Professional Documents
Culture Documents
For
ESE-2021
Basics of Project Management
By- Rahul Verma
(IES officer)
Cover complete syllabus and all topics of IES-2021, and GATE-2021.
Cover all concepts and questions from the top 3 coaching institute class notes.
Extra topics will cover in each subject if anything will be required in the future
according to IES -2021and GATE-2021syllabus.
Doubts and quarry solution through dedicated WHATSAPP group.
Carrier guidance and motivational support.
Concise, concept oriented and topic wise presentation with detailed video lectures
on Target IES YouTube channel.
S. No. Topic
1. Basic concept of project and its life cycle
2. Project formulation and appraisal
3. Project scheduling
4. Project network
5. Project control tools
6. Tendering, Contract and Depreciation
7. Organizations
1. Basic concept of project and its life cycle
Project- A project can be define as a non routine non rape title work with discrete time having
financial & technical performance goals.
987- Guide to ‘PMBOK’
‘Project management Body of knowledge’
Currently running 6th Edition.
Characteristics of project-
A Project is a planned execution of correlation actuator in a given time & within given cost. A
project is executed for the achievement of certain basic objective of scopes, time, cost & quality.
Progressive elaboration-
Project Project Project Project Project
Concept Research Concept Concept Feasibility
retirement Elaboration Study
Project Project
Plan Scope
Project Strategic time:-
1. Customer request
2. Legal requirement
3. Market demand
4. Technology advancement
5. Company’s own requirement.
4. Based on ownership.
▪ Public section project= Owned by GOZ &PSUS.
▪ Private section project = Owned by private organization
▪ Joint section project = Public private partnership
Project operation
Change On going
Project Operatio
n
Project
Unique Temporary
Project Operation
1. Setting up a factory 1. Producing goods
2. Developing a new verities of nice seeds 2. Harvesting rice crops
3. Installing a new software on a computer 3. Using the software
system 4. Using the robot
4. Design & development of robot 5. Living & Maintenance of complex
5. Constructing a residential complex 6. Supplying water to fields
6. Erecting of an irrigation dam
Page 2
Feature of project-
1. Project sponsor- He develops the business case to adders the corporate vision &
corporate requirements.
▪ It funds the project
▪ It is also called the client.
3. Project life cycle- A project is a series of sequential phases called project life cycle
phase. It has 5 phases.
Initiation Planning Execution Monitoring and Control 4th
1 st 2nd 3rd
Closing 5th
4. Project character – It translates the business case of the projects sponsor into project
objectives.
▪ It is signed b/w the project sponsor and project manager.
▪ It is also contract.
▪ It declares the existence of the project.
▪ It is statement of wok.
5. Project team –
▪ Project is administered by project team.
▪ Project team is heated by project manager.
▪ Project team is a part of project management office.
6. Project Procurement-
▪ It is done through contract
▪ A project procures material and components from outside.
▪ Suppliers and out sources work to other companies. This is done through
procurement process and planning.
7. Project Scope-
▪ It means the outcomes of the project.
▪ Project scope explains the boundary of project.
Project work- A project has a unique scope of work that defines what is not included in the
project. A Project Breakdown structure (PBS) can be used to sub divided the project in to
number of deli nobles that relate to the operational configuration.
Page 3
The work Breakdown structure (WBS) can be used to sub divide the work to make the
deliverable in to work packages.
Project Budget- If the Gadget is exceed than it is called cost overrun, cost over run most be
avoided, budget of the project is assign to different work packages, This result in button control
& better management, Project budget is monitored based on cost estimation for different
activities of project.
Father of project management – F.W Taylor
Harry Grott
Henri fagot
Project Stake holders:- Any individual or organization effect directly or indirectly by the
activities and outcomes of project are called stake holders.
Project Stake holders
1. Customers 2. Banks & financial institution
3. Project manager 4. Vendors & suppliers
5. Project spondee 6. Program managers
7. Functional manager 8. Partners & managers
Project Schedule- Time over leads to cost overrun project schedule is done by Bar chart or
Gants Chart & CPM.
