Quartz School for IPM Well Site Supervisors

Module – 11
Well Completions

Schlumberger Private
Section – 1
Introduction to
Well Completions

1/49
Introduction to Well Completion
Completion – Definition

Definition:
 The methodology and technology required to produce

Schlumberger Private
recoverable reserves (reservoir to surface).

Process:
 The design, selection and installation of tubulars, tools and
equipment, located in the wellbore, for the purpose of
conveying, pumping or controlling production (or injection)
fluids.

Quartz School for IPM Well Site Supervisors


C. Alvarez 2/49
Introduction to Well Completion
Completion History / Evolution
 1300 Marco Polo – wells dug at Caspian Sea
 1814 First naturally flowing oil well – 475 ft

Schlumberger Private
 1822 Rudimentary art of drilling established
 1905 Casing cemented
 1911 First gas lift device
 1913 First dual completion
 1926 First electric submersible pump
 1933 First gun perforation job
 1963 Commercial coiled tubing services introduced

Quartz School for IPM Well Site Supervisors


C. Alvarez 3/49
Introduction to Well Completion

Well Completions – Evolution

Over the last years Well Completion has been affected by:

Schlumberger Private
1. Philosophy

2. Technology

3. Applications

4. Safety

5. Contingency
Quartz School for IPM Well Site Supervisors
C. Alvarez 4/49
C. Alvarez
US$ x 1000

100
200
300
400
M
ob 500
C /D
as em
Dr ing ob
illi
n
Dr g R
illi
ng ig
C Flu
om
id
Lo pl
et s
gg io
in n
Di
re g Tu
ct & bu
Bit io Pe la
s& na rfo rs
l &
C C Se ra ti Eq
em o r rv ng
en ing ic ui
pm
Su es

Quartz School for IPM Well Site Supervisors


Completion Cost

pe tin en
Sit rvis g t
e io
P n
Operational Phase/Cost Category

Re rep
nt a
Pe a l E ra ti
rso q on
u
Introduction to Well Completion

O nn ip m
th e
er l L en
C og t
Completion cost (relative) example for a 10,000 ft land well

am ist
p ic
s
5/49

Schlumberger Private
Introduction to Well Completion
Completion Design Factors
Well Completion Design Factors include:
1. Casing protection
 e.g., protection against erosion, corrosion

Schlumberger Private
2. Tubing string removal
 e.g., for replacement or workover for the live of the well

3. Safety or contingency
 e.g., requirements for safety valves and well kill

4. Production control
 e.g., components providing flexibility and control of production
(nipples, profiles and sliding sleeves
Quartz School for IPM Well Site Supervisors
C. Alvarez 6/49
Introduction to Well Completion
Basic Production Configurations
Most Well Completions are based on the following configurations:
1. Reservoir interface
 Openhole
 Casing production

Schlumberger Private
 Liner production
 Gravel pack wellbore
 Deviation
2. Production conduit
 Suspended tubing
 Basic packer
 Packer and tailpipe
 Packer with additional safety and production devices
 Multiple Conduits

Quartz School for IPM Well Site Supervisors


C. Alvarez 7/49
Introduction to Well Completion
Open Hole Production

Key Features:

 No downhole flow control or isolation

Schlumberger Private
 Producing formation is unsupported

 Casing provides isolation between


shallower formations

Quartz School for IPM Well Site Supervisors


C. Alvarez 8/49
Introduction to Well Completion
Casing Production

Key Features:

 No downhole flow control or isolation

Schlumberger Private
 Casing provides isolation between
shallower formations with potential for
remedial work to isolate sections of
perforated interval

Quartz School for IPM Well Site Supervisors


C. Alvarez 9/49
Introduction to Well Completion
Liner Production

Key Features:

 Similar to casing production but with

Schlumberger Private
smaller (and shorter) tubulars set
through the reservoir

Quartz School for IPM Well Site Supervisors


C. Alvarez 10/49
Introduction to Well Completion
Gravel Pack Wellbore

Key Features:

Schlumberger Private
 Special application - requirement
determined by formation type

 May require special operation (under


reaming) during well construction
phase

Quartz School for IPM Well Site Supervisors


C. Alvarez 11/49
Introduction to Well Completion
Completions with Screens for Sand Control

Schlumberger Private
Wire wrapped screen Prepacked screen

Quartz School for IPM Well Site Supervisors


C. Alvarez 12/49
Introduction to Well Completion
Simple Tubing Completion

Key features:

 Circulation capability (well kill or kick-off)

Schlumberger Private
 Improves hydraulic performance

 Limited protection for casing

Quartz School for IPM Well Site Supervisors


C. Alvarez 13/49
Introduction to Well Completion
Basic Packer Completion
Key features:

 Tubing Anchoring

Schlumberger Private
 Isolation of Production Interval

 Circulation capability (determined by design and


setting of packer)

