can be extended into MYS section and can be
terminated at Kengeri, Hejjala, Bidadi, Ramanagara, Channapatna, Maddur and
Mandya. What is required at those stations is just one platform line which can
be easily constructed. Even if one train is terminated at each of these stations, 7
to 10 trains can be terminated in SBC-MYS section. The relief it brings to SBC
is just immense in terms of commuter capacity addition. The trains thus
extended shall also serve as commuter trains from SBC up to that terminal.
However, this arrangement has some logistic problems for S W Railway.
Arranging crew for operating these trains at isolated locations may pose
additional burden on S W Railway. Alternate stations are recommended
additional lines and PFs to deal CRS trains. S W Railway may weigh the
operational ease Vs logistic problems and make appropriate operations plan.
As already brought above, Mumbai has got many terminals like CSTM, Dadar,
LTT, Kalyan, Mumabi Central, Thane etc. Unless so many terminals are
planned like this, dispersion of traffic shall be a big problem.
th
Figure: 6.5 Hejjala 4 coaching terminal
It is highly recommended to develop all the four terminals (Binny Mill, BYPLN,
BAND and Hejjala) as discussed above.
On date, there exists only one freight terminal (SGT) near Whitefield on
Bangalore CRS. For the present level of freight traffic, existing facilities are
good enough. However, as the freight traffic increases, movement of freight
trains from all direction to SGT badly occupies the sections and net capacity for
commuter trains shall come down. Therefore, some more freight terminals
need to be developed in Bangalore area in future. Probably, one freight
terminal in the north will be required first in DBU area. Then some more freight
terminals in south and west can be planned depending on growth in freight
traffic. The new freight terminals should be developed as multimodal logistic
hubs providing one stop logistic solutions to customers. On date, Bangalore
City does not have such terminals.
In the morning time, long distance trains keep arriving Bangalore. During that
time, Down line (Bangalore Cantonment to SBC) is fully occupied and there will
be hardly any slot left over to run commuter trains. This is the time where
commuter trains also need to be run in this direction. During this time, trains in
opposite direction are comparatively less and thus the Up line is underutilised.
The situation becomes reverse in evenings when long distance trains start from
SBC and commuter trains also are to start from SBC. This phenomenon
causes hurdle to commuter trains as well as long distance trains. Any small
hitch anywhere hits series of trains. To address this issue:
The above cited solutions effectively tackle the morning and evening rush of
unidirectional traffic so that commuter trains do not get affected due to the
unidirectional rush.
BYPL area of Bangalore CRS has very peculiar arrangement. Trains from 5
different directions join here, from Bangarapet, Bangalore, Yelahanka, Hebbal
and Hosur. This type of multi directions at a single area affects the train
operations very badly. This being in heart of urbanisation, commuter trains take
a severe hit in this area. Some trains get more priority at the cost of other
trains. But, in this area all the directions are more or less equally important from
commuter‟s point of view. Basic motto of any commuter system is that public
should be able to reach their work places situated at about 70 to 100 Km within
1 hour. With the type of criss-cross movements at BYPL area, the basic motto
of the commuter system just cannot be thought of. Train movements in this
area criss-cross as under:
To →
Bangarapet Bangalore Yelahanka Hosur Hebbal
From ↓
Infringes Infringes
Bangalore- Bangalore-
Bangarapet Bangarapet
Bangarapet - Main Line No Connection
trains. trains.
Flyover Flyover
required required
Infringes
Bangarapet-
Direct Bangalore Direct
Bangalore Main Line -
Connection. trains. Connection
Flyover
required
Infringes
Bangalore-
Direct Bangarapet No
Yelahanka - No Connection
Movement trains. Flyover Connection.
required (via
Channasandra)
Direct
Hosur No Connection No Connection - Fly over exists
Movement
Direct Direct Direct Already Fly
Hebbal -
Connection Connection Connection over exists
From the above it can be seen that to avoid criss-cross movements and for
seamless movement of trains in this area, 4 flyovers are required. These
flyovers in order of priority are:
This tremendously boosts up the capacity of the system. In other words, more
commuter trains can be run in all the directions. These types of flyover
arrangements already exist in systems like Mumbai Suburban. Typical
Apart from flyovers, quadrupling of SBC – WFD also will give substantial relief
to the train operations to tackle criss-cross movements in BYPL area.
At YPR also, criss-cross movements can eat away the capacity of the system.
Trains criss-cross in this area are as under:
To →
Yesvantpur Tumkur Yelahanka Hebbal
From ↓
Direct Direct Direct
Yesvantpur -
Connection Connection Connection
Direct Direct Infringes YPR-
Tumkur -
Connection Connection. HEB line
Direct Infringes TK-YPR No Connection
Yelahanka -
Connection line exists
Infringes YPR-
Direct No connection
Hebbal YNK line and TK- -
Connection exists
YPR line
To →
Yesvantpur Tumkur Yelahanka Hebbal
From ↓
Direct Direct Direct
Yesvantpur -
Connection Connection Connection
Direct Direct Direct
Tumkur -
Connection Connection. Connection
Direct Infringes TK-YPR No Connection
Yelahanka -
Connection line exists
Direct Infringes TK-YPR No connection
Hebbal -
Connection line exists
Apart from Criss-Cross movements at BYPL and YPR area discussed above,
due to presence of Goods Terminal at White Field and Diesel shed in K R
Puram area, so many criss-cross movements take place. After a train is
terminated at SBC, Locomotive comes to diesel shed. After attention, again it
goes to SBC. Similarly, freight trains entering into Bangalore area have to
necessarily come to Goods Terminal at Whitefield for maintenance. All these
cause lot of criss-cross movements in this area.
That means, the trains are subjected to so many obstructions at BYPL, KJM
and WFD and trains virtually crawl from SBC-WFD. If at all any train does not
crawl, it is at the cost of many trains in other directions.
In the long run, when the existing rail network‟s potential is fully tapped (or when
Mumbai suburban like situation comes), the goods terminal may need relocation
to some distant place. Or some more goods terminals may need to be
developed in DBU side or TK side or MYS side or so. Similarly, when the entire
area is changed to electrified territory and diesel traction is totally done away
with, the diesel shed needs re-design and/or probably relocation. Therefore,
proposals like flyovers etc. in K R Puram – Whitefield should be planned in the
changed scenario and therefore not contemplated in the present study.
From the above, it can be seen that how automatic block signalling boosts up
the capacity of rail system. Mumbai, Chennai and Hyderabad are able to run
local trains because they have automatic signalling. Thus, automatic signalling
is a must to introduce commuter rail system in Bangalore.
1. Bangalore – Whitefield
2. Whitefield – Bangarapet
3. Bangalore-Mysore (along with full doubling and electrification)
4. Yeshvantpur – Tumkur (along with electrification)
5. Baiyyappanahalli – Yelahanka – Dodballapur (along with doubling)
6. Banaswadi – Hosur (along with doubling and electrification)
7. Soldevanahalli – Kunigal (line under construction)
To decide on exact strategies for each section or sub section, detailed field
surveys and studies are to be undertaken. When the projects are sanctioned by
IR, normally IR studies all these aspects before deciding the signalling
arrangements.
Traditionally, trains are run with 15 Kmph on loop lines. But, IR has identified it
as mission area to increase speed to 30 Kmph on all loop lines. Wherever it is
not yet increased to 30 Kmph, it should be done on top priority so that CRS gets
benefited.
Commuter system cannot serve the public meaningfully with single line. All the
sections of the CRS should necessarily be double lines. Also the tracks should
be electrified. Diesel traction adds to the already polluted urban environment.
Partly diesel and partly electric traction imposes severe restrictions on
operations and seamless movement of trains is not possible. Without full
Doubling Electrification
Sanctioned Sanctioned
To be sanctioned To be sanctioned
(in order of priority for (in order of priority for
(in order of priority) (in order of priority)
execution) execution)
1. Yeshvantpur – 1. Yelahanka – 1. Kengeri – Mysore 1. Bangalore -
Yelahanka (13 Km) Dodballapur (22 Km) (126 Km) Yeshvantpur - Tumkur
2. Yeshvantpur – 2. Yeshvantpur – (70 Km).
2. Yelahanka – Baiyyappanahalli (18 Yelahanka (13 Km) 2. Soldevanhalli –
Channasandra (14 Km) Km) 3. Yelahanka – Kunigal (45.2 Km)
3. Banaswadi – Hosur Channasandra (14 Km) 3. Yeshvantpur -
3. Ramanagara- Mysore (54 Km) 4. Yelahanka – Banaswadi – Hosur
(94 Km) 4. Yelahanka – Dodballapur (22 Km) (along with doubling)
Chikballapur (47 Km) 5. Yeshvantpur - (67 Km)
5. Soldevanhalli – Chikbanavar (8 Km) 4. Yelahanka –
Kunigal (45.2 Km) Chikballapur (along
with doubling) (47
Km)
The sanctioned projects should be executed as per the priority and new projects
also need be taken up for introducing commuter trains in Bangalore.
If running one goods train is reduced in any section, more than 2 additional
commuter trains can be run on that section. That is the kind of resources a
goods train consumes. To the possible extant, goods trains are not normally
run during commuter timings. However, running goods trains in commuter
timings cannot be totally avoided. These unscheduled trains hamper the
Presently goods trains which are to go from DBU side to HSRA side are
being taken to YPR, engine getting reversed and taken to HEB and then
to HSRA. A direct connection from YNK to HEB avoids such engine
reversals and also YPR gets relieved. This creates additional capacity at
YPR. Such connection from YNK to HEB may need to pass through
heavily built up area. Alignment should be fixed carefully and
meticulously for this connection so that relocation of structures shall be
least. Until such bypass line comes, LOGH should be made as junction
station with some loop lines so that trains from YNK need not go to YPR
for engine reversals.
Freight train movements on CRS should be planned only during off peak
hours especially during nights. In fact, South Western Railway has been
already adopting this strategy to some extent or other.
Trains have to observe the signals at Level Crossings and stop if required.