Project Quality- The out puts of the project must be conforming to the quality stand and decided
in the plan.
- Every project has a quality management plan.
Page 4
Quality control Quality Assurance
1. Quality control is product oriented 1. Quality assurance is process oriented
2. Q.C can be insured by removing 2. Q. A can not be assure nearly by
defects in product. removing product defect
3. Q.C is checking the defects & 3. Q.A is doing the right thing at right
minimizing them time, throughout the life cycle of
4. Q.C is corrective in nature project.
4. Q.A is preventive in nature.
Project risk- Risk is defined as variability from expected out comes, every project has risk
management tax & risk assessment matrix.
Extreme risk – Red – Entire team
High risk – Orange – Strict time lime
Moderate risk – Yellow – Intelligent planning
Low risk – Green – Ignored
PROJECT MANAGEMENT
Management- It is an act of getting people together to achoplirh a certain goal with in the
available resources & time in effective manner.
Project management- Project management is an application of knowledge, skills, tools
and techniques to meet the project requirements. The objective is to use the optimum
resources to accomplish a goal in minimum time.
Project management Process groups – Initiating
- Planning
- Execution
- Monitoring & controlling
- Closing process
Project
Obtaining
Management Plan Helps in handing
Resources
risks
Communicates
Procuring Benefits to
Materials Helps in overcoming
State holders obstracles
Page 6
Project life cycle- 10 Stages
Strategy plan
Project Phase
Operation Phase
▪ PLC shows how a project subdivided into a number of phases parented sequentially along
a project time line
▪ All phases from project start to end are known are project life cyle phases.
▪ Phases differ from project to project.
Quality
Cost Time
Page 7
Constraint of project management
Scope
Risk
6 – Contrasted Time
Resources
Quality Cost
Project life cycle (Classical Product life cycle)- PLC has maturely 4 phases.
1. (P-1) Feasibility or Appraisal conception
▪ In this problem is identified and potential solution are suggested.
▪ Feasibility study helps in starting from no. of possible business to get one option
which satisfy client requirement.
▪ How problem identified and potential solutions are suggested i.e idea is conceived.
▪ If idea is found feasible from all consideration it is given “Grow Ahead” signal.
▪ In feasibility stage objective clearly defined them appraisal conducted in term of
Risk, Benefits, and financial commitment.
Page 8
▪ Testing & teething problem solved. If trial Success full then commissioning
project is handed over.
▪ This stage might include training of operating personnel.
▪ In this phase intensity of activities reduces to minimal at end.
Life cycle graph between intensity & activities and time:
Implementatio
n
Planning
Commissioning
Appraised
Rule of effort
Page 9
▪ The level of effort is a use full indication for the project manager to quantity the amount
of work to be for form and the amount of work completed within each phase
▪ These parameters can be parented or a line graph of rate of expenditure or comparative
expenditure
▪ ‘S’ curve profile similar to that used in the earned value calculation.
▪ This graph help manage to quantity amount of work to be performed and the amount of
work completed in each phase.
▪ Similar project have similar led of effort profile.
Cost
Level of
Influences.
Potential to
add value
strategy
Level of Influences
Page
10
Project life cycle costing-
Payback period
+ Profit
Disposal
Resultant cash flow cost
Operation phase
Halo effect- Halo effect is the assumption that “the person is good at technology/ skills then he will be a
good manager it describer an error in thinking in which you make an inference about person.
Page
11
Execution
Planning
Initiation Control
Closing
Page
12
2. Project Formulation & Appraisal
Project formulation- It given a complete picture about a project being undertaken project being
undertaken. The information collected through this process can be used for preliminary scrutiny
of projects; The formulation structure may vary from project to project, Following as pacts are
considered in project formulation
1. Conceptualization of project idea
2. Conceptualization of validity of project idea
3. Making assessment of pre investment study.
4. Project demand analysis
5. Technical assessment.
6. Financial appraisal
7. Economic Analysis
8. Environmental impact analysis (EIA)
If a rough estimates all the above criteria are accessed the then for their detailed studies are
carried out for project development, But if initial rough study gives by report then project
idea is suspended.
