Professional Documents
Culture Documents
Maintenance Resource
Requirements
© A.K.S. JARDINE
Maintenance Optimization
© A.K.S. JARDINE 2
Queueing Theory
© A.K.S. JARDINE
Queueing Problem
Workshop
Arrivals 2 Departures
3
λ = 30 jobs / week
.
.
.
Wq
n
Ws
© A.K.S. JARDINE 4
Solution continued:
• If n = 5, then capacity of workshop = 5 x 5.5
= 27.5 jobs / week
• However, demand = 30 jobs / week
• Therefore, at least 6 lathes are needed
ρ = 0.91 When n = 6:
ρ (traffic intensity) = λ = 30
1.4 . nµ (6)(5.5)
∴ ρ = 0.91
∴ W s = Wq + 1 / µ
6
n = 0.255 + 1 / 5.5
(# of servers) = 0.437 week
NOTE: ρ is a measure of the average busyness of the system
© A.K.S. JARDINE 6
Solution continued:
• Similarly, we can obtain Ws for n = 7, 8, …, 12
• When n = 7, then ρ curve to use is:
ρ = λ = 30 = 0.78
nµ (7)(5.5)
© A.K.S. JARDINE
Initial Perspective of Lathe System
µl LARGE LATHES
µl
µl
|
|
p |
DEPARTURES
ARRIVALS
(1 – p)
µm
µm
µm
|
|
MEDIUM LATHES
|
© A.K.S. JARDINE 9
Second View of Lathe System
LARGE LATHES
1
MEDIUM LATHES
INCOMING
2
JOBS DEPARTING JOBS
3
4
5
6
7
8
SMALL LATHES
© A.K.S. JARDINE 10
Representation of Maintenance Workshop
LATHES
A QUEUE
A JOBS 1
p = 4.90 ∑ = 50 µ = 3.08
∑ = 36 λ = 2.28
λ = 1.64 B QUEUE
∑ = 14
B JOBS 2
p = 10.1 ∑= 37 ∑ = 135 µ = 7.25
INCOMING ∑ = 74 p = 24 λ = 6.14
JOBS λ = 3.36 ∑= 114
p = 76 3
∑ = 76 µ = 4.10
∑ = 733 D QUEUE ∑ = 151 λ = 3.46
λ = 33.32 4
D JOBS p = 15.2 ∑= 88 µ = 4.75
∑ = 111 λ = 4.00
λ = 5.05
∑ = 128 5
E QUEUE 6
E JOBS 7
p = 69.8 ∑ = 384 8 µ = 17.8
∑ = 512 λ = 17.45
λ = 23.27
p = Percentage of jobs going along branch ; ∑ = Total number of jobs going along branch in 22 weeks;
λ = Arrival rate of jobs/week during 22 week period; µ = Service rate of jobs/week during 22 week period
© A.K.S. JARDINE 11
Results
Lathe Idle Time as a Mean Wait of
Situation Number Percentage of Jobs in Queue
Hours Available (days)
1 26.4% 6.55
2 15.4% 5.25
Existing State 3 15.5% 9.37
4 15.7% 8.1
5, 6, 7, 8 2% 5.11
1 44.6% 2.95
Additional 2 38.8% 1.65
Machine in 3 43.0% 1.97
Group 6 4 36.4% 2.45
5, 6, 7, 8, +1 2% 2.83
1 44.6% 2.95
Additional 2 42.2% 1.49
Machine in 3 39.4% 2.56
Group 4 4+1 12.6% 2.46
5, 6, 7, 8 20.8% 1.77
© A.K.S. JARDINE 12
Petrochemical Plant
(Crew size and shift patterns)
LINE 1
LINE 2
LINE 3
MIXING TANK
Use Queuing Theory
© A.K.S. JARDINE 13
Why Use Simulation Modeling of Butyle 1?
© A.K.S. JARDINE 14
Maintenance Crew Size Simulation
TTF = E, MTTF = 2950 tonnes line Baler 1
TTR = Weibull 1
β = 4.20 Cyclones
Expellers Wrapper
η = 2.29 hours
Po l y Conveyors
Baler 2
Gene Good Product
rato
rs Coagulator
North line
2 Baler 3
Cement Cyclones
Halogenator Reslurry TK18XB Wrapper Scrap
Make-up Expellers
system Conveyors
Baler 4
Coagulator
South
Reblend
Piles
Crusher
West
© A.K.S. JARDINE 16
Lakeview Coal Power Station
© A.K.S. JARDINE 18
Summary of Simulation Model Validation
Results compared to actual data for previous year
Quite Similar
© A.K.S. JARDINE 19
Truck Shop Optimization
© A.K.S. JARDINE 20
Right Sizing a Fleet of
Mobile Equipment
(Section 5.5, page 207)
© A.K.S. JARDINE
Trend in Truck Operating Cost
60
$ per truck
operating
hour, c(k)
20
Equivalent
Economic Total Annual
Fleet Size Annual Cost
Life (Yrs) Fleet Cost ($)
(E.A.C.) ($)
16 5 506,102 8,097,632
7,995,132
18 5 444,174
(min)
22 6 381,299 8,388,578
© A.K.S. JARDINE 23
Optimal Contracting-out Decision (Section 5.6, page 209)
Optimal
level of Total cost/unit time
maintenance
resource
Fixed cost/unit time
Cost
Internal
processing
cost/unit time
Alternative service
deliverer’s
processing
Cost/unit time
© A.K.S. JARDINE 24
Maintenance Management
© A.K.S. JARDINE 25
Some Simulation Packages
SimProcess (www.simprocess.com)
Flexsim (www.taylorii.com)
Micro Saint (www.maad.com)
Witness (www.lanner.com)
Arena (www.rockwellsoftware.com)
© A.K.S. JARDINE 26
Maintenance Resource Requirements
© A.K.S. JARDINE 27