When running a train at every 10 minutes or even less is contemplated, level
crossings become seriously critical in the system. They need to be eliminated
by ROBs/RUBs or so. More the manned Level Crossings in a section, more
the running time of the trains. Average spacing of manned level crossings in
CRS area are:
Average spacing of
Section Length (Kms) manned Level Crossings
(Kms)
YPR-YNK 12.45 1.78
YPR-BYPL 16.11 1.79
YNK-DBU 20.72 1.88
SBC-MYA 92.88 2.32
BYPL-HSRA 48.59 2.56
YNK-BYPL 16.12 2.69
YNK-TK 64.00 2.78
YNK-CBP 46.05 4.61
SBC-YPR 5.35 5.35
Apart from spacing of manned level crossings, traffic at each of these level
crossings also affect the train operations. More the TVUs (Train Vehicle Units),
more is the average running time of the trains. TVUs of LCs in CRS area can
be appreciated as under:
YPR TK 64.00 1 3 5 2 12 23
Total → 7 3 4 20 19 22 66 141
Details of Level Crossings with TVUs more than 50000 are at Annexure-10
Level crossing becomes unmanageable and severely affects the train as well as
road operations if the TVU exceeds about 100000. How a train will be able to
maintain its speed with the level crossings with heavy TVUs and with less
average spacing as seen above is anybody‟s guess. Suburban trains should be
run at 5 to 10 minute frequency. How can a gate with 4 Lakh TVUs be opened
and closed once in 5 to 10 minutes. It is difficult even to think of. In commuter
train operations, every minute counts. Even a couple of minutes early/late
matters for the commuters. Therefore, these manned level crossings should
be replaced by ROB/RUBs on top most priority in the interest of commuter train
operations. By replacing the level crossings with ROB/RUBs, commuters
travelling by roads also save lot of time.
The snail pace of ROB‟s execution deters the planners to sanction new ROB
projects. At this pace, elimination of more than 100 Level crossings in CRS
area just cannot be thought of. A few things worth noting are:
The above issues are brought out here just to reiterate the seriousness of the
issue of level crossings. Like Jharkhand Government, GoK also may consider
entrusting ROBs execution (or at least critical ROBs) to one agency.
5
http://www.konkanrailway.com/node/610
6
Hon’ble Minister for Railways Sri Dinesh Trivedi’s 12-13 Railway Budget Speech
6.4.10 Quadrupling
With the above cited measures, on all commuter sections (double line sections),
trains can be run at about 10 minutes frequency during peak hours. However,
such running can be made comfortable and also enhanced further (to 5 minutes
frequency or so), by having an exclusive corridor for commuters. Wherever
quadrupling is not feasible due to land problems or so, at least tripling can be
done in those stretches. With this, 2 lines (1 line in case of triple line) can be
earmarked exclusively for commuter trains. Priorities of quadrupling:
With the implementation of CRS, every station has to cater for stoppage of
more number of trains. With EMUs, every station can act as terminal. Ideally,
an exclusive platform should be nominated for commuter trains at every station.
Therefore, 1 or 2 additional lines and platforms should be provided at least at
alternate stations of the CRS stations. One of the platforms can be even dead
end platform so that it will be earmarked exclusively to terminate/originate
EMUs. These additional lines can also be used for stabling EMU rakes during
nights and weekends. Other facilities like foot over bridges, ticketing windows,
vending stalls, parking space etc. should be created (or upgraded) at each
station.
More the halts in CRS, the better it will serve the public. Ideally:
City core area (lying within 15 km radius from SBC): Here population
density is more and very 1.5 Km or so, there can be a halt.
Area lying between 15 to 30 Km of SBC: Here, population density is
moderate and every 2.5 Km or so, there can be a halt.
Beyond about 30 Km of SBC: Population density is relatively less and
every 3 to 4 Km, there can be a halt.
Spacing of stations in Mumbai, the role model for any CRS in India is as under:
From the above, it can be seen that Bangalore needs good number of additional
halts.
Additional halts reduce the average speed of the trains. Hence all
activities to boost average speeds should be completed before additional
halts are introduced.
Provision of adequate length of platforms, FOBs, ticketing counters,
parking space etc. should be feasible at these halts.
Feeder roads should be feasible and should be developed for every halt.
Space for developing a bus halt is also required.
There need to be habitations nearby so that the new halt gets patronised.
Land should be available for all these facilities for establishing a new halt.
While acquiring the land, it needs to be planned for 20 coach trains
though, that much lengthier trains are not proposed now. This goes a
long way to enhance the CRS capacity in future.
Presently there are about 64 halts in the CRS area of about 440 Km. As felt
necessary by public and various voluntary organisations, another about 45 halts
are required in the CRS area (List at Annexure - 3). However, the list does not
cover the additional halts of full CRS area. These additional halts and even
more can be made possible provided the issues brought out above are
addressed and a detailed field survey is done duly covering above cited
aspects.
Existing terminals SBC and YPR have got certain natural convenience to deal
trains of particular direction as shown under:
If a train from DBU is terminated at SBC instead of YPR, extra time taken is
about 15 to 25 minutes. Similarly, if a train from BWT side is taken to YPR
instead of SBC, it takes about 15 to 25 minutes extra. This aspect is not
considered in the present time-table. With the result, both the terminals are
dealing trains from virtually all directions. If the time table is changed making
the terminals strictly as per the above cited directions:
A commuter needs a well-integrated, faster and simple terminal access (not like
long distance passenger who does not mind spending even 30 minutes extra
moving from one platform to another etc.). Hence it would be preferable to
develop a new terminal exclusively for CRS users.
RITES surveyed the surrounding open areas - both railway and non-railway
lands, to locate the terminal. While available railway land is not sufficient to
provide the terminal, open land vacated by the Binny Mills, lying abutting the
railway land is most promising. The terminal can be located at this place with
ease of access to the railway station. The place also has road access and thus
it can be designed into a multimodal terminal.
This can also be connected to the Mysore line directly as it lies towards the
Mysore end. The terminal would connect to other directions also suitably.
Therefore, it is suggested to develop an exclusive commuters handling area
(platforms, foot over bridges, feeder roads etc.) in Binny Mills Land.
DEMU/MEMUs are not meant for mass transit. They are medium transit
systems. EMU is specially designed for mass transit system. EMU
capacity is theoretically 20% more than DEMU/MEMUs. Practically, their
capacity is even 50% more considering standing commuters,
overcrowding etc. Ultimately, any mass transport urban system has to
switch over to EMUs.
Mumbai MRVC is using EMUs. Even Hyderabad MMTS, initially planned
for MEMUs. Later on, realising the limitations of MEMU/DEMUs, they
switched over to 3 car EMUs. This change in planning resulted in some
infructuous expenditure also.
Thus, EMU rakes are best suited for commuter operations.
However, routes where EMUs are to be run need special survey and
attention especially with reference to tracks spacing and platform heights
and lengths. Such attention is required only in CRS network of about 440
Km (where EMUs are proposed to be run).
Therefore, it is suggested to go for 16 car MEMUs for trains presently
serving commuters but travelling beyond the CRS (like trains to MYS,
MKM or so) and 15 car EMUs for trains going to ply within CRS area.
Cost estimates are also made accordingly.
Different features discussed above come with correspondingly higher
costs. EMUs normal life is about 35 years. It may be even over used by
6.9.1 Parameters
The operating plan for suburban system would be dictated by the available
capacity and type of trains run and the type of traffic different types of the day.
Mumbai‟s main terminals (CSTM and CCG) are dead end terminals
whereas SBC and YPR are passing through terminals connecting many
directions.
Mumbai is mostly linear system whereas Bangalore is a star like system.
CRS need to take care of criss-cross movements at BYPL, YPR etc. On
this count, Bangalore has less operational flexibility compared to Mumbai.
Mumbai has mostly quadruple lines whereas Bangalore will have double
lines.
Headway in Mumbai is 3 to 4 minutes due to quadruple lines. But in
Bangalore, it will be about 8 to 10 minutes due to double line.
This 8 to 10 minutes headway need further moderation considering
efficiency factor.
Thus, in an hour, about 6 trains can be run in Bangalore. These include
commuter trains, long distance trains, freight trains, empty trains,
departmental trains, provision for maintenance blocks etc. etc.
Suburban and Non Suburban travellers have different patterns of travel. Long
distance travellers expect to arrive in the morning, say between 5.30 and 8, and
depart late in the evening say 1900 to 2200 hours. However, these travellers
are not as sensitive to time as the suburban travellers are and thus little more
flexibility is permitted with these trains.
The suburban travellers have a different peak travel pattern – they like to rush in
before offices open and rush out when offices close. In Mumbai, on the Central
In addition to the peak, the day can be split into off peak and lean. Lean period
will be from 2300 to 0500 hrs. and the remaining 12 hours being off peak hours.
Frequency of trains during peak can be 10 minutes, during off peak 15-20
minute frequency, and during the lean period will be every 45 minutes or 1 hour.
Typical potential for headway for Bangalore CRS trains is as under:
A detailed time tabling of these schedules will have to be done to see how each
sector is served but it is beyond the scope of this report. Hourly distribution of
potential number of CRS trains that can be run after the CRS is implemented is
given at Annexure 9. This annexure is made duly considering the present
scheduled trains and making a suitable provision for non-scheduled trains,
freight trains, maintenance blocks etc.
Hour wise beak up of existing services (total trains as well as trains serving
commuters) are given in Annexures 7 and 8 respectively. These annexure
indicate that during the morning and evening peak periods of 0800 to 1100 hrs.
and 1700 to 2000 hrs., except in two sections all others have 4 or fewer trains.
Even the lone exception of SBC-BYPL-BWT section has 5 trains. Thus,
retaining the existing services intact, it is possible to meet the peak services of
the CRS as hourly capacity of fully developed system is going to be 7 to 8.