2. Pre feasibility stage- After the identification stage the project ideas are filtered through pre
feasibility study. In this stage more elaborate study is required than the previous stage.
After this stage one should be able to decide
1- Whether the project is accepted or rejected
2- whether project requires money detailed feasibility study
3- Some aspects of the projects need special investigation
Pre feasible study include-
1- Plant layout study
2- Project background study
3- Plant size
4- Location site
5- Technology
Page
13
6- Market demand
7- Impact resources
8- Project development methodology
9- Man power
10- Finical analysis
11- Environmental analysis
3. Feasibility study-
Generation of idea
Put to feasibility
Financial analysis
PROJECT APPRAISAL
Technical appraisal / Analysis.
1- Statement of objectives
2- Project background study
Page
14
3- Study of project location and site
Forecasting- Forecasting is the ability to use any previous date or recode to estimate happenings
of the future.
Method of demand fore casting-
1. Delphi- A panel of experts are asked sequential question & no available previous data of
demand & forecast.
2. Luminal group technique/ Jury of executive opinion-
▪ Questions are pre pared by facility or based on opinion pole market research,
economical analysis.
▪ Experts sit around a round table in full view of one another and asked to speak to
each other.
▪ Questions are distributed to the experts & they are requested to generate their ideas
to the question
Page
15
▪
After every one has written down their ideas, The idea shared is written or the flip
chart, which everyone can see:
▪ Experts are requested to discuss these ideas freely with each other.
▪ As a result no of ideas comes down
▪ Then experts are requested to prioritize these ideas.
Quantitative method-
1- Time series based-
𝑠𝑢𝑚 𝑜𝑓 𝑑𝑒𝑚𝑜𝑛𝑑 𝑜𝑓 𝑎𝑙𝑙 𝑝𝑒𝑟𝑖𝑜𝑑 𝑖𝑛
a. 𝑆𝑖𝑚𝑝𝑙𝑒 𝑎𝑏𝑒𝑟𝑎𝑔𝑒 𝑚𝑒𝑡ℎ𝑜𝑑 = 𝑇𝑜𝑡𝑎𝑙 𝑛𝑜 𝑜𝑓 𝑝𝑒𝑟𝑖𝑜𝑑𝑒
Page
18
Some commonly used Probability distributions-
5. Decision True analysis- It is assumed that the project will be completed in according with
the proposed planning but in reality there is always some flexibility in execution, Hence such
flexibility exists in implementation. There decision tree analysis evaluates project flexibility.
Steps-
I. Identify the problem & alternative option.
II. Make the path of decision
III. Specify the probability & monitory out come.
IV. Evaluate various decision alternative & implement the best decision
6. Game theory- Is the study of mathematical mode less of conflict are cooperation b/w
intelligent rational design- makers.
• Financial feasibility- 3 Major aspects-
i. Estimation of project cost- Total project cost
ii. Estimation of project operation cost – Managing day to day cost
iii. Estimation of project funding – The Cost of project & mote through following two
means.
a) Equity – Capital of investor
b) Debt – Loan from financial institutions.
Page
19
The equity does not attract any interest and is not needed to be paid back, The debt component is
required to be paid with interest.
2- Pay back period method (PB):- It is a measure in terms of which will take a recovery the
cost of investments in term of time.
If cash flow after tax (CFAT) per annum is uniform (equal in all periods) them
𝐼𝑛𝑡𝑖𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
𝑃𝐵 =
𝑐𝑜𝑛𝑠𝑡𝑎𝑛𝑡 𝑎𝑛𝑛𝑢𝑎𝑙 𝑐𝑎𝑠ℎ. 𝑖𝑛𝑓𝑙𝑤𝑜
It is important for every investor to know how and when he will be getting his investment
back.
