Professional Documents
Culture Documents
Technology Briefing - Superconductivity For Power Delivery Applications - November 2014
Technology Briefing - Superconductivity For Power Delivery Applications - November 2014
Superconductivity for
Power Delivery Applications
Decmber 2014 Program 36
continued on page 2
11159456
Figure 2: Transmission
system before and after
HTS cable (Source:
Nexans)
Figure 4: Diagram
of the AmpaCity
HTS cable cooling
system (Source:
Nexans)
AmpaCity Background
The total cost of the AmpaCity project is approximately • Start of Component Manufacturing: March 2013
€13.5 million ($16.8 million), including €5.9 million • Groundbreaking Ceremony: April 9, 2013
($7.3 million) from Germany’s Federal Ministry of Eco-
nomics and Technology (BMWi). AmpaCity milestones • System Installation On Site: September-December 2013
include: • Commissioning Testing: December 16, 2013
• Project Start: September 2011 • System Commissioning: March 10, 2014
• Prototype Manufactured: October 2012 • Pilot Operation: 2014 to 2016 (in progress)
• Type Text Completed: February 2013
• Fault current limiting: FCL capability allows approaches not Three Phases
available with other technologies.
In Phase 1 of Project HYDRA, AMSC and Southwire developed
REG systems would allow the installation of small, cost- an IFCL HTS cable that passed industry qualification tests at
effective urban substations, which is a significant advantage in Oak Ridge National Laboratory and was approved for installa-
densely built urban centers. By sharing load among substations, tion in urban power networks. Southwire’s Triax® cable arranges
REG enables urban utilities to better use their existing assets the three electrical phases concentrically around a common core
and offsets substation investments to handle load growth. If one cooled by liquid nitrogen, and reportedly has 10 times the power
substation in a REG system is compromised, other substations density of a same-sized copper wire (Figure 9). Southwire had a
can help to serve the load. Intercon-
nection at the distribution level in
effect creates a “backup system” that
can survive multiple transmission
or transformer outages, resulting in
N-3 or N-4 reliability (Figure 7). In
an REG system, a new urban substa-
tion would be just a simple distribu-
tion bus interconnected to the greater
grid via three HTS cables; in subur-
ban applications, new transformers
could be installed without requiring
new transmission circuits (Figure 8).
Figure 11: Jeju Island grid diagram (Courtesy of M. Park, Changwon National University, South Korea)
Figure 14: Summary of Yokohama project’s operational results (“LIN” = liquid nitrogen)
(Source: Sumitomo Electric Co.)
Project Long Island Long Island 2 HYDRA Phase 21 HYDRA Phase 3 US Navy DC Cable
Location Long Island, NY, Long Island, NY, Yonkers, NY, USA Chicago, IL, USA Florida State
USA USA University
Site Holbrook Substation Holbrook Substation Granite Hill–Rock- TBD CAPS
view Substations
Status Demonstration com- Upgrade commis- Under construction Undergoing detailed Laboratory testing2
pleted–transitioned sioned in 20132 at ConEd substation feasibility assessment
to Long Island 2
Developer AMSC AMSC AMSC AMSC Ultera
Utility/Host LIPA LIPA Consolidated Edison Commonwealth US Navy
Edison
In-Grid Start Date April 2008 2013 2014 (?) TBD TBD
End Date 2009 LIPA plans to operate No scheduled TBD TBD
See Long Island 2 system indefinitely termination date
Type (AC or DC) AC AC AC3 AC AC
Phases 3 3 3 3 1
Geometry Coaxial Coaxial Tri-axial TBD 4
Monopole5
Voltage 138 kV 138 kV 13.8 kV TBD 1 kV6
Rated Current 2400 Arms 2400 Arms 4000 Arms TBD 3 kA @ 77K
(Cable will operate (Cable will operate (96 MVA) 10 kA @ 40K
@ 800 to 900 Arms) @ 800 to 900 Arms)
Length 600 m 600 m 170 m ~3.5 miles 1 m and 30 m
Fault Current 51 kArms for 12 51 kArms for 12 40 kA for 4 cycles TBD Not tested
cycles cycles
(~140 kApeak (~140 kApeak
asymmetrical) asymmetrical)
Dielectric Design Cold dielectric Cold dielectric Cold dielectric TBD7 Cold dielectric
