PEP-GEN-PCD-004-A4
PT. KPM OIL & GAS
Page 1 of 177
PREP’D : Theresia PROC
PROCUREMENT PROCEDURE
CHK’D : Banar S. PE
APP’D : Taufik U. ED
TENDER NO : EPR1-S18PL0070A-P29
TABLE OF CONTENTS
Tender No.: EPR1-S18PL0070A-P29
JASA REKAYASA TEKNIK, KONSTRUKSI DAN PEMASANGAN STASIUN KOMPRESI GAS LP BETUNG PENDOPO FIELD
Document No.
PEP-GEN-PCD-004-A4
PROCUREMENT PROCEDURE Rev. No : A
PT. KPM OIL & GAS Page : 3 of 17
1. INTRODUCTION........................................................................................................................5
2. GENERAL SCOPE.......................................................................................................................5
3. DEFINITIONS.............................................................................................................................5
4. TYPE OF CONTRACT :................................................................................................................6
5. SPECIAL PROJECT REQUIREMENTS...........................................................................................6
5.1 Time Charges...............................................................................................................6
5.2 Taxes ........................................................................................................................6
5.3 Forms ........................................................................................................................6
5.4 Procurement Organization...........................................................................................6
5.5 Client Participation......................................................................................................7
5.6 Client Purchase Equipment..........................................................................................7
5.7 Spare parts for Operation............................................................................................7
5.8 Local Content...............................................................................................................7
6. PROCUREMENT SCOPE OF WORK.............................................................................................7
7. PROCUREMENT SCHEDULE.......................................................................................................8
7.1 Overall Project Schedule (Project Master Schedule)....................................................8
7.2 Project Procurement Front End Schedule....................................................................8
8. PROCUREMENT IMPLEMENTATION PLAN................................................................................9
8.3 Purchasing...................................................................................................................9
8.3.1 Source Of Material and Equipment.................................................................9
8.3.2 Bidders List......................................................................................................9
8.3.3 Invitation To Bid / Inquiries.............................................................................9
8.3.4 Commercial Bid Evaluation...........................................................................10
8.3.5 Vendor Recommendation.............................................................................11
8.3.6 Pre - Award Meeting.....................................................................................11
8.3.7 Issuance of Purchase Order (Equipment and Materials)...............................11
8.4 Expediting..................................................................................................................12
8.4.1 Preventive Expediting...................................................................................12
8.4.2 Commencement Of Expediting.....................................................................12
8.4.3 Representative Expediter..............................................................................12
8.4.4 Responsibilities.............................................................................................13
1. INTRODUCTION
The purpose of LP Betung Gas Compression is to replace existing rental units. With
the supply of compressors, production can be optimized so that the production gas
can be utilized as a gas sales that can increase profits for the country. In addition, the
utilization of this gas also reduces environmental pollution and supports zero flared
gas policy.
2. DEFINITIONS
3. TYPE OF CONTRACT :
4.2 Taxes
• Other than Indonesian Import Taxes and Value added Tax, should be Contractor
responsibility.
4.3 Forms
All applicable forms for this project are using CONTRACTOR standard form.
The nucleus of the procurement task force is the Procurement Engineer, Purchasing,
Expediting and Traffic Coordinator that occupied by CONTRACTOR's personnel.
Additional personnel including equipment/bulk purchasing buyers, traffic specialist,
expeditor, etc. will be assign by CONTRACTOR member as required to support
project requirement.
Procurement personnel shall be dedicated for this project and work in the project
team location.
The Client shall have the right to have CONTRACTOR Technical Bid Analysis and
Commercial Bid Tabulation and to proceed price negotiation with the recommended
vendor (by CONTRACTOR) up to selection of successful bidder for Provisional Sum
scope.
Purchase Order for long lead delivery/critical item that shall be placed before NTP to
CONTRACTOR then it should be issued by Client. CONTRACTOR position is only assist
Tender No.: EPR1-S18PL0070A-P29
JASA REKAYASA TEKNIK, KONSTRUKSI DAN PEMASANGAN STASIUN KOMPRESI GAS LP BETUNG PENDOPO FIELD
Document No.
PEP-GEN-PCD-004-A4
PROCUREMENT PROCEDURE Rev. No : A
PT. KPM OIL & GAS Page : 7 of 17
Client for technical and commercial clarification. All applicable documents have using
CONTRACTOR documents but the buyer name has changed to COMPANY.
6.1. Purchase the equipment / materials from local and foreign / offshore vendors as
required for the project.
6.3. Expediting vendors for all purchased equipment / materials to monitor the actual
vendor progress including documents requirement to maintain / keep vendor
delivery as scheduled.
6.4. Assist Client to prepare Master Importation List and Importation formalities
arrangement.
7. PROCUREMENT SCHEDULE
Initially the Project Master Schedule will be used as a timing; guide of all necessary
Procurement Departmental Plans, especially for the purchasing, expediting and
material delivery to job site.
Based on the above schedule, Procurement will develop and establish a detailed list
of early Procurement activities and schedule for critical items including long lead
delivery equipment / materials. In this procurement preliminary schedule and
activities, the following will be determined based on a prediction date of work
sequences starting from:
Procurement will use these scheduled dates during negotiations and purchase
commitment with vendors.
8.3 Purchasing
The purchasing group for this Project will consist of buyers for engineered
equipment and buyers for bulk materials. Buyers are accountable to the Project
Purchasing Coordinator for overall purchasing efforts.