At any moment, normally about 10% to 20% of the total rakes will be under
maintenance in EMU sheds. Balance rakes are under run. However, majority
of the rakes are stabled in nights and on weekends as less number of services
are run. 10% to 20% of rakes are always under run whether during nights or on
weekends. Thus, stabling arrangements are required for about 75% of the
rakes. Plan for stabling rakes is a part of detailed time tabling of services by S
W Railway and any study like the present one cannot attempt to draw stabling
plans. However, sufficiency of the infrastructure to facilitate stabling is
discussed as under:
Capacity enhancement of existing rail network has been brought out above
sections. However, the mission of commuter rail shall not stop there. It is a
continues process to enhance capacity and to extend the rail network to new
geographical areas to keep in pace with growing public needs.
MRVC in its phase II and phase III plans, made proposals to extend the network
to new areas which Indian Railways cannot do with its resources.
Suggesting alignments and locations for rail network to new areas need lot of
physical survey specially details about road network, demand pattern and land
availability.
7
DPR for High Speed Rail Link from City Centre to Bangalore International Airport by DMRC (2007)
Travel Time for an air traveller to reach Airport without High Speed Rail
Link, but by extension of CRS to airport =
Maximum travel time saving due to High Speed Rail link is only for the air
travellers who stay just near to any of the high speed rail stations i.e.
Cubban Road or Hebbal or Yelahanka. For the rest, the travel time
saving may not be substantial and may be even negative in some cases.
Extension of CRS network to airport (about 6 Km) on grade costs less
than Rs 100 Crores. Even if small part of this is required to be taken on
elevated route, then also the costs are far less than the costs
contemplated for HSRL.
In view of the heavy cost implications and in view of the minimal time
advantages to larger air travelling population, it may be worth reviewing
the issue in detail before making any final investment decision.
Savings by such review alone may finance the entire CRS project costing
Rs 8000 to 9000 Crores.
To propose exact alignment of CRS extension to airport (and arriving at to
what extent elevated track is required) and to assess the exact
comparative financial implications, a separate physical feasibility study is
required.
It is worth noting that Hyderabad MMTS phase-II provides for a rail link to
Shamshabad Airport just by extending the existing rail network by about 6
Km.
In any highly urbanized area, land definitely is a crucial issue. All big plans and
projects may get struck up when it comes to “land”.
In the context of CRS Bangalore, land issues that can change the game and
that need special attention by GoK are brought out in brief here.
For doublings and triplings, except at few locations, existing Railway land would
suffice. Additional land may need to be acquired at certain locations. Physical
field survey is required to identify the land requirement.
To serve more public, more stations need to be developed in the CRS. For
every such station, land for platforms, ticketing, parking, commercial space etc.
is required. Land is also required to develop the feeder roads to the new
stations and for bus stops. At existing stations, available Railway land may be
mostly sufficient to develop required facilities. However, for developing new
halts, land may need to be acquired.
If at all there exists one single most important issue that can bring CRS to
Bangalore, it is Binny Mills Land in SBC yard. This land is just a natural
extension of SBC yard and therefore, can be connected to SBC and other rail
network very easily and so naturally. This facilitates construction of additional
platforms exclusively for commuters so that commuters and long distance
passengers will have separate facilities at SBC. This land can also help for
locating lines, platforms, FOBs etc. to deal exclusively commuter trains so that
load on over saturated SBC get relieved which in turn help to run more and
more commuter trains in the entire CRS. Easy connection of SBC yard to MYS
side and thus making almost all lines of SBC universal for receipt/dispatch
from/to any direction is also possible with this land.
It is highly recommended that this land entirely should be made available for
Railways for bringing best CRS to Bangalore. In exceptional difficulties, if part
of this land is spared to Railways, other scaled down options can be explored
wherein capacity additions also shall be accordingly less.
To put in simple and plain words: “Without Binny Mill Land, there may not
be CRS”.
Binny Mills Land is recommended for using as an exclusive CRS trains
handling area in this report.
PFs, FOBs etc. of SBC yard are very much congested even with present
level of passengers. With increase in CRS trains, passengers present at
any moment in SBC area will become more and more; and cause
inconvenience to commuters as well as long distance passengers.
Exclusive CRS area in Binny Mills Land will address this issue. Without
Binny Mills Land, passengers handling may be unmanageable at SBC.
For handling commuters on a big scale, double discharge platforms are
ideal. Mumbai has double discharge platforms at important stations like
CSTM, CCG, and Dadar etc. Commuters entrain and detrain the train
from either side of the train (rather than from conventional one side
platform). With double discharge PFs, halt time required for the EMU at
the station will be less. Thus, more trains can be run in a given time.
Such double discharge platforms need more space. With Binny Mills
land, double discharge platforms are possible for commuter trains.
Without this land, concept of “double discharge platforms” may be
probably totally absent in SBC.
To handle passengers on big scale, in case Binny Mill Land is not
available, 2 level PFs may be required i.e. Long Distance trains are to be
dealt on ground floor and commuter trains are to be dealt on First Floor.
Such multi-level PFs are to be connected to all the 3 sides i.e. MYS, YPR
and BYPL side. Such arrangements are not impossible, but costs very
high. SBC yard alone may cost something like Rs. 5000 cores or so.
SBC has to run EMUs in 7 different directions. To start any service in the
early morning to any of these directions, a few EMU rakes needs stabling
at SBC during nights. Without Binny Mill land, it may not be possible to
stable any EMU rake in nights.
Capacity of SBC yard estimated as 150 pairs of trains per day in chapter
6 is based on the assumption of availability of full Binny Mills Land. If all
the remodelling suggested to SBC yard is done without Binny Mills land,
the capacity of SBC yard will be somewhere around 100 to 120 pairs.
The most crucial activity of connecting as many lines as possible of SBC
yard to MYS side reduces the length of various lines considerably in SBC
yard. Repercussions of reduced lengths of lines are already discussed in
this report. To maintain the same length of lines (or to increase) even
after connecting them to MYS side, Binny Mills land is essential.
Ideally, SBC should not have any terminal activities (i.e. pit lines etc.).
But, presence of a couple of pit lines at SBC will be handy in the long
term interests of the system. If Binny Mills land is not present, when all
the existing pit lines are converted into PFs for CRS trains, pit lines will be
totally absent. If any pit line is retained, number of PFs will come down.
With Binny Mills Land, there will be flexibility in redesigning SBC yard duly
retaining a few pit lines so that future train operations have flexibility,
especially with reference to introduction of any new trains. Though
BYPLN 3rd coaching terminal is contemplated, there may be resistance
from public to shift 100% terminating trains (at SBC) to BYPLN. To meet
such eventuality, a few pit lines may need to be retained at SBC. Such
planning needs Binny mills land.
Binny Mill land issue assumes prominence and significance due to the
commercial value it has got.
On date, there exists only one freight terminal (SGT) near Whitefield on CRS.
For the present level of freight traffic, existing freight facilities are considered
good enough. However, as the freight traffic increases, movement of freight
trains from all directions to SGT badly occupies the sections and net capacity
for commuter trains shall come down. Therefore, in future, some more freight
terminals need to be developed in Bangalore area. Probably, one freight
terminal in DBU area and one in TK area will be required. Land will be required
for these freight terminals.
Land is required for doublings, flyovers etc. suggested in this report. Detailed
field study is required to assess the total land requirement, land available with
Railways and state government and private land requirement.
8
Source: http://right2information.wordpress.com/category/rti-success-stories/page/3/
Vision of any city comes from its master plan. If master plan is made with due
care and vision, probably city development, particularly the transport problems
do not pose serious problems. Bangalore Development Authority is
contemplating to make City Master Plan for 2035. In fact, it has also called for
suggestions from public in this regard. South Western Railway should be
actively associated to identify future land requirements for Railway use. Land
requirement for all the above cited railway uses should be thoroughly studied
(by engaging a professional consultant if required) and analysed and land
should be clearly earmarked in the master plan for railway use. It is worth
noting that Hyderabad Metropolitan Development Authority (HMDA) earmarked
land for future Railway passenger terminal at Manoharabad and
Edulanagulapalli, freight terminal at Ravulapalli and passenger-cum-freight
terminal at Timmapur and Bhongir in the Hyderabad draft master plan published
in 20109.
Identifying land for railway use needs physical survey and series of
deliberations with various stake holders. In fact, it is a separate study by itself.
Therefore, specific locations (for earmarking the land for railway use) are not
suggested in this report.
9
source: http://www.thehindu.com/todays-paper/tp-national/article2297287.ece
Converting all CRS sections into double line, electrified and automatic
signalled.
Zero based redesign of SBC yard.
Developing 3rd coaching terminal at BYPLN.
Developing 4th Coaching terminal at Hejjala.
Procuring rolling stock (EMUs and MEMUs).
Developing EMU cum MEMU shed at BAND.
Bypass line at YNK (connecting DBU and CBP lines).
o Entry to MYS side from almost all the lines of SBC yard.
o Full length shunting necks and stabling lines and pit lines (if any).
Entry to MYS side facilitates movement of more trains to Mysore side and
to terminate trains (which do not need any pit line attention) at different
stations of MYS section. This greatly relieves SBC and increases
commuter capacity of SBC.
After finalising the plan of SBC, detailed phase wise activities are to be
drawn. Typically, a few lines are dismantled at a time, new line (or
platform or so) which is supposed to come in that location is to be
constructed, they are to be linked to adjoining lines, electrical wiring and
signalling arrangements should also be done for those lines. Then few
more lines are taken up. Such activity may warrant regulation or
cancellation of trains. This complex activity involves detailed and
meticulous stage planning duly associating Civil Engineering, Electrical,
Signalling and Traffic branches of the Railway. All these activities may
run into a few months or even a year or even more. During such time,
travelling public is put to inconvenience to some degree or other.
With the kind of trains congestion and passengers‟ congestion at SBC
now, attempting to revamp the yard without offloading substantial
operating activity to alternate terminal is considered very risky. It is likely
to lead to chaos and invites avoidable public criticism.
Therefore, a very meticulous and well deliberated stage plan need to be
drawn by S W Railway to execute SBC yard remodelling.
YPR-TK, YPR-BYPL-HSRA and YNK-CKP sectors are technically not
dependent on SBC revamp. Additional trains in these sectors can ply
upto YPR. However, when SBC revamp is not done and additional
services from these sectors are not extended upto SBC, YPR may not be
able to handle additional commuters‟ congestion.
