II DESIGN APPROVAL
12 - Approval Civil Work
13 - Approval Blower
14 - Approval Diffuser
15 - Approval Pump
16 - Approval UF - Ultra Filtration
17 - Aproval RO - Reverse Osmosis
18 - Aproval Electrical, Panel Controll, Instrumentation
19 - Approval Valve, Piping
20 - Material Approval
V DELIVERY TO SITE
36 - Local Material
37 - Overseas Material
VI CIVIL CONSTRUCTION
38 - Land Clearing
39 - Piling
40 - Aeration Tank
41 - Water Clarifier Tank
42 - Clarified Water Storage Tank
43 - UF Product Storage Tank
44 - Equipment Room & Foundation
45 - Intake - Pump & Panel Room Intake
Weekly Progress Plan 0.12 0.58 0.72 0.84 0.95 1.22 1.55 1.68 1.89 2.35 3.58 7.57 8.72 8.59 8.88 9.57 9.78 9.79 9.88 5.86 3.85 1.69 0.34
Cummulative Weekly Progress Plan 0.12 0.70 1.42 2.26 3.21 4.43 5.98 7.66 9.55 11.90 15.48 23.05 31.77 40.36 49.24 58.81 68.59 78.38 88.26 94.12 97.97 99.66 100.00
Actually Weekly Progress 0.00
Cummulative Actually Weekly Progress 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Recovery Plan Cummulative Progress
Deviation 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00