Major activities of purchasing include, but are not limited to the following :
Preference shall be given to locally supplied materials to the extent of price, quality,
schedule, availability and vendor's capability. Other materials will be procured on a
world -wide basis as per Client's approved vendor list.
Basically inquiry shall be issue to vendor listed in Client approved Bidder List.
However, CONTRACTOR may propose additions or modifications to the Client
Supplier List.
As the first priority, inquiries issued to the bidders that have supported
CONTRACTOR during proposal stage.
Due to very tight schedule for this project, inquiries will be issued on the basis of
obtaining competitive bids from three vendors (during proposal), especially for
equipment to short the clarification time. For bulk materials, inquiries may be issued
to more than three vendors to get competitive price.
Bids will be solicited directly from manufacturers or their authorized agent(s), except
for those commodities usually handled by a distributor or stockiest.
CONTRACTOR will indicate on all inquiries, whether or not equipment / materials are
subject to inspection by CONTRACTOR and / or Client or witnessed by a third party
inspection. A copy of inspection requirements will be included in appropriate inquiry
packages. All materials requiring inspection will be defined in the project inspection
procedure.
CONTRACTOR will prepare a complete commercial bid evaluation for all engineered
items and appropriate non-engineered items which shall include but not be limited
to the following information where applicable :
In parallel with the above, a complete technical evaluation and recommendation will
be made, independent of commercial terms or schedule impact. This technical
evaluation will include all normal technical debits and credits, plus weighted
considerations with respect to standardization, operability, serviceability,
subsequent maintenance costs and spare parts availability.
If, in the judgment of the Project Procurement Manager, the commercial evaluation
dictates that certain vendor(s) can be eliminated from contention on a first cost or
other commercial basis, a recommendation will be coordinated with engineering to
cease all further technical evaluation of these vendor (s).
Vendor recommendation will consist of Technical Bid Analysis (TBA) and Technical
Bid Compliance (TBC). TBA submit to Client by Transmittal while TBC submit to Client
by Confidential Letter.
When the magnitude of the order or complexity of the equipment and / or material
dictates, pre-award meetings will be scheduled with selected vendors to ensure all
aspects of the inquiry and their proposal have been properly interpreted and
evaluated. This meeting shall be held in the Jakarta Project Office, for major
equipment and critical items only. This meeting is intended to reconfirm all of
communication between CONTRACTOR and vendor during clarification stage both
commercial and technical aspects prior to placing order.
Definitive schedules for the receipt of engineering information from vendors, will
be established based upon project master schedule requirements.
8.4 Expediting
Vendor contact by Jakarta Project Office personnel will begin within one week period
following issuance of the Purchase Order. The assigned Project Expediter
(coordinator) will, together with the Procurement Manager, determine the level or
degree of the expediting effort required. The degree of expediting can range from
limited desk expediting, to weekly/bi-weekly visits, to in-residence expediting. The
degree varies depending upon criticality of the item and Project requirements.
Notification of delays of critical orders will be communicated immediately by the
Procurement Manager to Project Management.
8.4.4 Responsibilities
Once it is determined that such an assignment should be made and the frequency of
such visits determined, the responsible administrator will prepare the assignment
form. This will then be reviewed and initialed by the Project Procurement Manager.
Area expediting reports will then be sent to the Project Procurement Manager who
will review contents, annotate as required and forward to the responsible
administrator for action and distribution. Copies of all expediting reports shall be
transmitted in accordance with the project documents distribution list.
The expediter's report will include the Fabricator's Shop Schedule which can be
highlighted in order to determine problem areas or slippage of milestone events. The
Procurement Manager in turn, reports to Project Management.
• Tracing of lost of late delivered materials, along with assistance in the resolution
of material shortages and equipment damage will also be performed by the
Project Traffic section. Packaging methods and systems shall be included in the
Purchase Order package.
8.5.2 In detail planning and execution of traffic, the following shall be taken into
consideration :
• Shipping schedule:
The shipping will be prepared based on the information of equipment / material
shipping data (weight and volume), delivery point / port and required delivery
date.
This shipping schedule will be updated monthly, according to the purchase
order's delivery date and / or vendor's promise delivery date.
• Shipment arrangements, will be executed in accordance with the following:
- Meet the project schedule
- Use consolidation shipments.
- Basically, project cargo will be transported to site without transshipment.
However, for less than minimal volume cargo, transshipment shall be
considered.
Main forwarder shall be nominated by CONTRACTOR and Indonesia
shipping line shall be considered.
Forwarder's scope will be extended to duties between vendor's delivery and
FOB vessel, as well as export formalities, selection of ocean vessel and
booking of space.
At least seven (7) days prior to arrival at port of shipment, these documents
should be available to Traffic (clean B/L, AWB, FCR team)
Traffic shall be responsible to ensure all documents required for clearance,
will be received by Traffic job site at least ten (10) days prior to vessel
estimated time of arrival.
9. PROCUREMENT PROCEDURES
Contingency plan will generally cover alternative efforts to anticipate any problem
which might occur during execution of procurement activities, from purchasing stage
through expediting, traffic and material control which shall be established to
overcome each problem.
Considering to the budget, and then procurement should optimize the number of
personnel. Double assignment is applied for subordinates to handle purchasing and
expediting job. The following is manpower summary;
- Manmonth
- Manhours
- Personnel
Procurement budgeting and control shall be based on Project Cost Control's budget
designation within procurement scope of work which has been approved by Project
Manager. In the execution of procurement activities, Procurement Manager shall
closely coordinate with Project Control Manager, strictly monitor / control the
budget, and to the extent possible, achieve satisfactory results without utilizing all of
the budget.
14. ATTACHMENT