Due to morning and evening rush of unidirectional traffic and due to
meeting of lines from different directions at BYPL, and due to presence of
SGT and diesel sheds at WFD and KJM area, trains movement from SBC
to WFD is very critical. SBC – BYPL section is presently over saturated
and cannot handle even one additional train. Therefore, twin single line
arrangements from SBC to BNC and automatic signalling from BNC to
WFD are to be provided at the earliest so that SBC-BYPL section
capacity is enhanced.
Due to morning and evening rush of unidirectional traffic, commuter trains
may not get paths in YPR-SBC section. This needs additional capacity in
SBC-YPR. This block section is already provided with Twin Single Line
arrangements. This section may need to be further provided with IB
(Intermittent block) signals for both lines for both directions so that this
section capacity almost doubles.
Receipt of EMU/MEMUs should get synchronised with availability of its
maintenance facilities and readiness of the sections where these rakes
are to be run.
Platforms raising/lengthening and other works like checking tracks
spacing in yards en-route are to be done before EMUs start running.
Presently no facilities exist for EMU rakes maintenance in SBC area.
EMU services cannot be introduced unless EMU shed is developed. As
brought out in other chapters, EMU shed may need to be developed at
BAND. EMU cum MEMU shed can be planned for about 60 rakes.
However, actual facility needs to be developed for about 35 rakes of 16
cars each. Though initially 9 car EMU rakes are planned, facilities are
recommended to be developed for 16 car rakes because MEMUs are
going to be 16 cars right from the beginning. Cost difference of this
facility for 9 car rakes and 16 car rakes is also not substantial.
CRS is spread over 440.8 Km in 12 sections as already discussed in
other chapters. Electrification, doubling and automatic signalling is
normally done taking one section as one unit. To avoid duplication of
work, all the three (i.e. electrification, doubling and automatic signalling)
can be done simultaneously. Apart from this, up gradations of platforms,
procurement of MEMUs, EMUs etc. can also be done section wise so that
one section at a time can be implemented. Section wise Block Cost
estimates of various activities are placed at Annexure-5.
Rakes requirement calculations are done assuming on 15 car EMU rakes.
Though there is heavy demand for commuter services, patronage may
not pick up immediately as soon as service is started due to many
practical problems. Therefore, the EMU services proposed can be
started with 9 car EMU rakes initially and can be changed to 12 car rakes
and 15 car rakes in phases. This also helps in judicial phasing of
As can be seen from the block cost estimates (Anneure-5), rakes (EMUs
and MEMUs) cost and EMU/MEMU shed costs together constitutes about
20 to 25% of total costs.
Some design features of rakes were already discussed Para 6.8.3.
Depending on design features of EMU, maintenance facilities required at
EMU shed also vary.
The block cost estimates are made considering the latest design EMUs
with 3 car EMU units. (Energy efficient 3 phase motors, stainless steel
body, GPS based passenger information system etc.)
However, in case GoK desires to bring down the costs, the issue can be
deliberated with MoR and ICF to finalise the features required.
Such cost cutting measures can save upto about 40% of cost (of rolling
stock plus cost of EMU shed). On total project cost of Rs. 8000 to 9000
crores, this savings may work out to upto about 10% to 12% depending
on the design finalised.
As EMUs/MEMUs are going to serve more than 35 years and as in
between no major technological up gradations are normally done to the
Apart from the above cited issues, phasing of investments and corresponding
benefits to the public are also important considerations while deciding the
phases. Client advised that they had deliberated among their officials and
desired to keep TK, CBP and HSRA sections under Phase 1 and balance in
phase 2. Accordingly, total proposed investment is recommended in 3 phases.
However, during the meeting organised by DULT on 11th July 2012, some
Railway officials present expressed that a small sub-set of activities out of total
scheme of CRS project can be completed immediately (in about 6 months to 1
year time) and a few additional services can be run to give some immediate
service to the public and rest of the CRS project can follow later. The Railway
officials present during the meeting were DRM, CTPM and other divisional
officers (along with GoK and RITES officials). Sub-set of activities suggested
were by the Railway officials were:
Making SBC – BNC into twin single line and BNC – BYPL into automatic
signalling or IBs.
8.6 Phase 1A
MEMU rakes can be run on electrified double line sections i.e. SBC-BWT
and SBC-MYA sectors. Additional services possible with these 5 rakes:
Commuter trips
Potential $ Additional
Investment that can be
(Services that can Services
Phase (in Crores of generated per
be additionally proposed to be
Rupees) day at the end of
introduced) introduced #
Phase 1A in lakhs
1A 173 24 24 4
$
In addition to enhancing the capacity of existing services by replacing with
MEMUs and EMUs. Services in both directions together are indicated.
# Each service proposed is assumed to originate and terminate in the same
section. For example, if a new service starts in SBC-YPR section and ends in
YPR-TK section, it is counted as 2 services in this figure.
8.7 Phase 1
Total
Activity
Per
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Qty
Qty
Qty
Qty
Qty
Qty
Qty
(Cr)
1 Doubling 12 Km 16.12 194 48.59 583 46.05 553 177 1330
2 Electrification&& 1.25 Km 32.24 40 97.18 121 10.70 13 128.00 160 92.10 115 471 449
3 Auto Signalling 0.75 Km 16.12 12 48.59 36 5.35 4 64.00 48 12.45 9 46.05 35 441 144
4 Extn/Rising PFs 3 Stn 2 6 4.00 12 1.00 3 10.00 30 2.00 6 6.00 18 53 75
Facilities at
5
Terminals
15 Stn 1 15 1.00 15 1.00 15 1.00 15 1.00 15 9 75
Addl. lines at
6
Stns$
10 Line 1 10 4.00 40 5.00 50 3.00 30 36 130
Facilities at
7
Exg. Stations^
10 Stn 2 20 4.00 40 1.00 10 10.00 100 2.00 20 6.00 60 53 250
9 car EMUs (to
8 replace exg. 36 Rake 0.08 3 0.92 33 0.21 8 0.79 28 2 72
services)&
9 car EMUs (for
9
new services)*
36 Rake 2.5 90 7.51 270 0.23 8 2.77 100 0.64 23 2.36 85 24 576
Sections Cost Total -> 387 1117 41 536 81 939 3101
10 Development of EMU cum MEMU maintenance shed at Banaswadi → 200
11 SBC yard remodelling duly including Binny Mill Land → 370
12 Facilities at BYPLN (4 pit lines proposed in Phase 1A; Balance 6 pit lines, stabling lines PFs etc.) → 160
Total Cost of Terminals → 730
Total Cost of phase 1 (Sections Cost + Terminals Cost) → 3831
$
2 additional lines at terminals and one additional line at alternate stations are recommended
^
Facilities like parking, waiting & ticketing area, bus stop etc. are required to cater for increased commuter traffic.
&
Existing services requiring replacement with EMUs can be seen at Annexure -4
*
EMU rakes requirement at Annexure -6 assumes 15 car rakes. However, in this phase, 9 car rakes recommended.
&&
Where exg single line is electrified, one line cost is taken. Where exg Single line is non-electrified, both lines cost is
taken.
Commuter trips
Potential $ Additional
Investment that can be
(Services that can Services
Phase (in Crores of generated per
be additionally proposed to be
Rupees) day at the end of
introduced) introduced #
Phase 1 in lakhs
1 3831 330 172 8
$
In addition to enhancing the capacity of existing services by replacing with
MEMUs and EMUs. Services in both directions together are indicated.
# Each service proposed is assumed to originate and terminate in the same
section. For example, if a new service starts in SBC-YPR section and ends in
YPR-TK section, it is counted as 2 services in this figure.
8.8 Phase 2
Per
Amount
Amount
Amount
Amount
Amount
Amount
Amount
(Cr)
Qty
Qty
Qty
Qty
Qty
Qty
Qty
16 car MEMUs
1 (for replacing 21 Rake
exg. services)@
2 Doubling 12 Km 20.72 249 45.20 542 66 791
3 Electrification && 1.25 Km 20.72 26 90.40 113 111 139
Automatic
4 0.75 Km 19.23 14 20.72 16 45.20 34 59.45 45 92.88 70 237 179
Signalling etc.#
Extension/
5 3 Stn 1.00 3 1.00 3 3.00 9 3.00 9 8.00 24 12.00 36 28 84
Rising of PFs
Facilities at
6 15 Stn 1.00 15 1.00 15 1.00 15 1.00 15 4 60
Terminals
Addl. lines at
7 10 Line 1.00 10 3.00 30 4.00 40 2.00 20 6.00 60 7.00 70 23 230
Stations$
Facilities at Exg.
8 10 Stn 1.00 10 1.00 10 3.00 30 3.00 30 8.00 80 12.00 120 28 280
Stations^
9 car EMUs (for
9 36 Rake 1.44 52 1.56 56 1.00 36 0.15 6 0.85 30 3.00 108 8 288
new services)*
Sections Cost Total -> 89 405
819 65 254 419 2051
10 Developing Hejjala 4th Coaching Terminal→ 200
Total Cost of Terminals → 200
Total Cost of phase 2 (Sections Cost + Terminals Cost) → 2251
@
Services requiring replacement with MEMUs are at Annexure – 4. Costs included in phase 1A; Hence not shown.
#
SBC-BNC is recommended as twin single line. All other sections are recommended for Automatic Signalling.
$
2 additional lines at terminals and one additional line at alternate stations are recommended
^
Facilities like parking area, waiting/ ticketing area, bus stop etc. required to cater for increased commuter traffic.
*
EMU rakes requirement at Annexure-6 assumes 15 car rakes. However, in this phase, 9 car rakes recommended.
@@
Addl Services are proposed based on demand (high scenario) for 2021. In case patronage is more, services can
be increased upto the potential of the section simply by procuring additional EMU rakes
##
Potential is given in terms of services that can be introduced in both directions together in commuter timings
(Annexure-9) with the proposed up gradations duly making reasonable provision for freight trains, long distance
trains, maintenance operations etc.
$$
Share in overall commuter demand of the CRS area. This demand is expected to be met in this phase.