If cash flow after the tax is non uniform
𝐵
𝑃𝐵 = 𝐴 +
𝐶
A= last period with (-ve) commutative cash out flow.
B= Absolute value of commutative cash out flow
C= cash in flow during the period after period A
Ex- A company is planning to take a project that requires initial invest of Rs, 50 Cr. and is
expected to generate cash inflow after tax per annum as follow-
Year CFAT (Rs,cr) Cumulative
1 10 - 50 + 10 = -40
2 13 - 40 + 13 = -27
3–A 16 - 27 + 16 = -11 B
4 19 – C - 11 + 19 =8
5 22 22 + 8 = 30
𝐵
𝑃𝐵 = 𝐴 +
𝐶
11
=3+ = 3.57 𝑔𝑟.
19
If there are two projects there choose that one which has least payback period.
Page
21
▪ In this techniques discounted below, a discounting function is and to account for time value
of money. This analysis used the future free cash flow projections and discounts them to
convert in the present value estimates
𝑪𝑭𝟏 𝑪𝑭𝟐 𝑪𝑭𝟐 𝑪𝑭𝒏
𝑫𝑪𝑭 = + + ± − − − − − −
(𝟏 + 𝒓)𝟏 (𝟏 + 𝒓)𝟐 (𝟏 + 𝒓)𝟑 (𝟏 + 𝒓)𝒏
CF= future cash flow (after tax)
r= discounted rate
n= no of period of life
𝑵𝑷𝑽
▪ 𝑰𝒇 𝑫𝑪𝑭 > (𝑪𝒖𝒓𝒓𝒆𝒏𝒕 𝒄𝒐𝒔𝒕) 𝒕𝒉𝒆𝒏 𝒑𝒓𝒐𝒋𝒆𝒄𝒕 𝒔𝒉𝒐𝒖𝒍𝒅 𝒃𝒆 𝒑𝒓𝒆𝒇𝒆𝒓𝒆𝒅.
▪Net present value (NPV) - The money received today is worth more than the sum
received in future because it has time value, It is due to following Reason
1. Interest or cost of finance
2. Impact of inflation
3. Effect of risk
NPV computes the present value of the cash inflow after tax.
Net present value = Present value of cash inflow after tax – P.V of cash out flow (entire intestine
cost-)
Interpretation of NPV-
NPV>0 then project is financially valuable (√)
NPV= 0 then project is meeting B.E.P
NPV =0 then project is financially unviable.(×)
II. Cost Benefit ratio CBR or BCR-
𝑇𝑜𝑡𝑎𝑙 𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠 (𝑐𝑎𝑠ℎ 𝑖𝑛 𝑓𝑙𝑜𝑤)
𝐵𝐶𝑅 =
𝑇𝑜𝑡𝑎𝑙 𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑡𝑛.
BCR>1 Project is financially viable (√)
BCR<1 Project is financially unviable (×)
BCR=1 meat B.E.P
• Net benefit cost ratio (NBCR)
NBCR=BCR – 1
NBCR > 0 Viable
NBCR <0 non viable
III. Internal rate of return (IRR)
▪ It is also known as yield on investment method.
▪ Marginal efficiency of capital method.
▪ Marginal productivity of return method
▪ Rate of return method.
▪ Economical rate of return method.
▪ This method takes into account the time value of money by discounting cash inflow and
cash out flow.
The tern internal means that the calculation does not incorporate environmental/ external
factors such as interest vote and inflation.
Page
22
Interest rate may be considered as internal factor also, Due to this features this method is
also known discounted cash flow rate of return method of effective interest rate method.
Definition of IRR-
1. The IRR of an investment of project is the discount rate of return that Meany
NPV=0
2. It is the discounted rate at which the present value of all futures cash flow is equal
to the initial investment- The rate at which the investment achiever a breakeven
point.
