SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING

AT HARIHAR BHAWAN, LALITPUR


Minutes of Progress Review Meeting # 18 (Visit of World Bank Mission)

Date: Sep 7, 2020


Venue: Virtual Meeting through Webex

Participants:

GoN/ Department of Agriculture/ Central WORLD BANK / NIRTTP CONSULTANT CONTRACTOR


Agricultural Laboratory
Ms. Sabitri Baral Mr. Bibash Shrestha Ar. C.L. Kayastha Mr. Pitambar Badu
Chief World Bank Group Team Leader Director, Lama Construction

Mr. Sunil Mr. Alidu Babatu Adam Ar. Manish Kayastha Er. Sajal Shrestha
World Bank Group Site Engineer
Ms. Sunita
Mr. Surendra G. Joshi Er. Roshan Gyanwali
World Bank Consultant

Mr. Deepak Man Singh Shrestha

Mr. Devi Prasad Thapaliya

Mr. Prakash Awasthi

Mr. Erik Nora

Agenda:

. NIRTTP Review Mission Meeting between World Bank and Central Agriculture Lab Team.

. Update on remaining works

. Issuance of completion Certificate.

Meeting Minutes:
S.No. Action Responsibility Status
1. Physical and Financial Progress of  Ar. CL Kayastha presented the Physical and
the Project Financial Progress of the Project.  Physical Progress - 97%
 Financial Progress - 97%
 Contractor to complete the remaining works
within 2 to 3 working days after the lockdown
becomes less intensive.

2. Access Road  Mr. Prakash Awasthi presented the road


conditions and problems due to rain water  Government entity to be identified by the
clogging. client which has the authority over the road.
 Filling and maintenance of road with proper
 Possibility of disposing storm water to IRD gradient could rectify the problem.
office’s waste water management system was
discussed.

 World bank group asked the client if they are  Client was satisfied with how the building
3. Building satisfied with the outcome of the building. has turned out to be.

4. Variation  Consultant extension of time and variation on  World Bank group has said that the variation
the amount was discussed. on the amount will be discussed later on
 Client has approved to take the issue to the separate meeting after they receive all the
required level. supporting documents.

5. Budget  Client has mentioned about the shortage of  World Bank group has suggested to take
budget around 3 crore 80 lakhs to the world permission to use the amount allocated for
bank group. procurement of lab equipments and then
request for the budget later to Ministry of
Finance incase the amount becomes
insufficient for the procurement of lab
equipments.
6. Completion Certificate  Issuance of completion certificate letter was  Consultant to issue certificate of completion
discussed between consultant, Client, after the completion of remaining works.
Contractor and world bank