BUREAU: Construction
REGION: 10
DISTRICT/CITY: Mis. Or. First Dist. Eng'g Office
Construction of Multi-Purpose Building (27.6m x 17.7m), Excluding; Electrical and Drainage/Plumbing Works
% OF ADJUSTED
ITEM NO. DESCRIPTION QTY UNIT DIRECT COST UNIT COST TOTAL ITEM COST
TOTAL UNIT COST
Occupational Safety and Health
B.7 4.01 2.5 Month 40773.61 16309.444 18494.91 46237.27
Program
Project Billboard / Signboard
B.5 0.48 1 Each 4888.58 4888.58 6416.26 6416.26
Mobilization / Demobilization
B.9 0.87 1 Lump sum 8818.07 8818.07 11573.72 11573.72
1017077.68 1327636.37
TOTAL ESTIMATED EXPENDITURES
I. ESTIMATED COST:
A. DIRECT COST:
1. Mobilization/Demobilization
2. Materials 61.84 835,483.39
2.1 Supply/Delivery
2.2 Testing of Materials
3. Labor (including fringe benefits) 10.48 141,592.56
4. Equipment Expenses 2.96 40,001.73
B. INDIRECT COST:
1. Overhead, Contingency, Mis - 10.84 146,445.61
cellaneous (8% to 15% of A1 to A4)
2. Profits (8% to 10% of A1 to A4) 7.47 100,892.30
3. Comprehensive all risk insurance ------------- Mobilization
(1.5% of A1 to A4)
4. VAT (5% of A3 to B3) D.O. 4.68 63,220.78
Percentage Tax (5%)
98.27 1,327,636.37
1. Engineering and Administrative
overhead (3% of A1 to A4) D.O. 1 20,000.00
2. CO/RO Retention
3. Materials to be furnished by the
Government
1 20,000.00
III. CONTINGENCY/RESERVE