3. IRR of an investment is the discounted rate at which the NPV of cost (cash out
flow – cash inflow) of the investment = Net present value of benefits.
Page
23
3. Project Scheduling
Scheduling involves programming requirements and expected program over’s the project
duration. Techniques for Scheduling projects include –
Activities
1. Bar Chart
Each bar represents one specific job A
or activity of the project, the beginning
& end of each our represent the time of B
start & time of finest of that activity. C
▪ It does not show activity inters relationship.
▪ Does not indicate any event during activities D
▪ Does not show any time uncertainty E
▪ It become unmanageable for large no of activates. 1. 2. 3. 4. time
▪ It can not easy to find critical path.
▪ For simple project provide good scheduling & control tool but for large projects its
fail.
1 2
2. Milestone Chart
It is a modification over the original P
3 4 5
Gantt chart Q
Mile stones are key events of a main R
6 7
activity, this are specific pointy in time
8 9 10
which mark the competition of certain S
portions of the main activity.
▪ The beginning & and of the sub divided activates of teaks are termed as mile
stones.
▪ Milestone event is the point indication on the activity path.
▪ Better scheduling chart than bar chart. Activity
3. Line of balance-
The line of balance process
is employed when a
repetitive process exerts
within the contract’s work
space, It helps- Time
▪ Comparing actual progress with a formula plan- 1 2 3 4 5 6
7 8 9
▪ Examining only the deviation from established plane.
▪ Examining only the deviation from established plane.
Page
24
▪ Receiving timely information concerning trouble are an
▪ Fore costing future performance.
▪
4. Fast tracking- Do activity parallel & complete fast.
▪ This technique simply rearranges the activities in the original schedule.
▪ Although fast tracking may not result in an increase in the cost, it leads to an
increase in the risk.
5. Crashing- Crashing is a method for shortening the project duration by reducing the
time of one or more of the critical project activities to less than etc. normal activity
time
▪ Crash only the critical
activities
∆𝐶
▪ Cost slope =
∆𝑡
𝐶𝑐 − 𝐶ℎ
=
𝑡𝑐 − 𝑡ℎ
Crash those activities first which have a minimum cost slope, this is for cost optimization
6. What if Scenario – What it scenario is the process of changing the values in cells to
see how those changer will affect the outcome of formulas on the work sheet, Three
kinds of what if Analysis tools come with excel.
I. Scenarios
II. Goal seek
III. Data tables.
Page
25
9. Scheduling models-
Input
Project manager
pick up schedule
Out put
10. Leads & lags.
Leads- Accelerating an activity by advancing its starting time is called leads
10
Float –s 15 (schedule time)
7 12
(Can cat range date due to float & start 5 day earlier)
Lags – When the activity delayed due to delayed in peered loss activity.
Page
26
4. ProjectNETWORK
4. PROJECT Network
ADM PDM
(Arrow diagramming method) (Precedence diagramming Network)
AOA (Activity on Arrow system) AON (Activity on node system)
1
A B 5 7
2 3
5 7 A B
ADM- 3 Elements of network.
1. Event-
2. Activity - Arrow
3. Dummy --------- dotted line arrow.
Event- A event is an instant of time just on occurrence, It takes no time & no resources.
A A
2 3
1 B B 2 3
C Dual roal event
Page
27
PERT – Program evaluation & review technique
▪ It provides uncertainty in activity & evaluates activity completion duration beaded
on probability. Probability
▪ In PERT all activity follow B- distribution.