 Casing string protected from fluid and pressure


effects

Quartz School for IPM Well Site Supervisors


C. Alvarez 14/49
Introduction to Well Completion
Packer with Tailpipe

Key features

Schlumberger Private
 Additional flexibility for downhole
production (flow)control, e.g., plugs

 Facility for downhole instruments (gauges)

Quartz School for IPM Well Site Supervisors


C. Alvarez 15/49
Introduction to Well Completion
Enhanced Packer Installation

Key features

 Improved flexibility for downhole production

Schlumberger Private
control, e.g., plugs above or below packer

 Circulation capability independent of


packer

 Safety facility (SSSV)

Quartz School for IPM Well Site Supervisors


C. Alvarez 16/49
Introduction to Well Completion
Examples of Well Completion Configurations:

1. Single zone completions

Schlumberger Private
2. Multiple zone completions

3. Liner completions

4. Special completions
 Sand control
 Inhibitor injection
 Water flooding
 Thermal
 Remedial (scab liner)
Quartz School for IPM Well Site Supervisors
C. Alvarez 17/49
Introduction to Well Completion
Single Zone – Retrievable Packer

Key Features:

 Hydraulically set

Schlumberger Private
 Tail-pipe facility for pressure and temperature gauges

 Fully retrievable completion

 Packer can be set with well flanged up

 Thru-tubing perforation possible where size permits

Quartz School for IPM Well Site Supervisors


C. Alvarez 18/49
Introduction to Well Completion
Single Zone – Seal-Bore Packer

Key Features:

 Seal-bore packer set on electric-line or tubing

Schlumberger Private
 On-off connector and tubing anchor allows tubing to
be retrieved

 Tailpipe plugged and left in wellbore or retrieved


with production tubing

Quartz School for IPM Well Site Supervisors


C. Alvarez 19/49
Introduction to Well Completion
Single Zone – Packer and Tailpipe

Key Features:

 Tailpipe plugged and left in wellbore when production

Schlumberger Private
tubing is retrieved

 Permits safe thru-tubing perforating

 Block and kill system facilitates the killing of high-pressure,


high-flow rate wells

Quartz School for IPM Well Site Supervisors


C. Alvarez 20/49
Introduction to Well Completion
Multiple Zones – 2 Zones 1 Packer

Key Features:

 Separate or commingled production through single

Schlumberger Private
tubing string

 Blast joint protection across upper interval

 On-off connector and tubing anchor permits tubing


retrieval with lower interval isolated

Quartz School for IPM Well Site Supervisors


C. Alvarez 21/49
Introduction to Well Completion
Multiple Zones – Two Zones, Two Packers
Key Features:

 Independent production through dual tubing strings

Schlumberger Private
 Blast joint protection across upper interval

 Both packers retrievable

 Tailpipe instrument facility on both strings

 Thru-tubing perforation of lower zone possible

Quartz School for IPM Well Site Supervisors


C. Alvarez 22/49
Introduction to Well Completion
Liner CSR
Key Features:

 Most simple liner hook-up

Schlumberger Private
 CSR replaces packer

 Fluid circulation through sliding sleeve above the


liner hanger

 Tailpipe retrieved with production tubing

Quartz School for IPM Well Site Supervisors


C. Alvarez 23/49
Introduction to Well Completion
Monobore Completion

Key Features:
Safety valve

Schlumberger Private
 Designed to meet criteria for:
 appropriate production rates
 flexibility/contingency
 safety
 monitoring (reservoir management)
 longevity Packer/hanger
assembly

Liner
Quartz School for IPM Well Site Supervisors
C. Alvarez 24/49
Introduction to Well Completion
Multi-Zone Completion
Hydraulic Control Line for
the TRSCSSV

Tubing Retreivable Surface Example of a Multi Zone Completion


Controled Subsurface Safety
Valve (TRSCSSV) using a Standard Configuration for
Hydraulic Control Line for
the ASV each Zone
(this can be repeated for any number of zones)

Schlumberger Private
Annular Safety Valve (ASV)
System with Wet Disconnect

10 3/4 Casing

Gas Lift Mandrel

5-1/2 Production Tubing


Production Packer w/
TEC bypass
Tubing Encased
Conductor (TEC)

Flow Control Device w/


Isolation Cross Coupling Clamp Plug
Integral Pressure/
Packer w/ TEC
Temperature sensor
feedthru Venturi Flowmeter 9-5/8 Liner

