You are on page 1of 4

Work Instruction No.

:
Asset Protection
Cathodic protection 6602

Approved by: Manager


Thermit Welding Pipeline Standards

1 PURPOSE • Ultrasonic Thickness Gauge


This Work Instruction describes the
permanent electrical connection of stranded The following materials will be required to
copper conductors to steel pipelines by complete a thermit weld:
Thermit welding. The Thermit welding • Thermit weld charge 15 grams
process shall comply with APT O&MS (maximum)
Health, Safety and Environmental
Management Systems and meet the • Charge Caps
requirements of all relevant statutory gas • Coating repair material compatible
supply legislation. with parent coating
• Cleaning agent
2 REFERENCES
6301 Coatings Procedure The following Safety Equipment will be
required, to complete a thermit weld:
6302 Testing Coatings on Steel
Pipelines to Detect Holidays • Cotton full length overalls
• Flash Goggles
3 GENERAL INFORMATION • Welding Gauntlets
Thermit welding involves a mixture of • Safety boots
powdered copper oxide and aluminium held • Fire Extinguisher
in a graphite cubicle and ignited by means of • Fire Blanket (if required)
a flint gun. The reduction of the copper oxide
• Safety Glasses
by the aluminium (an exothermic reaction)
produces molten copper as well as
aluminium oxide slag. The molten copper 3.2 Personnel
flows over the conductors in the graphite
Two persons are required, one completing
mould and fuses them to the surface.
the weld and the other maintaining a fire
Penetration of the heat generated by the watch.
molten alloy is minimised through use of a
Personnel responsible for completing the
specific power charge size of 15 grams. weld must be trained and assessed as
AS 2885 approves the use of Thermit competent, or working under the supervision
welding on licensed pressure pipelines. of competent personnel.

3.1 Tools, Materials and Equipment 4 PROCEDURE


The following tools will be required to 4.1 Work Area Safety
complete a thermit weld:
Due to the exothermic reaction of Thermit
• Graphite crucible (mould)
Welding, Hot Work permits as well as
• Medium Cut File continuous flammable gas monitoring shall
• Pliers be maintained throughout the welding
procedure.
• Electrical Knife
A fire extinguisher must be present at the
• Rat Tail File or Screwdriver
work site.
• Hammer
All flammable materials shall be removed
• Flint Gun from around the work area. Where this is
• LPG torch (as appropriate) impractical a suitable fire blanket is to be
used to cover any flammable materials.
• Wire Brush
• Securing Chain and Spring
Issue 2 October 2007 Page 1 of 4
Work Instruction No.:
Thermit Welding
6602