Three PERT values 50% area
to=optimistic time
tm= most likely time
tp= Pessimistic times
te= expected time
𝑡𝑜+4𝑡𝑚+𝑡𝑝 time
𝑡𝑒 = 𝑤𝑒𝑜𝑔𝑗𝑡𝑒𝑑 𝑎𝑣𝑒𝑟𝑎𝑔𝑒. to tm te tp
6
𝑅𝑎𝑛𝑔𝑒 = 𝑡𝑝 − 𝑡𝑜
𝑡𝑝 − 𝑡𝑜 𝑡𝑝 − 𝑡𝑜 2
𝑆. 𝐷 = , 𝑣𝑎𝑟𝑖𝑒𝑛𝑐𝑒 (𝑣 ) = 𝜎 2 = ( ) )
6 6
𝑃𝑟𝑜𝑏 − 𝑡𝑖𝑚𝑒 𝑡𝑜 𝑐𝑜𝑚𝑝𝑙𝑒𝑡𝑖𝑜𝑛 = (𝑡𝑒 − 𝜎)𝑡𝑜 (𝑡𝑒 + 𝜎)
Page
28
Critical path method- (CPM)
▪ Activity oriented, based upon single time, use for repetitive work, Associated with
deterministic activity
▪ Total Float- This is the delay which can be imported in an activity without
affecting project completion time. Total float affect both preseason & successor
activity.
▪ Free float – This is the delay which can be imported in an activity without
affecting the successor activity & affective only presses activity.
▪ Independent Float- This float does not affect preseason or successor activity
𝑬𝒊 𝑬𝒋
𝒊 𝒋
𝑳_𝒊 𝑳_𝒋
TF= LJ – [Ei +teij]
FF = Ej – [Li + teij]
IF = Ej – [Li + teij]
1. Forward pass computation.
Li Li
Activity duration
Page
29
Fore cost Estimate to
▪ Earn value analysis- Cumulative Cost. completive
Ev= earn value AC Estimated at
Budgeted cost of work Completed
Performed PV
PV – Planed value
Budget at
AC – Actual cost EV
completive
Rate of review
At time row
Time
Earned value analysis is an industry standard method of measuring a project progress at
any given point in time, forecasting its completion date and final cost, and analyzing
variance in the schedule and budget as the project proceeds.
1. Cost variance (CV) = EV – AC
2. Cost performance index (CPI) = 𝐸𝑉/𝐴𝐶
3. Schedule variance (SV) = EV – PV
4. Schedule performance index (SPI) = 𝐸𝑉/𝑃𝑉
5. Time variance = Time from date of review when EV = PV
6. Estimated cost performance index (ECPI) = 𝐵𝐴𝐶/𝐸𝐴𝐶
BAC – Budget at completion
EAC – Estimated cost at completion.
1. Variance in completion = BAC – EAC
2. To complete performance index (TCPI) = (𝑤𝑜𝑟𝑘 𝑟𝑒𝑚𝑎𝑛𝑖𝑛𝑖𝑛𝑔 )/
(𝐵𝑢𝑑𝑔𝑒𝑡 𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔) = (𝐵𝐴𝐶 − 𝐸𝑉)/(𝐵𝐴𝐶 − 𝐴𝐶)
Q- A summary of the facts-
Original project cost = 320 staff days
Original project schedule = 4 months
Planned value = 80 staff- days at I month
Actual Cost =82
Earned value =75
Current staffing =4 peoples
Solve= 1. Cost variance (SV)= EV-AC
= 75-82=7 stuff days
2. Cost performance index(CPI)=𝐸𝑉/𝐴𝐶 = 75/82 = 0.91
3. Schedule variance (SV)= EV-PV
= 75-80=5stuff days
4. Schedule performance index(SP)= 𝐸𝑉/𝑃𝑉 = 75/80 = 0.9375
Page
30
5. Project Control Tools
There are many tools available to assist with accomplishing the task and executing the
responsibility.
1. Graphical Evaluation and review technique(GER)-
It is a network analysis technique used in project management that allows
probabilistic treatment both network logic and estimation of activity duration.
▪ It use the activity as well as nudes as probalistic
▪ It allows loops within takes
▪ It user Monte Carlo simulation technique.
▪ It resolves the limitations of both CPM & PERT
2. Critical chain method- It is a method of planning and managing projects that
emphasizes the resources required to execute project tasks.