&&
If existing single line is electrified, cost is taken for one line only. If existing single is non-electrified, cost is taken
for both lines.
8.9 Phase 3
$ Commuter trips
Potential Additional
Investment that can be
(Services that can Services
Phase (in Crores of generated per day
be additionally proposed to be
Rupees) at the end of Phase
introduced) introduced
3 in lakhs
& &
3 2504 NA NA 25
$
In addition to enhancing the capacity of existing services by replacing with MEMUs and EMUs.
Services in both directions together are indicated.
&
It is recommended to increase length of EMU cars in this phase. However, this phase can also be
converted into introduction of additional services instead of lengthening of existing EMU rakes as
enough potential is available to introduce additional services as seen in above table.
Additional EMUs proposed in this phase are for increasing the length of EMU
rakes. However, these additional EMUs can also be used to run additional
services instead of lengthening existing rakes as CRS network will have
potential to run additional services with various up-gradations recommended.
Once the above phases are completed, to increase the capacity of the system
further, it will be required to remove finer bottlenecks. Also it is required to
extend the CRS to new geographical areas. Some activities to take forward the
mission of CRS Bangalore are:
side) so that freight trains need not enter into whitefield area
unnecessarily and eating away commuter capacity.
l. Development of Ring Rail around the city to cover greater public (One at
40 Km radius and another at 60-70 Km radius from SBC).
9 Return on Investment
9.1 Extra Revenues to GoK due to implementation of CRS
Apart from direct revenues in the form of surcharge, there will be indirect
revenue to GoK due to increase in property values. To appreciate such
revenue, a broad idea is presented as under:
Out of the identified CRS network of 440.8 Km, about half the network is
in Bangalore Urban District / BBMP area.
Area where property prices are going to increase due to CRS
implementation is assumed as about 2.5 Km width ( i.e. about 1.25 Km
on either side of the track)
This works out to about 1100 SqKm i.e. about half the area of urban
district area.
Property Tax collection of BBMP for 11-12 (approx.): 1500 Cr
Income by way of Stamps and Registration charges in 11-12 10: 3500 Cr
Total: 5000 Cr
Against this, contribution of CRS influence zone (about half): 2500 Cr
If the property values shoot up by 50% in the first 1 or 2 years (this is
somewhat conservative estimate, actual shoot up may be even more),
increase in revenues to GoK due to implementation of CRS is about Rs
1250 Cr. This Rs 1250 Crores need to be enhanced by another 25% to
cover hikes of property values in rural districts of CRS network (as they
constitute balance 27% of the revenue).
That means, more than Rs 1500 Crores return to GoK in the first 1 or 2
years.
Even if it is assumed that property values become stagnant after 2 years,
this additional revenue of Rs 1500 Cr accrues to GoK every year
thereafter.
That means a return of about 1500 Crores per annum to GoK on an
investment of Rs 8000 to 9000 Crores. This is in addition to giving a
10
Income for the state of Karnataka is Rs 4800 Crores in 11-12 out of which 73 % is from Bangalore Urban Area –
source : http://www.thehindu.com/news/states/karnataka/article3009869.ece)
reduction (due to fully developed CRS) in one or more of the above modes shall
bring great savings to GoK as the per Km costs are huge (Metro / High Speed
Rail Link to Airport: Rs 250 Cr/Km, Mono Rail : 175 Cr / Km).
Savings on account of such review can be like Rs. 10,000 crores as brought out
in discussion about cost of overlap (Para 2.9 and Table 2.9). Savings from
review of “High Speed Rail Link to Airport” proposal as brought out in Para 6.11
alone can fully finance this CRS implementation project of Rs. 8000 to 9000
crores.
Rate of return depends on the demand and pricing. For a commuter rail project,
especially for a system like Bangalore, demand is not an issue. Demand is
normally much more than the project can offer. But, the pricing is very tricky.
Any business model adopts scientific pricing model like demand-supply model
(price is fixed such that demand equals to supply) or cost plus profit model. As
is well known, Commuter train fares are not decided based on any of these
scientific methods. Fares are decided based on popular considerations without
concerning about the costs incurred to produce the service. Therefore, it is too
much of an optimism to think in terms of recovery of capital costs or even
running costs from a commuter project.
In this context, costs and returns scenario of Indian Railways is worth looking at.
Indian Railways accounting system is not in the form of a typical profit and loss
statement which normally any corporate entity maintains. It is in the form of
various indices and comparisons to previous years. Most of the assets (Track,
Signals, Locomotives, and Stations etc.) are used for all trains i.e. commuter
trains, long distance trains, freight trains etc. Therefore, it is practically not
possible to bifurcate various O & M costs into different categories. However,
certain parameters of Indian Railways are given below to give an idea of Indian
Railways financial returns.
Earnings Earnings
Vehicle Km
Segment (in Crores of (Rupees per
(in Millions)
Rupees) Vehicle Km)
Sub-Urban Passenger
1438.50 1792.59 12.46
Service (EMUs only)
This operating ratio is for total services i.e. freight as well as passenger service.
As can be seen from above, passenger earnings per vehicle Km is far less than
freight earnings per vehicle Km. Thus, operating ratio of IR passenger service
(more so in case of commuter passenger service) shall be much more than
100%.
In the absence of detailed account available, O&M costs are broadly analysed
as under:
11
Source: Indian Railways Year Book 2010-11
Commuter trips
Potential $ Additional
Investment that can be
(Services that can Services
Phase (in Crores of generated per
be additionally proposed to be
Rupees) day (Cumulative
introduced) introduced
in Lacs)
@
0 0 0 56 2
1A 173 24 24 4
#
1 3831 330 172 8
#
2 2251 320 94 15
& &
3 2504 NA NA 25
$
In addition to enhancing the capacity of existing services by replacing with
MEMUs and EMUs. Services in both directions together are indicated.
@
List of services existing as on now. Can be seen at Annexure 4
# Each service proposed is assumed to originate and terminate in the same
section. For example, if a new service starts in SBC-MYS section and ends in
SBC-BYPL section, it is counted as 2 services in this figure.
&
It is recommended to increase length of EMU cars in this phase. However, this
phase can also be converted into introduction of additional services instead
of lengthening of existing EMU rakes as enough potential is available to
introduce additional services as seen in above table.
Savings in journey time because rail is going to capture the traffic which is
presently being served by bus or private transport etc.
Reduction in fuel consumption (trains are more fuel efficient than busses).
Reduction in pollution of atmosphere (Electrical trains emit no smoke into
atmosphere).
Extra comfort to commuters.
Increase in real estate prices near to CRS stations and correspondingly
more revenue to GoK by way of property sale/purchase registration
charges, property taxes etc. as brought out in Para 9.1.
Savings to GoK in overall infrastructure planning as brought out in Para
9.2.
IR Non sub-urban fare is less than Sub-urban fare for the same distance
and same class.
Overall CIDCO fare > Overall MRVC fare > Overall MMTS fare.
2nd Class 2nd Class monthly 1st Class 1st Class Monthly
Distance Remarks
Ticket Ticket Ticket ticket
Upto 10 Km 0 0 0 0
Surcharge levied
11 to 50 Km 1 10 2 20 on 16th Sep ’03.
MRVC
51 to 100 Km 1 15 2 30 Not revised since
then
101 to 150 1 20 2 40
Not based on
distance but Surcharge initially
for a levied in 1990.
CIDCO 1 to 4 17 to 80 2 to 6 42 to 200
particular Revised once in
origin to 04-05.
destination
Figures in Rupees
Surcharge accrued from MRVC projects is somewhere around Rs.90 Cr in 11-12 with ridership of about 60 lacs. This
works out to about 41 paisa per commuter trip
From the above, it can be seen that fares with 100% surcharge are
comparable to BMTC fares.
From the above, we can reasonably assume that commuter rail system in
Bangalore shall continue to grow at a rate of 0.64% per annum under this
financing model which is nowhere nearer to the growth of demand (or growth of
population). Hence this model of financing is not suggested. In fact, if this
model of financing is to be adopted, probably this study by RITES is not
warranted at all.
Feasibility study was got done by GoAP to develop mass rapid transport plan
for Hyderabad. This feasibility study and further follow up by Government of
Andhra Pradesh (GoAP) led to signing of MOU between MOR and GoAP on
25th Sep „2000. Based on the report prepared by GoAP, Railways put up a
feasibility report to CCEA (Cabinet Committee on Economic Affairs) in Jul‟01.
The MOU was basically to develop commuter rail services on existing rail
network in HYB/SC-Lingampalli (28.1 KM) and SC-Falaknuma (14.54 KM)
sections. As per the MOU, Cost has to be shared at 50%-50% with a provision
for levy of at least 25% surcharge to be retained by IR. The costs were
estimated as 69.96 Cr for infrastructure and 84 Cr for 20 MEMU rakes. Work
was sanctioned by MOR in Oct ‟01 and work completed in Feb ‟04 at a cost of
98.75 Cr for up gradation and Rs 60.88 Cr for Rolling Stock. Patronage of
MMTS phase-I is:
@
Description Originating passengers per day
Initially projected during project appraisal 336000
03-04 13104
04-05 25486
05-06 35770
#
11-12 Over 150000
@
Source : http://www.cag.gov.in/html/reports/railways/2007_6_peraud/chap_4.pdf
#
Source: http://www.thehindu.com/news/cities/Hyderabad/article2981025.ece
Govt. of Andhra Pradesh mooted the proposals for Phase-II even when Phase-I
was under execution. However, Railways decided (in 2006) that Phase-II would
not be taken up until phase-I becomes financially viable. Finally Phase-II was
sanctioned by Railways in 2012 with financing by GoAP (66.67%) and MOR
(33.33%). MOR also proposed to set up a SPV for commercial management of
MMTS leaving the O&M to IR for rapid growth of MMTS and to meet public
aspirations12. While the South Central Railway started making all planning for
execution, the SPV is yet to take shape. The scope of the project under MMTS
phase-II is:
Length Estimat
Section Activity
(KM) e (Cr)
Falaknuma – Umdanagar Doubling
20 85
New Line to Shamshabad Airport New Line
Telapur – Patancheru Restoration of abandoned Line 9 32
Secunderabad – Bolaram Electrification & Stations Remodelling 14 30
Sanatnagar – Maulali doubling Doubling 22 170
Moula-Ali – Malkajgiri- Seethapalmandi Doubling and Electrification 10 25
Bolaram – Medchal Doubling and Electrification 28 74
12
Source: 12-13 budget speech of Hon’ble MR
Length Estimat
Section Activity
(KM) e (Cr)
Moula-Ali – Ghatkesar Quadrupling 12 120
Passenger Amenities Platforms, Station Buildings etc. 20
EMU Rakes Rakes 85
Total 115 641
Expected Capacity : 3 Lakh trips per day
Source : http://www.thehindu.com/news/cities/Hyderabad/article2981025.ece,
http://www.exclventures.com/News/Newslink-11324.asp and
http://www.thehansindia.info/News/Article.asp/category=1&subCategory=2&ContentId=42711
In 2000-01 period, the then ruling party of AP was the most key ally of
the then ruling party at the centre. Therefore, the project (Phase-I) got
sanctioned and got executed expeditiously.
