Method Statement Plate Load Test PDF
Method Statement Plate Load Test PDF
Chulalongkorn University
Saraburi Campus
NOVEMBER 2009
BY
Infratech ASTM CO., LTD.
TABLE OF CONTENTS
Table of Contents.................................................................................................................................. 1
Appendix
1
Infratech ASTM CO., LTD.
List of Appendix
2
Infratech ASTM CO., LTD.
x Location : Saraburi,Thailand
x Number of Tests : 11
2. A dia.12”x 25 mm thick steel plate was used to distribute the load from the jack to the plate
and to the ground.
3. Three dial gauges with accuracy of 0.01 mm were used to measure the deflections during
loading and unloading.
Loading: 0- 25% - 50% - 75% - 100% - 125% - 150% - 175% - 200% - 225% - 250% of the
design load.
3
Infratech ASTM CO., LTD.
Each loading and unloading stage was maintained for 15 minutes with readings made at 1, 2, 4,
8 and 15 minutes after the application or removal of load. During the test, records including plots of load
vs. time and load vs. settlement were maintained progressively.
Results of test will be presented in graph form show relationship among load-time-settlement
and prediction of subgrade modulus.
4
Appendix-A
Footing
System : ………..……….... Area : ……… Pit 1 Contractor :
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
SUBMITTED BY RECEIVED BY
COMPANY ASTM Testing Co.,ltd. Kenber
SIGNATURE
NAME Rangsan Gamsantia Poosit S.
DATE
Footing
System : ………..……….... Area : ……… Pit 1 Contractor :
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
SUBMITTED BY RECEIVED BY
COMPANY ASTM Testing Co.,ltd. Kenber
SIGNATURE
NAME Rangsan Gamsantia Poosit S.
DATE
Footing
System : ………..……. Area : ………………… Contractor :
TIME, (hrs)
PRESSURE, (t/m2)
0 10 20 30 40 50 60 SETTLEMENT, (mm) 0.0 1.0 2.0 3.0 4.0
0.0 0.0
-1.0
Actual loading -2.0
-1.0 Unloading -3.0
Linear loading -4.0
-5.0
-2.0
SETTLEMENT, (mm)
-6.0
-7.0
-3.0
30
(t/m )
2
20
-6.0 10
0
0.0 1.0 2.0 3.0 4.0
-7.0
TIME, (hrs)
Test by : Check by :
SUBMITTED BY RECEIVED BY
SIGNATURE
DATE
Footing
System : ………..……….... Area : ………………… Contractor :
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
SUBMITTED BY RECEIVED BY
COMPANY Infratech ASTM Co.,ltd.
SIGNATURE
NAME Rangsan Gamsantia
DATE
Footing
System : ………..……….... Area : ………………… Contractor :
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
SUBMITTED BY RECEIVED BY
COMPANY Infratech ASTM Co.,ltd.
SIGNATURE
NAME Rangsan Gamsantia
DATE
Footing
System : ………..……….... Area : ………………… Contractor :
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
SUBMITTED BY RECEIVED BY
COMPANY Infratech ASTM Co.,ltd.
SIGNATURE
NAME Rangsan Gamsantia
DATE
Jack Calibration
Project : Chulalongkorn Saraburi Campus
Contractor EMC PCL
Plate Size 0.3048 m.(Dia.)
Plate area 0.0730 Sq.m.
20 1459 92 UNLODING
25 1824 113 A= 15.6833
30 2189 133 B= -176.3889
35 2554 154
40 2919 175
45 3283 195
50 3648 216
40 2919 197
30 2189 151
20 1459 104
10 730 58
0 0 0
Appendix-E