Structures Daily Progress from 16-08-2019 to31-08-2019
Date Description of Work Chainage Unit Quantity Remarks
8/16/2019 Return wall shuttering 66500
8/17/2019 Return wall casting 66500 Cum 5.85
8/19/2019 Return wall casting 66500 Cum 3.75
8/24/2019 Return wall casting 66500 Cum 8.217
8/24/2019 RR Machernery work 26576 Cum 4.095
8/25/2019 Return wall shuttering 66500
8/25/2019 Return wall casting 66500 Cum 1.47
8/25/2019 Return wall casting 66500 Cum 5.25
8/25/2019 RR Machernery work 26576 Cum 13.65
8/26/2019 RR Machernery work 26576 Cum 13.65
8/27/2019 Return wall shuttering 66500
8/27/2019 RR Machernery work 26576 Cum 4.095
8/28/2019 Return wall casting 66500 Cum 6.615
8/28/2019 RR Machernery work 26576 Cum 4.095
8/29/2019 Return wall casting second lift 66500 Cum 5.512
8/29/2019 RR Machernery work 26576 Cum 4.095
8/30/2019 Return wall casting second lift 66500 Cum 4.41

For DRB Infrastructure Pvt Ltd

Authorized Signature
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Highway Daily Progress from 16-08-2019 to 31-08-2019
Date Description of Work Chainage Unit Quantity Remarks
8/24/2019 Boulder breaking Crusher
8/24/2019 In quary boulder loading 52km Trips 6
8/27/2019 Boulder collecting in quary
8/28/2019 Boulder collecting and loading 52km Trips 7
8/29/2019 Boulder collecting and loading 52km Trips 10
8/29/2019 Boulder shifting in rega bridge 26km Cum 25
8/30/2019 Boulder collecting and loading 52km Trips 16

For DRB Infrastructure Pvt Ltd

Authorized Signature
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Rain Details
Time
Date Description Cm Remarks
Starting Closing
8/16/2019 Rain 12PM 4pm
Rain 8.0pm 3.0am
8/17/2019 Sunney
8/18/2019 Sunney
8/19/2019 Sunney
8/20/2019 Rain 11.0am 3.0pm
8/21/2019 Sunney
8/22/2019 Rain 3pm 6pm
8/23/2019 Sunney
8/24/2019 Sunney
8/25/2019 Cloudy
8/26/2019 Cloudy
8/27/2019 Cloudy
8/28/2019 Sunney
8/29/2019 Rain 10.30am 2.45pm
8/30/2019 sunny
8/30/2019 Rain 7.0pm 4.0am
8/31/2019 Rain 4.0pm 7.0pm
8/31/2019 Rain 3.30pm 6.30am
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of Structures
Sl.No Description of Work Chainage Span /
Length(Mtr)
1 Culverts 38+300 CD
2 Culverts 38+700 CD
3 Culverts 40+200 CD
4 Culverts 41+900 CD
5 Culverts 43+300 CD
6 Culverts 44+500 CD
7 Culverts 45+000 CD
8 Culverts 45+100 CD
9 Culverts 45+400 CD
10 Culverts 46+500 CD
11 Culverts 46+600 CD
12 Culverts 46+850 Wingwall
13 Culverts 49+060 CD
14 Culverts 52+050 CD
15 Culverts 53+300 CD
16 Culverts 54+500 CD
17 Culverts 55+100 CD
18 Culverts 55+400 CD
19 Culverts 55+600 CD
20 Culverts 56+200 CD
21 Culverts 58+300 CD
22 Culverts 58+600 CD
23 Culverts 59+600 CD
24 Culverts 61+900 CD
25 Culverts 66+800 CD
26 Culverts 71+500 CD
re Pvt Ltd. DRB Infrastr
Chayangtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Se
Structures Work Comp
Remarks Sl.No Description of Work