As per MOU, state government shall provide land free of cost wherever
required for development of stations and concerned facilities like roads
etc.
In the first year of sanction i.e. 2012-13, Railway allotted about Rs 100 Cr
budget for the phase-II project whereas Government of AP has not
allotted any funds so far. In fact, first year of sanction normally goes for
planning, survey, tendering etc. and not much budget grant will be spent.
Success of this project depends on how Railway and GoAP allot the
funds in subsequent years.
Today, the finance crunch being faced by Railway is probably the worst
ever. Therefore, GOI agreeing for cost sharing of Bangalore CRS
(whether 33% or 25% or so) is anybody‟s guess.
While the system (phase-I) was expected to cater for more than 3 lacs
passengers per day, patronage even today is about 1.6 lacs per day.
This is mostly due to non-development of feeder roads to MMTS
stations. There is no institutional mechanism to plan and monitor the
development of feeder roads. The patronage has been increasing not
because some additional facilities were created to the public (like feeder
roads etc.). It is simply due to its low cost. Even without proper feeder
roads, public is taking all pains to make use of this cheaper service.
GoAP has virtually no say in the services being run. IR decides on their
own the number of services, their direction, timings etc. IR is under no
obligation to run certain number of services etc.
Surcharge if at all levied, accrues to IR and not to GoAP as per the MOU
(phase-I). Levy of surcharge (or otherwise) shall be mostly decided by IR
themselves and GoAP does not have any say.
In Nov „1986, MOU was entered by CIDCO with IR for provision of rail
connectivity to Navi Mumbai.
IR levied surcharge of Re 1/- per ticket on 2nd class & Rs 2/- on first
class ticket and the same was transferred to CIDCO. In 04-05, the
surcharge was raised to Rs 2/- to 6/- per ticket depending on the class
and distance.
CIDCO had the rights to commercialize the air space and other parts of
the station area.
Under this model, The Mankhurd to Belapur new line (27 Km) was
commissioned in 1993.
MRVC came into existence in Jul ‟99 with equity of Rs 25 Cr (GOI: GOM = 51%:
49%). The corporation gets the identified projects executed and also plans
development of Mumbai Suburban Rail System on a continuous basis. The
mandate of the entity is:
Where direct involvement of running trains and signals is involved, works are
executed by IR. Works like station buildings, circulating areas etc. which need
not involve disturbance to train operations are executed by MRVC directly.
Procurement of EMU rakes is also done by MRVC. Feeder roads etc. are
executed by GoM. Phase-I costs about Rs 4200 Cr. The funding mechanism:
Procurement of EMUs.
If GoK approaches GOI with a simple proposal without details like preliminary
survey report, preliminary estimates etc., GOI refers the projects to S W
Railway for survey. This phase itself takes lot of time. To cut short such time, it
is recommended to carry out preliminary survey and draft SPV before
approaching GOI. However, while undertaking preliminary survey, S W Railway
should be taken into confidence and Ministry of Railways also should be kept
formally informed.
Pure Business entity Model: This model is like KRCL (Konkan Railway
Corporation Ltd). The SPV shall be totally responsible for generating
necessary revenue for its operations and also for debt servicing apart
from executing the projects. Even with long distance express trains
earnings, KRCL ran into losses in the initial years of its inception due to
debt servicing burden. Then equity was enhanced to bring down the
debt burden on KRCL to manageable levels.
and transfers half of the surcharge to GoM. World Bank loan is directly
repaid by GoI and GoM.
With the surcharge income or with the very less commuter fares, the SPV
cannot sustain to function in KRCL model. Therefore, it is recommended that
BCRC be formulated in the same lines of MRVC.
As in case of MRVC model, equity is required only for day to day functioning of
the BCRC and not for projects. Therefore, equity can be about 100 Crores
(MRVC‟s equity is 50 Crores). Equity share holders will be basically
Government of India and Government of Karnataka. It can be 50% - 50%
equity share holding or 51% (GOI): 49% (GOK) like in the case of MRVC. In
case GoI does not come forward, it is worth even to hike GoK‟s equity upto
100% considering the importance of CRS for Bangalore.
Normally no infrastructure project can take off purely with equity. Some debt
component may be a must for the success of any project. However, BCRC per
se does not have any debt component as it only offers some services as
discussed above. Debt component is jointly decided by shareholders (GoI and
GoM) separately for each project. Accordingly, justification is made and lending
agencies are approached.
Private Equity can be attracted only in case of viable projects. Commuter rail
business per se does not attract private equity due to its less revenue.
Therefore, some options that need to be explored to attract private equity by the
SPV:
Provide alternate income sources like real estate exploitation etc. (apart
from commuter fares) to investors.
Accordingly, BCRC can also formulate certain projects involving private equity.
Therefore, private investor can only finance the project leaving design,
construction and operation to IR.
Assumed return of 12% may not attract any private investors because
their cost of capital itself will be around 10%.
Commissioner, DULT
Apart from Chairman, MD and above cited independent directors, BCRC shall
also have full time functional as under:
Director (Finance).
The projects shall be proposed keeping in view the total transport plan of
the city. Projects proposed by BCRC shall be formally approved by
shareholders (IR and GoK). This will also help IR to plan the necessary
arrangements for O & M of such projects (for manpower recruitment,
training etc.).
BCRC shall divide each project into logical and meaningful packages.
Packages which directly affect running trains, track and signalling
systems shall be executed by South Western Railway. Feeder road
projects are normally executed by state government agencies.
Packages which can be executed free of running trains/track etc. can be
executed by BCRC itself. To this extent, BCRC can have suitable
engineering team to execute the projects.
All assets created shall be handed over to Indian Railways for O & M. O
& M costs and O & M profits / losses shall be borne by IR.
Working out O&M costs by IR is easier said than done. IR‟s accounting
system does not facilitate bifurcation of O&M costs into various heads
like freight, commuter rail, long distance trains etc. Moreover, IR takes
entire South Western Railway as one unit (not even Bangalore Division)
while working out O&M costs. Then working out O&M costs for
commuter rail that too only for Bangalore area alone is very complex with
IR‟s accounting system. Therefore, any model to share O&M costs (or
profits/loss) may not be practicable. Instead, simple surcharge model
which is easy to implement is suggested.
Available Railway land shall be used for commuter rail projects and the
same shall continue to be Indian Railways‟ property. Also, land
belonging to GoK if required for the projects shall also be handed over to
Railways duly charging its cost to the projects or free of cost as decided
from project to project.
Vacant Railway land and vacant GoK‟s lands and even vacant air space
along the commuter lines shall be processed by BCRC for commercial
exploitation.
BCRC can take such properties on nominal lease rentals from GoI and
GoK and exploit them. Alternatively, it can charge certain fee from the
shareholders for co-ordinating the process and the revenues accrue to
GoI or GoK as the case may be.
GoK may also consider enhancing the property taxes, property values,
and other indirect charges from the properties around the CRS stations
to tap the increased commercial value of those areas due to
implementation of CRS.
Any commuter transport plan (rather any transport plan) shall be incomplete, if it
does not integrate rail system into it apart from other modes.
Therefore, to tap the full potential of Railway network and to effectively integrate
rail network into commuter system of Bangalore, Government of Karnataka has
to take the lead (rather, an extra lead).
b) Deciding Locations and Making plans for new halt stations. Aspects
like land availability, road connectivity, feasibility in rail system to provide
new halt, patronage potential etc. need to be analysed thoroughly for
locating new halt stations. This needs physical survey of the entire 440.8
Km of CRS network apart from interactions with S W Railway and all
other stake holders.
e) Developing conceptual plans in the above lines for SBC and all other
stations of the CRS network.
i) RITES has got expertise and all wherewithal to undertake the above
cited physical surveys.
An SPV coming into existence and start delivering services to the public is a
long drawn process. Therefore, it is recommended that:
Make out a proposal to Ministry of Railways duly bringing out the total
scope of the projects (covering all the 3 phases suggested) and its
readiness to finance 100%.
The proposal can also contain a request to form BCRC in the lines of
MRVC to implement phases 2 and 3 and take the mission further.
Against this investment, GoK should not expect any further returns like
share of revenues, say in fare policy, say in day to day O & M, ownership
Once such a proposal goes to MoR, it is likely to sanction the projects (100%
financed by GoK) within 3 to 6 months‟ time. BCRC also may come into
existence in about 2 years‟ time.