Dielectric Material LPP LPP Cryoflex TM
TBD CryoflexTM
HTS Material BSCCO YBCO fault current YBCO fault current YBCO fault current YBCO
w/Cu stabilizer limiting tape limiting tape limiting tape
HTS Conductor AMSC AMSC AMSC AMSC Not available
Supplier/Fabricator
AC Loss 3.5 W/m/phase @ Not available Not available TBD Not applicable
60 Hz, 2400 Arms
Cable Fabrication Nexans Nexans UlteraTM TBD8 UlteraTM
1. HYDRA Phase 1 was a 25-meter prototype that was successfully tested at Oak Ridge National Laboratory.
2. Current laboratory testing is to validate cryogenic and thermal issues. Obtaining higher voltages is next step.
3. Fault tolerant cable.
4. Expected to be tri-axial.
5. Long-term goal is a coaxial dipole construction
6. Long-term goal is +/- 5 kV DC
7. Expected to be cold dielectric
8. Expected to be competitively bid
1. Loss of 50% DOE funding led consortium partners to cancel the three-phase system project
2. AMSC, Siemens, Southern California Edison Co., Nexans, Los Alamos National Laboratory (LANL), and Texas Center for Superconduc-
tivity (TcSUH)
3. NYSERDA = NY State Energy Research & Development Agency
4. The installation at SCE was to be at 115 kV
1. Tests occurred at the Chemical Automation Design Bureau’s LH2 Test facility in Voronezh, Russia.
2. Sample cable tests were conducted in 2013 on two 30-m samples. Fabrication of two, 430-m cable lengths in cryostats was com-
pleted August 2014.
3. KIT = Karlsruhe Institute of Technology. The German Federal Ministry of Economics and Technology has given funding of $8 million for
the $18 million project.
4. FGC UES = Federal Grid Company of Unified Energy System
5. Russian Scientific R&D Cable Institute (VNIIKP), Institute of Microelectonics Nanotechnology, and the Moscow Aviation Institute (MAI).
Project funding was from the Russian Academy of Science (RAS).
6. Date cable was commissioned. Project started September 2012.
7. After 2 years of operation in the grid an evaluation will be conducted. The utility may opt for installation of additional HTS cables.
8. Go and return conductors are in a single cable.
9. Tsentralnaya substation conversion is to 330 kV AC. RP-9 substation conversion is to 220 kV AC. Converters are 12-pulse, thyristor
based.
10. Cable insulation design is suitable 20-30 kV dc, but high-voltage tests were not conducted.
11. Each of the five layers of MgB2 had a measured IC of 529 A at 20K. (Superconductor Week, June 30, 2012)
12. 80 km of wire will be produced for the project (Superconductor Week, Vol. 26, No. 20).
13. Forward (inner) conductor: 22 tapes, IC = 160 A, two layers. Reverse conductor: 19 tapes, IC = 180 A, one layer.
14. In cable section alone. Complete system had measured losses of 1.6–1.9 kW in July-August 2014, calculated as (Tout-Tin)∙cp∙dm/dt,
where Tout-Tin is the cable cryogen temperature difference between outlet and inlet and dm/dt is the measured mass flow.
15. FGC UES = Federal Grid Company of Unified Energy System.
1. System is temporarily off line. A new refrigeration system is being designed and fabricated.
2. METI = Ministry of Economy, Trade and Industry; NEDO = New Energy Development Organization.
3. Project began in 2007.
4. Pre-tested at 10 kA for 18 sec. This was a “pre-performance” test of a 30-meter cable with same design. [H. Yumura, “Update of Yoko-
hama HTS Cable Project,” preprint of ASC 2012 Proceedings, Table IV, October 9, 2012.]
Charity Mangan
Technical Assistant
Phone: 704-595-2534
E-mail: cmangan@epri.com
© 2014 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute, EPRI, and TOGETHER ... SHAPING THE FUTURE OF ELECTRICITY are
registered service marks of the Electric Power11159456
Research Institute.