▪ Critical chain project management is based on method and algorithms
derived from theory of constraints.
▪ It is based on criteria of resource buffer, project buffer and feeders’ buffers.
▪ These buffers are added to the critical chain as a result, very after the
critical path of the network changes.
▪ It is the resources optimization control tool
▪ Resource based network technique
3. Decision CPM- In a network there are multiple network path, decision CPM
technique helps in choosing the best alternating path.
4. Resource Leveling- “A technique in which start and fresh dates are adjusted
based on resources constraints with the goal of balancing demand for resources
with the available supply”. recourse
Resourc 3 3 3 3
3
e Time
3
Time
1 2 3 4
Page
32
6. Tendering
Tender is a written after to execute the certain work under certain terms and condition, it
is also called BID.
▪ It is written by the tender or (The persons who after the tender).
Contract Signing of
execution ad contract
ministrative
Page
33
▪ Infrastructure available, Machinery, Equipment and Manpower
▪ Previous Experience
Earnest money deposit- (EMD)
It is the amount to be deposited by all the tenders when they submit their tender. The
EMD amount values from 1% to 3% of the tender value, Once the construct is finalized,
the EMO is return back to all the un successful tenders, the EMD of the successful
tenders is retained as a resource of caution so that he will not with draw his often.
Security deposits- Security deposits is the amount to be deposits by the successful tender
after the contract is finalized. Normally it is about 15% of the total value of the contract.
This amount is collected as safety measure so that the constriction fulfills all terms and
conditions of contract.
Lotion of intent (LOI)- This is a letter issued to the successful tender about his often
being accepted. LOI is not a legal document the two parties have to necessarily executive
the contract by singing the contract argument.
Contract
A contract is legal argument b/w two parties for the execution of certain works under
specific condition. The argument enforceable by law, It has two distant parts.
▪ A contract is an argument
▪ An argument most be enforce able by law
Essential features of a void contract-
▪ Lawful consideration b/w the parties to the construct.
▪ Object of the contract most be lawful
▪ The terms of the contract shall be capable of performance
▪ Contract shall full fill the necessary legal formalities
Contract
Turnkey contract Non turn key contract
Lump sum fixed price contact
Unit price contract
Bill of quality contract
Schedule of rates contact
Cost plus contract
K-2 Contract (Software based)
Hybrid contract (Time & material contract)
Item rate contracts (Govt, Contracts)
Turnkey contract-
In turnkey contract, the entire responsibility of project execution is entrusted to the
contractor.
Page
34
▪ The owner comes into picture only when the project is completed and he turns the
key of plant to start production.
▪ Since the entire works is done by a single contractor
▪ It may be for whole project or even for a sub unit of a main project.
Non turnkey contract- Non turnkey contract are performed when the projects are small
sized, It is also called as item sate contract in which the drawing is provided by the
company, The contractor will only basic based on the drawing given to him.
1. Lump sum contract (fixed price)- Under the lump sum contract, a single ‘lump
sum’ price for all the works is agreed before the works, It is generally used for
construction work.
2. Unit for prize contract- In unit price contract, construction work is done in which
is client or owner pays a fixed sum for each completed unit of work.
3. Hybrid contract- A hybrid contract is something mode by joining two or more
things together in under to form a separate and distinct contract.
4. Item rate contract- An item rate contract or unit price or schedule contract is a
type of contract which is undertaken on per price or item basis.
Depreciation
Depreciation is an accounting method to allocate the cost of tentative asset for a
particular period of useful life.
Type of depreciation- a) Physical depreciation
b) Function deprecation
c) Contingent deprecation (due to accident)
Difference b/w desperation and Obsolescence-
Depreciation Obsolescence
▪ Physical in nature ▪ Functional in nature
▪ Depend upon age ▪ Do not depend on age
▪ Depend upon physical condition ▪ Do not depend on physical
▪ Calculation method is used condition.
