Professional Documents
Culture Documents
Memo
Additional scope
DRAIN VALVE REPLACEMENT
Scope location
LOCATION : AREA-4
UNIT-U152 (HYDROGEN PRODUCTION TRAIN-2 & PSA (HPU-2)
EQUIPMENT TAG : U152-ZV-0020
ELEVATION : GROUND LEVEL (0.3 M)
WP holder
TAG # : 152ZV0020
NOTIFICATION # : 10113235
UWL #U1520114
STOPPOINT NOTIFICATION : ZV20 DOWNSTREAM DRAIN VLAVE ( N7-NOTIFICATION)
SCOPE: REPLACE THE DRAIN VALVE
HEIGHT FROM THE GROUND LEVEL : 0.3 MTR
DRAIN VALVE SIZE : 2" x 600# (VALVE TO BE ORDERED)
Freeze
** Frozen by Multi change **
** UNDO frozen by Multi change **** Frozen by Multi change **
TAG # : 152ZV0020
NOTIFICATION # : 10113235
UWL #U1520114
STOPPOINT NOTIFICATION : ZV20 DOWNSTREAM DRAIN VLAVE ( N7-NOTIFICATION)
SCOPE: REPLACE THE DRAIN VALVE
HEIGHT FROM THE GROUND LEVEL : 0.3 MTR
DRAIN VALVE SIZE : 2" x 600# (VALVE TO BE ORDERED)
No. Job description / resources Job no. Lib no. Job discipline / circumstances
001 INSPECTION NEW VALVES _QJ2 A019 FITTINGS OVERHAUL
Inspect New Valves as per Material Ordered.
Drain Valve Size : 2" x 600#
VALVE TR-2 Valves’ Refurbishment BLOCK-C/4_AL-NAJIM /
TECHNICIAN M.PRECISION
INSPECTOR TR-2 SATORP INSPECTION
TRANSPORT NEW VALVE FROM
002 _QG6 H302 MECHANICAL
WAREHOUSE TO SITE
Keep the Valve Ready for Transport & Re-installation.
FORKLIFT
TR-2 Lifting & Transp Exec. BLOCK-C/4_AYTB
OPERATOR
FLAG MAN TR-2 Lifting & Transp Exec. BLOCK-C/4_AYTB
003 OBTAIN WORK PERMIT _QG7 D818 OPERATIONS
Refer to SATORP Work Permit System Procedure to apply a work permit and detailed job safety analysis JSA.
Conduct Tool Box talk in Work location, prior to start the job.
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
004 REMOVAL OF VALVE _QG8 D145 FITTINGS OVERHAUL
Un-bolt and Remove the Existing Drain Valve
MECHANICAL
TR-2 Static Exec. BLOCK-C/4_AYTB
SUPERVISOR
Show jobs:
SCOPE:
24H - 0:00 System Isolation Complete / Ready For Mainten
24H - 0:00 A4-Pre-Turnaround Start PAU_AA-152-S0 - HYDR
24H - 0:00 U152-Scope Execution Start PAU_AA-152-S0 - H
24H - 0:00 A4-Scope Execution Start PAU_AA-152-S0 - HYD
24H - 0:00 A4-Pre-Turnaround Finish PAU_AA-152-S0 - HYD
24H - 0:00 System Hand Over Complete / Ready For Commi
24H - 0:00 U152-Scope Execution Finish PAU_AA-152-S0 - H
24H - 0:00 A4-Scope Execution Finish PAU_AA-152-S0 - HYD
SCOPE: 2018484 - zv 20 downstream drain valve ( N7-NOTIFI
_QJ2 12TA - 1:00 INSPECTION NEW VALVES
_QG6 12TA - 1:00 TRANSPORT NEW VALVE FROM WAREHOUSE TO
_QG7 24TA - 1:00 OBTAIN WORK PERMIT
_QG8 24TA - 1:00 REMOVAL OF VALVE
_QG9 24TA - 2:00 REPLACEMENT OF VALVE
_QGA 24TA - 1:00 QA/QC CHECKS
_QGB 24TA - 1:00 HOUSEKEEPING / CLEANING AREA
_QGC 24TA - 1:00 CLOSE WORK PERMIT
Subtotal: 0 16 0 0 0
Total: 16 0
Resource Type Qty Unit Article no. Article description Legacy art. no. 1 Legacy art. no. 2