The work area shall be clear of obstructions than 2000kPa, and the hoop stress does not
that could inhibit the safe application of the exceed 30% of the SMYS, welding can be
Thermit weld or evacuation of the work site. carried out on material down to 4.8mm wall
thickness.
4.2 Distance from Other Welds
4.5 Cable Preparation
Thermit welds shall not be placed within
75mm of a longitudinal pipe weld or within Strip approximately 125mm of insulation from
200mm of a circumferential pipe weld. a single core multi stranded cable using an
Thermit welds shall be a minimum of 75mm electrical knife.
apart. Split the cable strands into smaller numbers
and twist the ends of the cable together using
4.3 Surface Preparation pliers, forming a group no greater than
10.5mm², this is the maximum allowable for a
Remove all coating on the structure for a 15 gram charge mould.
minimum area of 50mm x 50mm for each The weld to be completed first shall be the
Thermit weld to be applied. For pipelines, it
closest to the cable insulation. The weld is to
is best practice to remove the coating with be no closer than 40mm to the insulation.
full circumferential cuts to reduce the risk of
future coating failures.
Remove any mastic or primer with an 4.6 Mould and Cable Positioning
approved cleaning agent (such as Position the mould over the cleaned metal
environsol). Surface area must be washed surface and secure with chain and spring.
thoroughly with clean water. Dry immediately Point the cable entry slot in the mould in the
with clean rags to remove possible chemical desired direction, in the case of a pipeline
residues. this shall be longitudinally along the pipe.
 Note: Cleaning agents are Once the mould is secure, slide the prepared
generally flammable products cable into the cable opening on the base of
and appropriate care must be the mould until it touches the rear of the
taken when using them. mould, then slide the cable back
Roughen the cleaned area with a medium cut approximately 3mm to allow the molten alloy
file so as to give a rough clean finish. After to flow completely around the cable. It is
filing, the finished metal areas must not be important that the mould sits flat on the metal
cleaned using chemical cleaning agents as surface to prevent molten alloy spillage. The
chemical cleaning agent can leave a film that appropriate moulds must be used for
inhibits the welding process. attaching cables in the vertical plane,
To prevent oxidisation or contamination of likewise when attaching cables to small
the prepared surface the welding procedure piping.
should be conducted within four hours of
preparation. Should oxidisation or 4.7 Mould Loading and Firing
contamination of the prepared surface occur
the surface is to be cleaned again using a Care should be taken to ensure the mould is
medium cut file. moisture free. In the event of moisture being
present, then an appropriate method of pre
heating may be used to remove any moisture
4.4 Wall Thickness Check from the mould by the use of an LPG torch or
The thickness of the substrate to be welded similar.
shall be measured and recorded using an Place the supplied metal retaining cap into
ultrasonic thickness gauge. Generally the mould crucible. The caps conical side
welding shall not be carried out on material shall face down, as shown in Figure 1.
less than 6mm thick without qualification (in Confirm that the cap is sitting flat on the
accordance with AS 2885.1). However for bottom of the crucible chamber.
pipelines fabricated from API 5L X42 or a
lower grade steel, where the MAOP is less

Issue 2 October 2007 Page 2 of 4


Work Instruction No.:
Thermit Welding
6602

Safety flash goggles, full cotton overalls and


welding gauntlets must be worn during firing
of charge.
Finally check that the area is clear. Stand at
arms length from the mould with the flint gun
pointing into the mould exhaust port opening.
Ignite the charge with the flint gun, as shown
in Figure 3.

Placement of Metal Retainment Cap


Figure 1

Grip a 15gram charge container firmly from


the bottom with one hand. With the other
hand slowly twist the cap free from the base,
Igniting The Charge
care should be taken not to spill any charge
Figure 3
materials.
Once open, carefully dump the material into
 Caution: Hot molten alloy may
the open mould, as shown in Figure 2. Do
leak from the mould.
not tap the mould to settle the material.
If a charge fails to ignite the whole charge is
to be discarded and a new charge loaded as
previously described.
Do not look directly at the flame while the
burn continues. Once the flame has
extinguished, allow 1 minute for the alloy to
cool and remove the mould.

4.8 Weld Inspection


Check the integrity of the weld by tapping it
with a hammer. This also will clean off weld
slag. Figure 4 shows completed thermit
welds.
Pouring a 15g Charge into an Open Mould Clean the mould of slag using a screwdriver
Figure 2 or file, this is best done whilst mould is still
warm.
 Caution: The mould and slag
The ignition powder is contained in the base will be very hot following a weld
of the charge cap. To dislodge this material, and safety gauntlets and safety
hold the cap over the open mould and glasses must be worn during the
squeeze firmly. Sprinkle the ignition powder cleaning operation and integrity
evenly over the charge material. A small check.
amount of powder shall be placed on the
edge of the mould near the opening to aid
ignition.
Once the charge has been loaded close the
mould lid.
Issue 2 October 2007 Page 3 of 4
Work Instruction No.:
Thermit Welding
6602

Completed Thermit Welds


Figure 4

Do not use water to quench the completed


weld. Allow the weld to cool naturally to
ambient temperature.
If the weld fails, repeat the process, ensuring
that the cable is stripped back sufficiently to
expose new cable.
If a weld fails when tapped with the hammer,
the new weld shall be no closer than 75mm
from the failed weld.

4.9 Clean Up
Wire brush all finished welds and clear work
area of all debris and make area safe.

4.10 Coating Repair


Repair the pipeline coating in accordance
with Work Instruction 6303. Holiday test the
coating prior to burial in accordance with
Work Instruction 6302.

Issue 2 October 2007 Page 4 of 4

You might also like