Completed 1 Weidening
Completed 2
Completed 3
Completed 4
Completed 5
Completed 6
Completed 7
Completed 8
Completed 9
Completed 10
Completed 11
Completed 12
Completed 13
Completed 14
Completed 15
Completed 16
Completed 17
Completed 18
Completed 19
Completed 20
Completed 21
Completed 22
Completed 23
Completed 24
Completed 25
Completed 26
DRB Infrastructure Pvt Ltd.
Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of Cutting
Chainage
Length (Mtr) Remarks
From To
37+600 37+750 150 Completed
39+500 39+580 80 Completed
43+900 44+100 200 Completed
44+400 45+250 850 Completed
45+800 45+870 70 Completed
47+450 47+630 180 Completed
49+160 49+320 180 Completed
51+200 51+320 120 Completed
52+000 52+300 300 Completed
52+796 52+836 40 Completed
52+876 52+926 50 Completed
53+010 53+160 150 Completed
53+160 53+180 20 Completed
53+200 53+350 150 Completed
54+370 54+460 90 Completed
54+750 54+820 70 Completed
55+000 55+090 90 Completed
55+090 55+550 460 Completed
58+995 59+005 10 Completed
59+228 59+298 70 Completed
59+600 59+680 80 Completed
60+209 60+279 70 Completed
60+339 60+369 30 Completed
61+001 61+061 60 Completed
61+111 61+256 145 Completed
64+140 64+240 100 Completed
3815
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of GSB
Chainage
Sl.No Description of Work Length (Mtr)
From To
1 GSB 37+600 37+750 150
2 39+100 39+180 80
3 43+900 44+100 200
4 44+400 45+250 850
5 45+800 45+870 70
6 47+450 47+630 180
7 49+160 49+320 180
8 51+200 51+320 120
9 52+000 52+300 300
10 52+796 52+836 40
11 52+876 52+926 50
12 53+010 53+160 150
13 53+160 53+180 20
14 53+200 53+350 150
15 54+370 54+460 90
16 54+750 54+820 70
17 55+000 55+090 90
18 55+090 55+550 460
19 58+995 59+005 10
20 59+228 59+298 70
21 59+600 59+680 80
22 60+209 60+279 70
23 60+339 60+369 30
24 61+001 61+061 60
25 61+111 61+256 145
26 64+140 64+240 100
3815
Pvt Ltd. DRB Infrastructure
yangtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Seppa - Cha
GSB Work Completed of W
Chainage
Remarks Sl.No Description of Work
From
Completed 1 WBM 37+600
Completed 2 35+790
Completed 3 37+320
Completed 4 38+030
Completed 5 39+600
Completed 6 40+120
Completed 7 44+100
Completed 8 47+260
Completed 9 48+800
Completed 10 49+170
Completed 11 51+800
Completed 12 53+210
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
DRB Infrastructure Pvt Ltd.
Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of WBM
Chainage
Length (Mtr) Remarks
To
37+750 150 Completed
37+320 1530 Completed
38+030 710 Completed
40+120 2090 Completed
39+710 110 Completed
41+280 1160 Completed
45+200 1100 Completed
47+390 130 Completed
48+920 120 Completed
49+450 280 Completed
52+260 460 Completed
53+450 240 Completed

7930
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work In Progress of Structures
Sl.No Description of Work Chainage Span /
Length(Mtr)
1 Culverts 43+350 6Mtr
2 Culverts 61+700 CD
3 Culverts 70+700 4Mtr
4 Culverts 73+100 CD
5 Culverts 76+100 4Mtr
6 Breastwall 48+900 to 48+945 45
7 Breastwall 65+900 to 65+910 10
8 Culverts 65+900 CD
9 R/Wall 65+000 to 65+030 30
10
re Pvt Ltd. DRB Infrastr
hayangtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Se
Structures Work In Pro
Remarks Sl.No Description of Work

In Progress 1 Weidening
In Progress 2
In Progress 3
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
DRB Infrastructure Pvt Ltd.
Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work In Progress of Cutting
Chainage
Length (Mtr) Remarks
From To
59+228 59+298 70 In Progress
61+111 61+256 145 In Progress
64+420 64+600 180 In Progress

325
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of GSB
Chainage
Sl.No Description of Work Length (Mtr)
From To
1 GSB 39+100 39+180 80
2 43+900 44+100 200
3 44+400 45+250 850
4 45+800 45+870 70
5 47+500 47+630 130
6 51+200 51+320 120
7 52+000 52+300 300
8 52+796 52+836 40
9 52+876 52+926 50
10 53+056 53+110 54
11 53+160 53+180 20
12 54+370 54+460 90
13 55+089 55+119 30
14 55+285 55+355 70
15 58+995 59+005 10
16 59+228 59+298 70
17 60+209 60+279 70
18 60+339 60+369 30
19 61+001 61+061 60
20 61+111 61+256 145
2489
Pvt Ltd. DRB Infrastructure
yangtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Seppa - Cha
GSB Work Completed of W
Chainage
Remarks Sl.No Description of Work
From
Completed 1 WBM 35+790
Completed 2 37+320
Completed 3 38+030
Completed 4 39+600
Completed 5 40+120
Completed 6 44+100
Completed 7 47+260
Completed 8 48+800
Completed 9 49+170
Completed 10 51+800
Completed 11 53+210
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
DRB Infrastructure Pvt Ltd.
Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Work Completed of WBM
Chainage
Length (Mtr) Remarks
To
37+320 1530 Completed
38+030 710 Completed
40+120 2090 Completed
39+710 110 Completed
41+280 1160 Completed
45+200 1100 Completed
47+390 130 Completed
48+920 120 Completed
49+450 280 Completed
52+260 460 Completed
53+450 240 Completed