▪ No method to use for calculation
Depletion- A reduction of the values of on asset on a balance short that comes about as a
result of the physical reduction of the asset’s features Depletion reduces the value of the
oil field in away related to the amount of oil drilled up over a given period of time
Depletion is used most after with natural resources,
𝐴𝑛𝑛𝑢𝑙𝑎 𝑑𝑒𝑝𝑙𝑒𝑡𝑖𝑜𝑛
= (𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑡ℎ𝑒 𝑟𝑒𝑠𝑜𝑢𝑟𝑐𝑒)/(𝑁𝑜. 𝑜𝑓 𝑢𝑛𝑖𝑡𝑠 𝑜𝑓 𝑟𝑒𝑠𝑜𝑢𝑟𝑠𝑒)
× 𝑁𝑜𝑓 𝑜𝑓 𝑢𝑛𝑖𝑡 𝑢𝑠𝑖𝑑 𝑖𝑛 𝑎 𝑦𝑒𝑎𝑟.
Depletion fund- When one source of natural resources is exhaust, company buy another
source for use, the found which is use is called depletion found.
Method of depletion calculation-
Page
35
Ci= Initial cost of asset
Cs= Salvage value of asset
n= life of asset in year.
Bm= Book value in the with year,
1. Straight line method- Depletion is calculated at a fixed value of every year, &
Depletion is fixed in every year
𝐷_1 = 𝐷_2 = 𝐷_3 = 𝐷_𝑚 = (𝐶_𝑖 − 𝐶_𝑠)/𝑛
𝐷_𝑚 = 𝐶_𝑖 − 𝑚((𝐶_𝑖 − 𝐶_𝑠)/𝑛)
Application – Purpose of taxes, civil construction civil appliances, civil application.
2. Declining balance method – Depletion is calculated at a prcenatge value of every
year.
1st Year – B1 = Ci(1 – FDB)
FDM= (FATOR OF DECLING BALANCE)
2nd Year – B2 = Ci (1 – FDB ) – Ci (1 – FDB) FDB
= Ci (1 – FDB)2
B3 = Ci (1-FDB)3
Bn = Cs
CS= Ci (1 –FDB)n
FDB = 𝟏 − (𝑪_𝑺/𝑪_𝒊 )^(𝟏/𝒏)
Application – Electronics industry.
Page
36
7. Organizations
Social unit of people that is structured and managed to meet a need or to purpose
collective goals.
1. Functional organization- Functional organization is a type of organizational structure that
uses the principle of specialization based on function or role.
General Manager
PM-1
Project relationship
PM-2
PM-3
Supervision
PM-4
PM - Project manager
Page
37
Strong matrix organization- The command of technology with project manager saw a
result his influence for the worker is more than the functional manger, hence the
manager is called program manager or project manager.`
Weak matrix Organization- functional mangers have commerce of technology &
influence of project manager is reducing. Considerately, it is called weak matrix
organization; here the manager is called co-ordination or foliature
Balanced matrix organization – The influence of project manager & functional
manager are balanced, here the project manager is called project manager or
project leader
PROJECT EVALUATION
Project evaluation is an assessment of the project during the course of implantation.
Objectives-
▪ To verify if the progress the progress of project implementation is as planned and
to take corrective measures if the project progress lager behind the schedule.
▪ To check the quality standards.
▪ To identify any unexpected problem areas and to plan for managing such
situations.
▪ To appraise the clines about the progress of project
▪ To bring about overall improvement in project performance.
Method of evaluation-
Post project evaluation (Post Audit)- Post Audit done after completion of Project.
1st Phase – After completion of project
2nd Phase – 2 to 3 years after completion of program objective of post project evaluation
is to insure find out the reasons for short coming, archive men of Project.
- To create a data for further education & research purpose.
Enterprise resource planning (ERP): ERP is a process by which a company manager, integrate the
important parts of its business.
Maintenance
management Production
Material management
management
Enterprise Account &Financial
Lugestic Resource management
Management Planning
Share & Market
management
Page
39