The document describes two wastewater treatment system installations. The first at a public school in Oyster Bay, Eastern Cape included a Clarus Fusion ZF4000 system, UV disinfection, and an underground holding tank and pump. Treated effluent was used to irrigate a vegetable garden. The installation took one week. The second was at a school in Bloemfontein and included two Clarus Fusion ZF4000 systems, sewage pumping, pre-screening, UV and chlorine disinfection, lifting stations, three 10kl holding tanks, transfer pumps, and air pumps. Treated effluent was used to irrigate sports fields, and the installation took two weeks.
The document describes two wastewater treatment system installations. The first at a public school in Oyster Bay, Eastern Cape included a Clarus Fusion ZF4000 system, UV disinfection, and an underground holding tank and pump. Treated effluent was used to irrigate a vegetable garden. The installation took one week. The second was at a school in Bloemfontein and included two Clarus Fusion ZF4000 systems, sewage pumping, pre-screening, UV and chlorine disinfection, lifting stations, three 10kl holding tanks, transfer pumps, and air pumps. Treated effluent was used to irrigate sports fields, and the installation took two weeks.
The document describes two wastewater treatment system installations. The first at a public school in Oyster Bay, Eastern Cape included a Clarus Fusion ZF4000 system, UV disinfection, and an underground holding tank and pump. Treated effluent was used to irrigate a vegetable garden. The installation took one week. The second was at a school in Bloemfontein and included two Clarus Fusion ZF4000 systems, sewage pumping, pre-screening, UV and chlorine disinfection, lifting stations, three 10kl holding tanks, transfer pumps, and air pumps. Treated effluent was used to irrigate sports fields, and the installation took two weeks.
Components: Clarus Fusion ZF4000 Treated effluent is used for irrigating vegetable garden UV For disinfection Underground holding tank and pump
Installation time: one week
Curro, Bloemfontein Components: Clarus Fusion ZF4000 x 2 Zoeller U282, pump sewage from existing conservancy tank Pre-Screen (inorganics) UV and chlorine (disinfection) Lifting station for effluent with Zoeller pump 3 x 10kl holding tanks for treated effluent Transfer pump to irrigation tanks Air pumps x 3 for keeping treated effluent fresh in holding tanks
Installation time: two weeks
Treated effluent is used for irrigating sports fields