Memo
Scope location
Plant : HPU
Area - 4
Unit - 152
Elevation : 1.5 mtr from ground level.
WP holder
No of valves : 2
Size of the valves : 2" x 600#
Scope of work :
Remove insrumentation
Remove the valve
Replace the valve
Reconnect Instrumentation.
Freeze
** Frozen by Multi change **
No of valves : 2
Size of the valves : 2" x 600#
Scope of work :
Remove insrumentation
Remove the valve
Replace the valve
Reconnect Instrumentation.
No. Job description / resources Job no. Lib no. Job discipline / circumstances
001 OBTAIN WORK PERMIT _AH0 D818 OPERATIONS
Refer to SATORP Work Permit System Procedure to apply a work permit and detailed job safety analysis JSA.
Conduct Tool Box talk in Work location, prior to start the job.
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
DISCONNECT/REMOVE ASSOCIATED
002 _AGY D009 INSTRUMENTATION
INSTRUMENTATION
Disconnect the associated instrument prior to the replacement of isolation valve
152 PI 0040
Dis connect the pressure gauge 152-PI-0040 with diaphragm and capillary,
BOOM
TRUCK/HIAB TR-2 Lifting & Transp Exec. BLOCK-C/4_AYTB
OPERATOR
FORKLIFT
TR-2 Lifting & Transp Exec. BLOCK-C/4_AYTB
OPERATOR
005 REPLACEMENT OF VALVE _AH1 H247 VALVE
Replace the 051-PI-0040 isolation valves with the new gasket
No of valves : 2
Size of the valves : 2" x 600#
PIPE FITTER TR-2 Static Exec. BLOCK-C/4_AYTB
MECHANICAL
HELPER/IND
TR-2 Static Exec. BLOCK-C/4_AYTB
CLEANER/LAB
OR
006 QA/QC CHECKS _AH4 D167 INSPECTION
Reviewing to be carried out after the valve installation.
INSTRUMENT
TR-2 Instrumentation Exec. all blocks JAL INT'L
TECHNICIAN
INSTRUMENT
TR-2 Instrumentation Exec. all blocks JAL INT'L
HELPER
008 HOUSEKEEPING / CLEANING AREA _AJI D277 MECHANICAL
Clean All the Area and Maintain Good Housekeeping after completion of all the activities.
MECHANICAL
HELPER/IND
TR-2 Static Exec. BLOCK-C/4_AYTB
CLEANER/LAB
OR
009 CLOSE WORK PERMIT _AH2 D819 OPERATIONS
Refer to SATORP Work Permit System Procedure to close a work permit
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
Show jobs:
SCOPE:
24H - 0:00 System Isolation Complete / Ready For Mainten
24H - 0:00 U152-Scope Execution Start PAU_AA-152-S0 - H
24H - 0:00 A4-Scope Execution Start PAU_AA-152-S0 - HYD
24H - 0:00 System Hand Over Complete / Ready For Commi
24H - 0:00 U152-Scope Execution Finish PAU_AA-152-S0 - H
24H - 0:00 A4-Scope Execution Finish PAU_AA-152-S0 - HYD
SCOPE: 2020384 - To service both isolation valves
_AH0 24TA - 1:00 OBTAIN WORK PERMIT
_AGY 24TA - 1:00 DISCONNECT/REMOVE ASSOCIATED INSTRUMEN
_AGX 24TA - 3:00 REMOVAL OF VALVE
_AH3 24TA - 2:00 TRANSPORT NEW VALVE FROM WAREHOUSE TO
_AH1 24TA - 3:00 REPLACEMENT OF VALVE
_AH4 24TA - 1:00 QA/QC CHECKS
_AGZ 24TA - 1:00 CONNECT / RE-INSTATE ASSOCIATED INSTRUME
_AJI 24TA - 1:00 HOUSEKEEPING / CLEANING AREA
_AH2 24TA - 1:00 CLOSE WORK PERMIT
152 PI 0040
Dis connect the pressure gauge 152-PI-0040 with diaphragm and capillary,
Subtotal: 0 24 0 0 0
Total: 24 0