Annexure: 4 Trains presently serving Bangalore commuters and enhancing their capacities
Existing Rakes
Service Service Within CRS Strategy Capacity Enhanced to
Capacity Requirement
MEMU Rake Km
EMU Rake Km
Existing Type
From Station
Leave as it is
To Station
Departure
Distance
Arrival
Train
From
Total
No
To
1 56229 Pass MYS SBC 137 MYA 09:21 SBC 12:10 92.88 Y 9 3710 8793 0 0 0 8793 137 0
2 56230 Pass SBC MYS 137 SBC 16:25 MYA 18:16 92.88 Y 9 3710 8793 0 0 0 8793 137 0
3 56231 Pass MYS SBC 137 MYA 06:45 SBC 09:10 92.88 Y 16 6595 8793 0 0 0 8793 137 0
4 56232 Pass SBC MYS 137 SBC 09:30 MYA 11:23 92.88 Y 16 6595 8793 0 0 0 8793 137 0
5 56233 Pass SBC MYS 137 SBC 05:15 MYA 07:24 92.88 Y 9 3710 8793 0 0 0 8793 137 0
6 56234 Pass MYS SBC 137 MYA 19:41 SBC 22:30 92.88 Y 9 3710 8793 0 0 0 8793 137 0
7 56237 Pass MYS SBC 137 MYA 15:25 SBC 18:00 92.88 Y 8 3298 8793 0 0 0 8793 137 0
8 56238 Pass SBC MYS 137 SBC 19:00 MYA 20:47 92.88 Y 8 3298 8793 0 0 0 8793 137 0
9 56507 Pass MKM SBC 86 BWT 07:05 SBC 09:15 70.21 Y 15 4674 6647 0 0 0 6647 86 0
10 56508 Pass SBC MKM 86 SBC 18:05 BWT 19:58 70.21 Y 15 4674 6647 0 0 0 6647 86 0
11 56509 Pass MKM SBC 86 BWT 14:40 SBC 17:00 70.21 Y 10 3116 6647 0 0 0 6647 86 0
12 56510 Pass SBC MKM 86 SBC 07:00 BWT 08:58 70.21 Y 10 3116 6647 0 0 0 6647 86 0
13 66529 MEMU KPN SBC 104 BWT 07:30 SBC 09:30 70.21 Y 8 3324 6647 0 0 0 6647 104 0
14 66532 MEMU SBC MKM 86 SBC 14:55 BWT 16:39 70.21 Y 8 3324 6647 0 0 0 6647 86 0
15 66533 MEMU MKM KJM 72 BWT 18:00 KJM 19:10 56 Y 8 2651 5302 0 0 0 5302 72 0
Existing Rakes
Service Service Within CRS Strategy Capacity Enhanced to
Capacity Requirement
MEMU Rake Km
EMU Rake Km
Existing Type
From Station
Leave as it is
To Station
Departure
Distance
Arrival
Train
From
Total
No
To
16 66534 MEMU KJM KPN 90 KJM 19:30 BWT 20:40 56 Y 8 2651 5302 0 0 0 5302 90 0
17 76511 DEMU SBC MKM 86 SBC 12:20 BWT 14:30 70.21 Y 9 3739 6647 0 0 0 6647 86 0
18 76512 DEMU MKM SBC 86 BWT 08:37 SBC 10:30 70.21 Y 9 3739 6647 0 0 0 6647 86 0
19 56221 Pass SBC TK 70 SBC 09:20 TK 11:05 69.35 Y 8 2462 0 4432 2955 0 7387 0 70
20 56222 Pass TK SBC 70 TK 11:20 SBC 13:10 69.35 Y 8 2462 0 4432 2955 0 7387 0 70
21 56225 Pass SBC TK 70 SBC 13:40 TK 15:25 69.35 Y 8 2462 0 4432 2955 0 7387 0 70
22 56226 Pass TK SBC 70 TK 15:50 SBC 17:40 69.35 Y 8 2462 0 4432 2955 0 7387 0 70
23 56525 Pass SBC CBP 64 SBC 18:00 CBP 19:50 63.85 Y 7 1984 0 4080 2720 0 6800 0 64
24 56526 Pass CBP SBC 64 CBP 07:55 SBC 09:45 63.85 Y 7 1984 0 4080 2720 0 6800 0 64
25 66530 MEMU SBC BWT 70.21 SBC 09:45 BWT 12:05 70.21 Y 8 3324 0 4487 2991 0 7478 0 70.21
26 66531 MEMU BWT SBC 70.21 SBC 14:55 BWT 16:25 70.21 Y 8 3324 0 4487 2991 0 7478 0 70.21
27 76507 DEMU BNC BWT 66 BNC 11:00 BWT 12:50 66 Y 8 3124 0 4218 2812 0 7030 0 66
28 76508 DEMU BWT BNC 66 BWT 15:30 BNC 17:20 66 Y 8 3124 0 4218 2812 0 7030 0 66
29 76551 DEMU SBC CBP 73 SBC 08:40 CBP 10:50 77.28 Y 8 3658 0 4939 3293 0 8232 0 73
30 76552 DEMU CBP SBC 73 CBP 15:55 SBC 18:00 77.28 Y 8 3658 0 4939 3293 0 8232 0 73
31 56213 Pass CMNR TPTY 532 MYA 17:55 BWT 22:00 163.09 Y 15 10857 0 0 0 10857 10857 0 0
Existing Rakes
Service Service Within CRS Strategy Capacity Enhanced to
Capacity Requirement
MEMU Rake Km
EMU Rake Km
Existing Type
From Station
Leave as it is
To Station
Departure
Distance
Arrival
Train
From
Total
No
To
32 56214 Pass TPTY CMNR 532 BWT 05:15 MYA 09:15 163.09 Y 15 10857 0 0 0 10857 10857 0 0
33 56223 Pass SBC ASK 166 SBC 18:20 TK 19:50 69.35 Y 8 2462 0 0 0 2462 2462 0 0
34 56224 Pass ASK SBC 166 TK 07:20 SBC 09:10 69.35 Y 8 2462 0 0 0 2462 2462 0 0
35 56227 Pass SBC SMET 274 SBC 16:45 TK 18:20 69.35 Y 9 2770 0 0 0 2770 2770 0 0
36 56228 Pass SMET SBC 274 TK 09:15 SBC 11:20 69.35 Y 9 2770 0 0 0 2770 2770 0 0
37 56241 Pass SA YPR 225 HSRA 08:30 YPR 10:45 67 Y 9 2676 0 0 0 2676 2676 0 0
38 56242 Pass YPR SA 225 YPR 16:05 HSRA 17:31 67 Y 9 2676 0 0 0 2676 2676 0 0
39 56261 Pass AJJ SBC 289 BWT 16:40 SBC 18:45 70.21 Y 10 3116 0 0 0 3116 3116 0 0
40 56262 Pass SBC AJJ 289 SBC 09:20 BWT 11:00 70.21 Y 10 3116 0 0 0 3116 3116 0 0
41 56503 Pass YPR BZA 741 YPR 08:00 DBU 09:00 33.17 Y 11 1619 0 0 0 1619 1619 0 0
42 56504 Pass BZA YPR 741 DBU 14:55 YPR 17:10 33.17 Y 11 1619 0 0 0 1619 1619 0 0
43 56513 Pass NCR SBC 557 HSRA 16:50 SBC 19:00 60.59 Y 14 3764 0 0 0 3764 3764 0 0
44 56514 Pass SBC NCR 557 SBC 07:15 HSRA 08:32 60.59 Y 14 3764 0 0 0 3764 3764 0 0
45 56515 Pass SBC UBL 470 SBC 07:50 TK 09:28 69.35 Y 16 4924 0 0 0 4924 4924 0 0
46 56516 Pass UBL SBC 470 TK 17:22 SBC 20:20 69.35 Y 16 4924 0 0 0 4924 4924 0 0
47 56523 Pass SBC HUP 101 SBC 18:40 DBU 19:33 38.52 Y 13 2222 0 0 0 2222 2222 0 0
Existing Rakes
Service Service Within CRS Strategy Capacity Enhanced to
Capacity Requirement
MEMU Rake Km
EMU Rake Km
Existing Type
From Station
Leave as it is
To Station
Departure
Distance
Arrival
Train
From
Total
No
To
48 56524 Pass HUP SBC 101 DBU 07:53 SBC 09:25 38.52 Y 13 2222 0 0 0 2222 2222 0 0
49 56913 Pass SBC UBL 470 SBC 06:30 TK 07:58 69.35 Y 12 3693 0 0 0 3693 3693 0 0
50 56914 Pass UBL SBC 470 TK 21:05 SBC 22:45 69.35 Y 12 3693 0 0 0 3693 3693 0 0
51 56917 Pass SBC SMET 274 SBC 06:30 TK 08:00 69.35 Y 21 6463 0 0 0 6463 6463 0 0
52 56918 Pass SMET SBC 274 TK 19:22 SBC 21:30 69.35 Y 21 6463 0 0 0 6463 6463 0 0
53 76505 DEMU BNC KQZ 83 BNC 17:55 BWT 19:30 66 Y 8 3124 0 0 0 3124 3124 0 0
54 76506 DEMU KQZ BNC 83 BWT 08:00 BNC 09:40 66 Y 8 3124 0 0 0 3124 3124 0 0
55 76553 DEMU SBC DPJ 152 SBC 18:30 HSRA 19:36 60.59 Y 8 2868 0 0 0 2868 2868 0 0
56 76554 DEMU DPJ SBC 152 HSRA 06:33 SBC 08:10 60.59 Y 8 2868 0 0 0 2868 2868 0 0
Total → 18 12 26 204778 134124 53176 35452 101116 323868 1964 826.42
Rakes required to replace existing services (@ 1 per 500 Rake Km) → 3.928 1.653
After adding 20% maintenance spare→ 4.714 1.984
Rounding off → 5 2
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
Amount
No (in Cr)
(Cr)
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
Qty
16 car MEMUs (for
1 replacing exg. 21 Rake 0.75 16.00 1.25 26.00 3.00 63 5 105
services)
2 Doubling 12 Km 16.12 194 48.59 583 46.05 553 20.72 249 45.20 542 177 2121
3 Electrification 1.25 Km 32.24 40 97.18 121 10.70 13 128.00 160 92.10 115 20.72 26 90.40 113 471 588
4 Auto Signalling etc. 0.75 Km 16.12 12 48.59 36 5.35 4 64.00 48 12.45 9 46.05 35 19.23 14 20.72 16 45.20 34 10.76 8 59.45 45 92.88 70 441 331
Extension/ Rising
5 3 Stn 2 6 4.00 12 1.00 3 10.00 30 2.00 6 6.00 18 1.00 3 1.00 3 3.00 9 3.00 9 8.00 24 12.00 36 53 159
of PFs
Facilities at
6 15 Stn 1 15 1.00 15 1.00 15 1.00 15 1.00 15 1.00 15 1.00 15 1.00 15 1.00 15 9 135
Terminals
Addl. lines at
7 10 Line 1 10 4.00 40 5.00 50 3.00 30 1.00 10 3.00 30 4.00 40 2.00 20 6.00 60 7.00 70 36 360
Stations
Facilities at Exg.
