Professional Documents
Culture Documents
:
Asset Protection
Cathodic protection 6602
The work area shall be clear of obstructions than 2000kPa, and the hoop stress does not
that could inhibit the safe application of the exceed 30% of the SMYS, welding can be
Thermit weld or evacuation of the work site. carried out on material down to 4.8mm wall
thickness.
4.2 Distance from Other Welds
4.5 Cable Preparation
Thermit welds shall not be placed within
75mm of a longitudinal pipe weld or within Strip approximately 125mm of insulation from
200mm of a circumferential pipe weld. a single core multi stranded cable using an
Thermit welds shall be a minimum of 75mm electrical knife.
apart. Split the cable strands into smaller numbers
and twist the ends of the cable together using
4.3 Surface Preparation pliers, forming a group no greater than
10.5mm², this is the maximum allowable for a
Remove all coating on the structure for a 15 gram charge mould.
minimum area of 50mm x 50mm for each The weld to be completed first shall be the
Thermit weld to be applied. For pipelines, it
closest to the cable insulation. The weld is to
is best practice to remove the coating with be no closer than 40mm to the insulation.
full circumferential cuts to reduce the risk of
future coating failures.
Remove any mastic or primer with an 4.6 Mould and Cable Positioning
approved cleaning agent (such as Position the mould over the cleaned metal
environsol). Surface area must be washed surface and secure with chain and spring.
thoroughly with clean water. Dry immediately Point the cable entry slot in the mould in the
with clean rags to remove possible chemical desired direction, in the case of a pipeline
residues. this shall be longitudinally along the pipe.
Note: Cleaning agents are Once the mould is secure, slide the prepared
generally flammable products cable into the cable opening on the base of
and appropriate care must be the mould until it touches the rear of the
taken when using them. mould, then slide the cable back
Roughen the cleaned area with a medium cut approximately 3mm to allow the molten alloy
file so as to give a rough clean finish. After to flow completely around the cable. It is
filing, the finished metal areas must not be important that the mould sits flat on the metal
cleaned using chemical cleaning agents as surface to prevent molten alloy spillage. The
chemical cleaning agent can leave a film that appropriate moulds must be used for
inhibits the welding process. attaching cables in the vertical plane,
To prevent oxidisation or contamination of likewise when attaching cables to small
the prepared surface the welding procedure piping.
should be conducted within four hours of
preparation. Should oxidisation or 4.7 Mould Loading and Firing
contamination of the prepared surface occur
the surface is to be cleaned again using a Care should be taken to ensure the mould is
medium cut file. moisture free. In the event of moisture being
present, then an appropriate method of pre
heating may be used to remove any moisture
4.4 Wall Thickness Check from the mould by the use of an LPG torch or
The thickness of the substrate to be welded similar.
shall be measured and recorded using an Place the supplied metal retaining cap into
ultrasonic thickness gauge. Generally the mould crucible. The caps conical side
welding shall not be carried out on material shall face down, as shown in Figure 1.
less than 6mm thick without qualification (in Confirm that the cap is sitting flat on the
accordance with AS 2885.1). However for bottom of the crucible chamber.
pipelines fabricated from API 5L X42 or a
lower grade steel, where the MAOP is less
4.9 Clean Up
Wire brush all finished welds and clear work
area of all debris and make area safe.