Project Ampara I Road (Am-01)

Sub Contractor SJT Engineering Pvt.Ltd Pag -2


Supplier NEM Construction Pvt Ltd
Date 10.07.2020
Period 31st March 2020

SECOND INTEGRATED ROAD INVESTMENT PROGRAM


Contract Package - RDA/ADB/iROAD-2(EP)/NCB/AM-01

Previous Certified This Period Cummulative Up to date


Item Description Unit Rate
Qty Amount Qty Amount Qty Amount

Asphalt Concrete wearing course (Ex-Plant) From Plant


1 MT 7,100.00 2,711.71 19,253,141.00 403.73 2,866,483.00 3,115.44 22,119,624.00
Mahiyanganaya
Mobilization & De-mobilization of Asphalt laying machinery
2 Item 687,500.00 0.50 343,750.00 - 0.50 343,750.00
and equipment

3 Ton 1,100.00 2,711.71 2,982,881.00 403.73 444,103.00 3,115.44 3,426,984.00

4 Bitumen Spray Bowser (Dry) Mnth 215,000.00 3.00 645,000.00 - - 3.00 645,000.00

5 Selfloader One Way (Wet) Km 300.00 1,844.00 553,200.00 - - 1,844.00 553,200.00

Load 7,500.00 27.00 202,500.00 16.00 120,000.00 43.00 322,500.00


Asphalt Transport Dump truck 6 wheels (Minimum charge
6
Rs: 7,500.00 Per Trip)
Ton/Km 11.00 36,762.75 404,390.22 - - 36,762.75 404,390.22

24,384,862.22 3,430,586.00 27,815,448.22