8 10 Stn 2 20 4.00 40 1.00 10 10.00 100 2.00 20 6.00 60 1.00 10 1.00 10 3.00 30 3.00 30 8.00 80 12.00 120 53 530
Stations
9 car EMUs (for
9 Replacing Exg. 36 Rake 0.08 3 0.92 33 0.21 8 0.79 28 2 72
services)
9 car EMUs (for
10 36 Rake 2.5 90 7.51 270 0.23 8 2.77 100 0.64 23 2.36 85 1.44 52 1.56 56 1.00 36 0.15 6 0.85 30 3.00 108 24 864
new services)
Developing New
11 15 Stn 9 135 9.00 135 1.00 15 11.00 165 3.00 45 3.00 45 7.00 105 3.00 45 4.00 60 1.00 15 7.00 105 14.00 210 72 1080
Halt Stations
EMUs Conversion
12 24 Rake 2.5 60 7.51 180 0.31 7 3.69 89 0.85 20 3.15 76 1.44 35 1.56 37 1.00 24 0.15 4 0.85 20 3.00 72 26 624
(9 to 15 car)
Total cost of Sections 582 1432 63 790 146 1060 229 487 903 108 405 764 6969
Development of EMU cum MEMU maintenance shed at BAND --> 200
Note Phase Cost Development of additional pit lines at YPR --> 20
1A 173 SBC yard remodelling duly including Binny Mill Land --> 370
Cost of Binny Mill Land is 1 3831 Development of pit lines, PFs etc. (4 pit lines proposed in Phase 1A Balance 6 pit lines, stabling lines PFs etc.) at BYPLN --> 200
2 2251 Developing Hejjala 4th Coaching Terminal--> 200
not included in the 3 2504 Bypass Line connecting DBU and CBP lines --> 300
estimates Total 8759 Quadrupling between SBC and WFD --> 500
Total Cost of Terminals → 1790
Total Cost (Sections Cost + Terminals Cost) → 8759
Annexure: 7 Hourly Distribution of total scheduled trains running in CRS network at present
S.No Section 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 TOTAL
SBC - MYA 2 1 2 1 1 1 2 0 1 0 1 1 0 1 1 1 0 16
1
MYA - SBC 1 1 1 0 1 0 2 0 1 2 1 1 1 2 2 1 1 18
SBC - YPR 0 2 1 0 1 0 1 0 2 0 0 2 0 1 0 0 4 14
2
YPR - SBC 0 0 1 1 0 0 2 1 1 0 1 0 1 0 1 1 1 11
YPR - TK 0 3 1 1 1 1 0 1 2 0 1 1 1 1 1 0 3 18
3
TK - YPR 2 1 1 1 2 1 1 1 0 1 1 0 1 0 1 2 1 17
YPR - YNK 0 0 1 1 0 0 0 0 1 1 0 1 3 1 1 2 0 12
4
YNK - YPR 0 2 1 1 4 2 0 0 1 0 0 1 0 1 0 0 0 13
BYPL - YNK 1 0 0 0 1 0 0 0 1 1 1 0 1 1 1 1 0 9
5
YNK - BYPL 2 0 1 0 0 0 2 1 0 0 0 0 1 0 0 1 1 9
BYPL - YPR 1 1 1 0 1 1 1 0 0 0 2 0 0 0 0 3 0 11
6
YPR - BYPL 2 0 1 3 0 1 1 0 1 0 1 0 0 0 1 0 0 11
YNK - DBU 0 1 1 2 0 0 0 1 1 2 1 3 3 1 2 3 2 23
7
DBU - YNK 3 2 1 3 3 2 1 2 0 0 1 2 0 1 0 1 1 23
YNK - CBP 0 0 0 0 1 0 0 0 0 0 0 0 0 1 0 0 0 2
8
CBP - YNK 0 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 2
BYPL/BYPLA - HSRA 0 1 1 0 0 0 0 0 0 0 0 1 0 1 1 1 2 8
9
HSRA - BYPL/BYPLA 1 2 1 1 0 0 0 0 1 0 0 0 1 1 0 0 1 9
SBC/BNC - BYPL 1 3 2 2 3 2 0 1 2 3 1 2 5 4 3 2 2 38
10
BYPL - SBC/BNC 5 3 2 5 2 1 3 3 1 1 0 2 1 2 3 1 3 38
BYPL - BWT 0 4 1 3 4 4 3 1 1 2 1 2 6 2 3 2 0 39
11
BWT - BYPL 2 5 2 3 2 4 1 1 0 3 2 1 0 3 4 3 2 38
SVDL - Kunigal 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1
12
Kunigal - SVDL 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 1
S.No Section 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 TOTAL
SBC - MYA 1 0 1 0 1 0 0 0 0 0 0 1 0 0 1 0 0 5
1
MYA - SBC 0 1 0 0 1 0 0 0 0 0 1 0 0 1 1 0 0 5
SBC - YPR 0 1 1 0 1 0 1 0 1 0 0 1 0 1 0 0 0 7
2
YPR - SBC 0 0 0 1 0 0 1 1 0 0 1 0 1 0 1 1 0 7
YPR - TK 0 1 0 1 1 0 0 0 1 0 0 0 1 1 0 0 0 6
3
TK - YPR 0 0 1 0 1 0 1 0 0 0 1 0 1 0 1 0 0 6
YPR - YNK 0 0 0 1 0 0 0 0 0 0 0 0 0 1 1 0 0 3
4
YNK - YPR 0 0 0 1 1 0 0 0 0 0 0 1 0 0 0 0 0 3
BYPL - YNK 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 1
5
YNK - BYPL 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 1
BYPL - YPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6
YPR - BYPL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
YNK - DBU 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 0 0 2
7
DBU - YNK 0 0 0 1 0 0 0 0 0 0 1 0 0 0 0 0 0 2
YNK - CBP 0 0 0 0 1 0 0 0 0 0 0 0 0 1 0 0 0 2
8
CBP - YNK 0 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 2
BYPL/BYPLA - HSRA 0 0 1 0 0 0 0 0 0 0 0 1 0 1 0 0 0 3
9
HSRA - BYPL/BYPLA 0 1 0 1 0 0 0 0 0 0 0 0 1 0 0 0 0 3
SBC/BNC - BYPL 0 0 2 1 2 1 0 1 0 1 0 0 1 2 0 2 0 13
10
BYPL - SBC/BNC 0 1 0 2 2 0 0 0 1 0 0 2 0 2 0 0 0 10
BYPL - BWT 0 0 1 0 1 1 1 1 0 0 1 0 0 2 1 1 0 10
11
BWT - BYPL 1 0 2 2 0 0 0 1 0 1 1 1 0 1 0 0 0 10
SVDL - Kunigal 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1
12
Kunigal - SVDL 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 1
Annexure: 9 Hourly distribution of assessed potential for introducing additional services after proposed investments
S.No Section 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 TOTAL
SBC - MYA 0 1 2 2 2 2 1 3 1 1 1 2 3 3 3 2 1 30
1
MYA - SBC 1 3 3 3 2 3 1 2 1 1 2 1 1 2 2 1 1 30
SBC - YPR 0 1 1 1 1 1 1 1 0 0 2 2 2 2 2 2 1 20
2
YPR - SBC 2 2 2 2 2 2 0 0 0 1 1 1 1 1 1 1 1 20
YPR - TK 1 1 1 1 1 1 2 1 0 2 3 3 3 3 3 3 1 30
3
TK - YPR 1 3 3 3 3 3 1 2 2 2 1 1 1 1 1 1 1 30
YPR - YNK 0 1 1 1 1 1 1 1 0 1 1 1 2 2 2 2 2 20
4
YNK - YPR 1 2 2 2 1 1 1 1 0 1 1 1 1 1 1 2 1 20
BYPL - YNK 1 1 3 2 1 1 1 1 1 1 3 2 3 3 2 2 2 30
5
YNK - BYPL 2 2 2 2 2 3 1 1 2 2 3 2 1 2 1 1 1 30
BYPL - YPR 0 1 1 1 1 1 1 1 1 1 1 2 2 2 2 1 1 20
6
YPR - BYPL 1 2 2 2 2 1 1 0 0 1 1 1 1 2 1 1 1 20
YNK - DBU 1 1 1 1 1 2 2 1 1 2 3 2 2 3 3 2 2 30
7
DBU - YNK 2 3 3 2 2 2 2 1 2 2 1 2 1 2 1 1 1 30
YNK - CBP 1 1 1 1 1 1 1 1 2 2 3 3 3 2 3 2 2 30
8
CBP - YNK 2 2 2 2 2 2 2 2 1 1 1 1 2 2 2 2 2 30
BYPL/BYPLA - HSRA 2 2 2 3 3 3 3 3 2 2 3 3 3 3 3 3 2 45
9
HSRA - BYPL/BYPLA 3 3 3 3 4 3 3 1 1 1 3 4 2 3 2 3 3 45
SBC/BNC - BYPL 1 1 1 1 1 1 1 1 1 0 2 2 0 1 2 2 2 20
10
BYPL - SBC/BNC 0 1 2 0 0 2 1 1 1 1 2 1 2 2 2 2 0 20
BYPL - BWT 1 1 1 1 0 1 2 1 0 1 2 2 0 2 2 2 1 20
11
BWT - BYPL 1 0 2 1 2 1 2 1 1 1 1 1 2 1 1 1 1 20
SVDL - Kunigal 2 2 2 2 2 2 1 1 1 1 2 2 2 2 2 2 2 30
12
Kunigal - SVDL 2 2 2 2 2 2 2 1 1 0 2 2 2 2 2 2 2 30