7930
DRB INFRA PVT LTD
Construction & Improvement Of Seppa - Chayangtajo Road(81.00KM) Under NEC
List Of Balance Widening Chainages Given By PWD
Sl.No Chainage Length Remarks
From To
1 28425 28435 10
2 29890 29910 20
3 29910 29930 20
4 29930 29950 20
5 29950 29970 20
6 31800 31820 20
7 31820 31840 20
8 31840 31860 20
9 31860 31880 20
10 31880 31900 20
11 31900 31920 20
12 31920 31940 20
13 32690 32710 20
14 32710 32730 20
15 32730 32750 20
16 32750 32770 20
17 32770 32790 20
18 32790 32800 10
19 32850 32870 20
20 32870 32890 20
21 32890 32910 20
22 33400 33420 20
23 33420 33440 20
24 33440 33460 20
25 33460 33480 20
26 33480 33500 20
27 33500 33520 20
28 33520 33540 20
29 44630 44650 20
30 44650 44670 20
31 44670 44690 20
32 52820 52840 20
33 52840 52860 20
34 64340 64360 20
660
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Balance Work of Structures
Sl.No Description of Work Chainage Span / Length(Mtr) Remarks

1 Culverts 29500 CD
2 Culverts 30600 CD
3 Culverts 31400 CD
4 Culverts 32100 2Mtr
5 Culverts 32800 CD
6 Breastwall 33700 CD
7 Breastwall 28900 26
8 R/Wall 30200 17
9 R/Wall 31400 16
10 Breastwall 34800 105
11 R/Wall 38000 17
12 R/Wall 38300 10
13 R/Wall 39100 7
14 R/Wall 40500 30
15 R/Wall 49000 5
16 R/Wall 58000 14
17 R/Wall 61000 30
18 R/Wall 61200 20
19 R/Wall 62300 10
20 R/Wall 63000 20
21 R/Wall 65000 30
22 R/Wall 69100 20
23 R/Wall 73100 15
24 R/Wall 73400 30
25 R/Wall 75000 30
26 R/Wall 75850 30
27 R/Wall 77000 20
DRB Infrastructure Pvt Ltd.
Project : Construction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Balance Work of GSB
Chainage
Sl.No Description of Work Length (Mtr)
From To
1 GSB 28425 28435 10
2 29890 29910 20
3 29910 29930 20
4 29930 29950 20
5 29950 29970 20
6 31800 31820 20
7 31820 31840 20
8 31840 31860 20
9 31860 31880 20
10 31880 31900 20
11 31900 31920 20
12 31920 31940 20
13 32690 32710 20
14 32710 32730 20
15 32730 32750 20
16 32750 32770 20
17 32770 32790 20
18 32790 32800 10
19 32850 32870 20
20 32870 32890 20
21 32890 32910 20
22 33400 33420 20
23 33420 33440 20
24 33440 33460 20
25 33460 33480 20
26 33480 33500 20
27 33500 33520 20
28 33520 33540 20
29 44630 44650 20
30 44650 44670 20
31 44670 44690 20
32 52820 52840 20
33 52840 52860 20
34 64340 64360 20
660
t Ltd. DRB Infrastructure Pvt Ltd.
gtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Seppa - Chayangtajo R
Balance Work of WBM
Chainage
Remarks Sl.No Description of Work
From To
1 WBM 28425 28435
2 29890 29910
3 29910 29930
4 29930 29950
5 29950 29970
6 31800 31820
7 31820 31840
8 31840 31860
9 31860 31880
10 31880 31900
11 31900 31920
12 31920 31940
13 32690 32710
14 32710 32730
15 32730 32750
16 32750 32770
17 32770 32790
18 32790 32800
19 32850 32870
20 32870 32890
21 32890 32910
22 33400 33420
23 33420 33440
24 33440 33460
25 33460 33480
26 33480 33500
27 33500 33520
28 33520 33540
29 44630 44650
30 44650 44670
31 44670 44690
32 52820 52840
33 52840 52860
34 64340 64360
tructure Pvt Ltd. DRB Infrastruc
Seppa - Chayangtajo Road (81.00 KM Under NEC.) Project : Construction & Improvement of Sepp
e Work of WBM Balance W
Length (Mtr) Remarks Sl.No Description of Work

10 1 BT
20 2
20 3
20 4
20 5
20 6
20 7
20 8
20 9
20 10
20 11
20
20
20
20
20
20
10
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
660
DRB Infrastructure Pvt Ltd.
nstruction & Improvement of Seppa - Chayangtajo Road (81.00 KM Under NEC.)
Balance Work of BT
Chainage
Length (Mtr) Remarks
From To
26500 29813 3313
31285 36500 5215
37950 42686 4736
43517 43858 341
47412 47662 250
48745 49373 628
49669 53400 3731
53750 67982 14232
68582 73850 5268
74800 75843 1043
77323 79500 2177