IT Infrastructure Change Management Gu

Change Categories:
Normal - Planned changes that meet risk-based lead time requirements
Expedite - Changes with increased urgency that can't meet risk-based lead time requirements of a Normal chan
Emergency - Changes required immediately to restore service, or prevent imminent service outage. (If no wor
changes are exempt from lead time requirements)

Risk Levels:
High - Service/business impact or outage and/or significant coordination required
Medium - Outage/service impact posssible and/or coordination required
Low - No outage or service impact/no coordination required

Request Lead Time (minimum):


(Lead time is determined by the difference in days between the date when the request is submitted, and requested im
High risk - 10 calendar days
Medium risk - 7 calendar days
Low risk - 48 hours

Form Process: *Note - Changes are not to be implemented without proper approval
Requestor completes all required fields of the Request for Change (RFC) form.
Requestor emails completed RFC form to Functional Approver for review and approval with DL-GIS IT Change M
(Functional Approver is the manager to whom the requestor reports). *Note: Requestor cannot be the same
may appoint a delegate to approve changes. If a delegate approves a change, the manager retains full account
granted.
Functional Approver or delegate sends approved RFC form back to requestor with 'Approved' (or similar) in the b
the request is rejected by the approver, the requestor must revisit steps 1 and 2 with updated RFC).
Change Management will then review the RFC and reply to the email thread with 'Approved' (or similar) in the b
request is rejected by Change Management, the requestor must provide clarification, and/or revisit steps 1, 2 an
Once approval has been granted by both the Functional Approver and Change Management, the change can be
approved change window.
Requestor implements change, or coordinates implementation with team(s) required to implement within the ap
If AMI (Application Master Inventory) update is required, requestor will update AMI as needed before submitting
Upon completion, requestor updates 'Closure Code' field on RFC form, and adds implementation outcome/comm
Requestor sends completed RFC form to Change Management team (via DL) for upload to IT Operations ShareP

For assistance with the RFC form, please contact the Change Management team via DL-GIS IT Change Managem

**If there are any questions/issues/concerns with this process, contact IT Operations Manager To
immediately – Otherwise, requestor is expected to adhere to this process until further notice.**
For assistance with the RFC form, please contact the Change Management team via DL-GIS IT Change Managem

**If there are any questions/issues/concerns with this process, contact IT Operations Manager To
immediately – Otherwise, requestor is expected to adhere to this process until further notice.**
gement Guidelines

irements of a Normal change


ervice outage. (If no work-around exists--Emergency

ubmitted, and requested implementation date.)

out proper approvals!

with DL-GIS IT Change Management carbon copied


stor cannot be the same as the approver. Manager
nager retains full accountability for any approval

roved' (or similar) in the body of the email reply (if


updated RFC).
oved' (or similar) in the body of the email (if the
nd/or revisit steps 1, 2 and 3 with updated RFC).
ment, the change can be implemented within the

o implement within the approved change window.


needed before submitting RFC for closure.
mentation outcome/comments.
d to IT Operations SharePoint.

L-GIS IT Change Management.

Operations Manager Tom Narsavage


til further notice.**
L-GIS IT Change Management.

Operations Manager Tom Narsavage


til further notice.**
Change Category Change Risk

Normal High
Expedite Medium
Emergency Low
Outage Required? Closure Codes

Yes Completed Successfully


No Partially Completed (provide details in Comments section)
Backed Out (provide details in Comments section)
Cancelled
IT Infrastructure Request for Change (RFC) Form
This form is intended to capture all the information necessary to implement a change for the Ortho enterprise environment. Once completed, form is to be submitted to line manager for approval ( i.e. James
Cooney for Compute Services, John Mitchell for Network, etc .---DL-GIS IT Change Management should be in CC on all change requests).

Click here to review request submission Guidelines


Request Submission Date:
Requestor Name: Surjit Singh
(Date that the request is submitted to CM Team) 2/1/2019
Scheduled Start Day/Time:
(d-mmm-yyyy h:mm) (Eastern Time) 02/16/2019 1:15 PM ET
Requestor Phone: 1 5857557058

Scheduled End Day/Time:


(d-mmm-yyyy h:mm) (Eastern Time) 02/16/2019 3:15 PM ET
Requestor eMail: surjit.singh@orthoclinicaldiagnostics.com

The following section is intended to capture all of the required information for review & approval. All fields are required unless otherwise noted.
Downgrade SQL SERVER BI servers from Enterprise SQL Server 2016
to Standard Edition
Change Summary:
Change Category:
(Brief summary of request)

Downgrade SQL SERVER BI servers from Enterprise SQL Server 2016


to Standard Edition
Change Risk:
Change Details:
(Full description of work to be done)
Outage Required?
(If Yes, details must be provided in Outage
Impact field below)

To use the enhanced features in standard edition later which at The SQL Server instance will be unavailable when the downgrade
present was earlier only available in SQL Server 2014 Enterprise from Enterprise to Standard edition is in progress and Application
edition . This will also save the licence cost of the SQL Server. Some team when be. The process has been tested on a development
of the features are compression , Columnstore indexes etc. server. The unavailability of the service has been communicated by
the eConn team and agreed to by the business. Craig
Ritson/Veronika from Application team will be working with DBA and
monitoring for any possible application issues which will require
Reason for Change/ Database Admin/BI application team to resolve any issue.
Outage Impact
Business Justification: (Expected duriation of outage, and who/what
(Must be provided for all changes) will be impacted?)

Change Driver
AMI Update Required?
(If your change is being driven by a specific IN, N/A
(If yes, provide details of what needs to be
SR or project request, provide reference
updated in Affected CIs section)
number; otherwise N/A)
The server downgrade is the standard process and will be executed
Test Plan and screenshots are logs will be provided to confirm the upgarde has Backout Plan The backup of the system databases will be taken and scripts has been
(What steps will be taken to confirm been sucessful. Check the version and edition of the SQL Server from (What steps will be taken if implementation generated for all the user accounts.1) Upgrade from Standard edition to
implementation was successful?) MMC which should show "Microsoft SQL Server 2016 (SP2)" was unsuccessful?) Enterprise Edition by running the SQL Server 2016 Enterprise edition setup.

Emergency Change Justification:


Closure Code:
(For Emergency change requests only)
LEBPDVWBI19 (GLOBAL DATA MART) SQL Server 2016 has been successfully downgraded from Enterprise
edition to Standard edition. The output of the @@version command is
Affected CIs: BI below "Microsoft SQL Server 2016 (SP2-CU5) (KB4475776) -
(e.g. servers, network devices, applications) 13.0.5264.1 (X64) Jan 10 2019 18:51:38 Copyright (c) Microsoft
Corporation Standard Edition (64-bit) on Windows Server 2012 R2
Standard 6.3 <X64> (Build 9600: ) (Hypervisor) "