Zone 1 Zone 2

Quartz School for IPM Well Site Supervisors


C. Alvarez 25/49
Schlumberger Private
Completions for Well Profile Type

26/49
Introduction to Well Completion

1. Completions in Vertical Wells

2. Completions in Deviated Wells

Schlumberger Private
3. Horizontal Wells Completions

4. Extended Reach Well Profile

5. Multilateral Wells

6. Intelligent Completions

Quartz School for IPM Well Site Supervisors


C. Alvarez 27/49
Introduction to Well Completion
Completions in Vertical Wellbore Profiles

Vertical wellbore
Cap rock

Schlumberger Private
1. No great productivity benefit

2. May catch unwanted water or gas Basement

3. Preferred for fracturing

Quartz School for IPM Well Site Supervisors


C. Alvarez 28/49
Introduction to Well Completion
Completions in Vertical Wellbore Profiles

Open Hole (Barefoot) Completions


Options:

Schlumberger Private
Cap Rock
1. Conductor with open hole
 No ground water protection

2. Casing string with open hole Reservoir

 Provides top-hole stability

3. Liner with open hole Open hole Gravel Pack


Completion Completion
 Cross-flow protection

Quartz School for IPM Well Site Supervisors


C. Alvarez 29/49
Introduction to Well Completion
Completions in Vertical Wellbore Profiles

Perforated Completions
Options: Cap Rock

Schlumberger Private
1. Casing or liner
 Without production tubing
Reservoir
2. Casing or liner with production tubing
 Production through tubing or annulus
Cemented Cemented
3. Casing or liner with tubing and packer casing liner

 Production through tubing enables flow


control

Quartz School for IPM Well Site Supervisors


C. Alvarez 30/49
Introduction to Well Completion
Completions in Deviated Wellbore Profiles

Key Features: Cap rock

 Increased productivity

Schlumberger Private
especially in thin reservoirs
 Extends reach within reservoir
Reservoir
 0 – 90 degrees
 Issues with Wireline/Slickline
Basement
work beyond 65 degrees

Quartz School for IPM Well Site Supervisors


C. Alvarez 31/49
Introduction to Well Completion
Completions in Horizontal Wellbore Profiles
Horizontal wellbore
Features:
 Significant increase in productivity

Schlumberger Private
 Reduced influence of skin
 Reduced influence on coning
Cap rock
Issues:
 Depth Control
 Zonal Isolation
 Flow Control
Water zone

Quartz School for IPM Well Site Supervisors


C. Alvarez 32/49
Introduction to Well Completion
Completions in Extended Reach Wellbore Profiles

Definition:

Schlumberger Private
 A well in which the ratio of measured depth (MD) to true vertical
depth (TVD) is greater than 2.0
 A mega-reach well has a MD/TVD ratio of 3.0 or greater

Examples of Extended Reach Well Profiles:


 Hibernia - 2.05 Ratio
 BP Wytch Farm - 5.4 Ratio

Quartz School for IPM Well Site Supervisors


C. Alvarez 33/49
Introduction to Well Completion
Examples of Extended Reach Wells

1000
Wytch Farm

Schlumberger Private
Oman
Angola Argentina
Foinhaven Gulfaks
2000 S. Italy
Valhal
Prudhoe
Dan Statfjord
3000

Dunlin Hibernia
Magnus
Alwyn
4000
Guida

Colombia
5000
1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

Quartz School for IPM Well Site Supervisors


C. Alvarez 34/49
Introduction to Well Completion
Completions in Multi-Lateral Well Profiles
Multi Lateral Well:
 A well in which there is more than one horizontal or near horizontal
lateral well drilled from a single main bore and connected back to the
same main bore.

Schlumberger Private
Quartz School for IPM Well Site Supervisors
C. Alvarez 35/49
Introduction to Well Completion
Typical ML Well Trajectories

Schlumberger Private
Multi branched Forked Laterals in Vertical Hole

Stacked Laterals Laterals in Horizontal Dual Opposing Laterals

Quartz School for IPM Well Site Supervisors


C. Alvarez 36/49
Introduction to Well Completion
Multilateral Nomenclature

Schlumberger Private
Junction

Mainbore Lateral

Quartz School for IPM Well Site Supervisors


C. Alvarez 37/49
Introduction to Well Completion
First Multilateral Well Drilled

The first Multilateral well was drilled in Russia in 1953

Well Data:

Schlumberger Private
 9 lateral branches from the main bore
 Increased exposure to the pay zone by 5.5 times
 Increased production by 17 times
 Only increased capitol expenditures by 1.5 times

Quartz School for IPM Well Site Supervisors


C. Alvarez 38/49
Introduction to Well Completion
Completions in Multi-Lateral Well Profiles
Example of ML well with two Laterals (Not two wells in one):
Cost
 To be economical the Capex should be no greater than 50%

