Professional Documents
Culture Documents
Breakthroughs In Tunneling
Denver Colorado September 09 – 11th
Geotechnical Information – Underground Construction
– All project delivery methods will be improved with lower risk for the
contractor & client = Lower prices, if a GBR or at least a GDR are
provided at the time of bid.
Tunnel Face support Methods
1. Open – No Support
2. Mechanical Support
3. Compressed Air Support
4. EPB – Earth Pressure Balance Support
5. Slurry Pressure Support
Tunnel Excavation Methods
– Conventional
• Drill and Blast (D&B)
• Mechanized excavation / Road headers
etc.
– Mechanized Boring
• Open TBM – Gripper & Open shielded
• Closed TBM – Slurry, EPB & Dual mode /
Hybrid
– Specialty
• Pipe Jacking & Microtunneling
• Immersed Tube
• Cut and Cover
Tunnel liner
– Unsealed support
• None - Rock (Bolts)
• NATM/SEM – Bolts, Ring Beam / Lattice
Girder, Mesh & Shotcrete
• Steel Liner Plate
• Ribs & Lagging
Double Shield
Gripper Rock TBM
– Cohesive Material
• Low fat clays & silts
• Slurry mode with chamber pressure
jets
– Granular Material
• Sands & gravels
• Slurry mix shield mode with air
pressure chamber
– Rock
• Slurry mode with medium jets
• Invert jet
Slurry TBM
Slurry System
Solids Removal
Extended Scope of EPB & Slurry TBM’s
Method Choice – Variable Ground
Slurry Box
Able to switch from EPB to Slurry in stages without any mechanical changes
– Variable ground conditions with high – Special Multi Mode EPB/Slurry TBM
permeability limestone and karst • EPB with screw Conveyor
formation • Slurry circuit with stone crusher
– Water pressure up to 47psi (3bar) • Slurrification box
– PPP Contract with special financial • Probing and grouting
contingency arrangements with the
client
New Innovations - Tuen Mun CLKL – Hong Kong Dual Sized Slurry TBM
– Long 6 mile undersea crossing – Dual Sized Slurry TBM 57.7ft and reduced
57.7ft ( Worlds Largest) Slurry to 46ft
TBM
– Robotic cutter inspection and
– Maximum 120psi (8Bar) water replacement over 60% of face
head
– Hyperbaric interventions
– Little Geotechnical
information- forecast to be
Alluvium with weathered
granite , possibility of strong
granite
– DB Contract with TBM
specified and special pay
conditions based on ground
conditions
Cutter Changes TBM Hyperbaric Intervention under Saturation
Real Time Cutter & Geotechnical Monitoring
Cutter Changing Robot
Tunnel Cross Passages
56 Cross Passages (100m spacing - 328ft)
with 44 by Slurry Pipe Jacking
Research and Development
– NeTTUN 2012 -17 financed by an EU grant carried out research on improving
TBM’s and tunnel related issues
– In Rock Open Gripper TBM’s with minimal tunnel support give the highest
performance for excavation rates – Are susceptible to unanticipated ground
changes including fault zones and water flows
– Rock open TBM’s should have extensive forward probing and grouting capability
– Uncertainty in the ground conditions increases risk of delay and higher costs
– Use of Closed Shielded TBM’s with RC bolted and gasketed segmental liner
rings reduces risk but increases cost due to slower production and higher cost
of materials and equipment.
– Hybrid / Multi Mode TBM’s with robotics and ground sensing equipment is a
reality for variable & mixed ground conditions
Thank You