Schlumberger Private
additional for each lateral

Production
 Will probably be between 30-60% improvement over a horizontal
well, not double

Economics
 Should improve by approximately 40%

Quartz School for IPM Well Site Supervisors


C. Alvarez 39/49
Introduction to Well Completion
Completions in Multi-Lateral Well Profiles
Technical Advantages:
 Increased reservoir exposure
 Increase in connectivity to the reservoir, to reduce water

Schlumberger Private
coning, gas coning, and sanding potential
 More efficient exploitation of complex reservoirs
Economic Advantages:
 No added cost for the main bore and surface equipment
 No additional slot use on an offshore platform
 Smaller platform due to decreased surface equipment
 Increase in recoverable reserves

Quartz School for IPM Well Site Supervisors


C. Alvarez 40/49
Introduction to Well Completion
Completions in Multi-Lateral Well Profiles
Technical Disadvantages:
 Well intervention is more complicated
 Reservoir monitoring is more complicated

Schlumberger Private
 Increased drilling risks
 Increased problems to control the well while creating
additional laterals
 Increased debris
Economic Disadvantages:
 Increased risk of losing the main bore and lower laterals
 Dependent on new technology

Quartz School for IPM Well Site Supervisors


C. Alvarez 41/49
Introduction to Well Completion
Completions in Multi-Lateral Well Profiles

Technology Advancement of Multi Laterals


The objective of the “TAML”
TAML” consortium is to promote the

Schlumberger Private
efficient development and utilization of multilaterals within the
international petroleum industry, through dialogue; information
and technology exchange; and collective sponsorship.

“TAML” Members

Schlumberger, Baker Hughes, BP-Amoco, Chevron, Mobil, Norsk


Hydro, Phillips, Saga, Shell, Smith, Sperry Sun, Statoil, Texaco,
TIW,Total, Weatherford, Well Service Technology

Quartz School for IPM Well Site Supervisors


C. Alvarez 42/49
Introduction to Well Completion
TAML Classification (Levels) of Multilateral Wells

• Open hole Main bore • Cased Main bore • Cased Main bore
• Open hole Lateral • Open hole Lateral • Mechanical Integrity
at Junction

Schlumberger Private
RapidExclude Animation

• Cased Main bore • Cased Main bore • Cased Main bore


• Cemented Junction • Mechanical and • Mechanical and
Hydraulic Integrity Hydraulic Integrity
at Junction at Junction
through Casing through Junction
Packers construction

RapidSeal Animation
Quartz School for IPM Well Site Supervisors
C. Alvarez 43/49
Introduction to Well Completion
Intelligent Completions
Intelligent Wells = Reservoir Monitoring & Control, RMC
Known in Schlumberger as “RMC Completion”
 RMC stands for: “Reservoir Monitoring & Control”

Schlumberger Private
 Referred to by the industry as: “Intelligent Completions”

What is “RMC” or “Intelligent” Completion?

A completion system which can measure and selectively control flow


into or out from a specific wellbore or interval.

 Two Key Words:


 Measure (or Monitoring)
 Control
Quartz School for IPM Well Site Supervisors
C. Alvarez 44/49
Introduction to Well Completion
Intelligent Completions
Reservoir Monitoring Control, RMC

Current Scenario
 Water Cut interferes with Oil Production

Schlumberger Private
Gas
 Water and/or Gas
Production will limit total
Oil Recoveries to a Oil
maximum of 35% of
Oil in Place
Water

Quartz School for IPM Well Site Supervisors


C. Alvarez 45/49
Introduction to Well Completion
Intelligent Completions
Reservoir Monitoring Control, RMC

Schlumberger Private
Quartz School for IPM Well Site Supervisors
C. Alvarez 46/49
Introduction to Well Completion
Intelligent Completions
Reservoir Monitoring Control, RMC

Schlumberger Private
Quartz School for IPM Well Site Supervisors
C. Alvarez 47/49
Introduction to Well Completion
Intelligent Completions
Reservoir Monitoring Control, RMC
System Overview
Data Transmission
Reservoir
Management Data Acquisition

Schlumberger Private
Power & Communication

Permanent Gauges
Flow Control Valves

Quartz School for IPM Well Site Supervisors


C. Alvarez 48/49
Introduction to Well Completion
Intelligent Completions
Reservoir Monitoring Control, RMC
Basic Requirements
A completion system must provide a means of oil or gas
production which is:

Schlumberger Private
1. Safe
 e.g., well security, environment

2. Efficient
 e.g., production objectives

3. Economic
 e.g., cost vs. revenue
Quartz School for IPM Well Site Supervisors
C. Alvarez 49/49