Participants:
Mr. Sunil Mr. Alidu Babatu Adam Ar. Manish Kayastha Er. Sajal Shrestha
World Bank Group Site Engineer
Ms. Sunita
Mr. Surendra G. Joshi Er. Roshan Gyanwali
World Bank Consultant
Agenda:
. NIRTTP Review Mission Meeting between World Bank and Central Agriculture Lab Team.
Meeting Minutes:
S.No. Action Responsibility Status
1. Physical and Financial Progress of Ar. CL Kayastha presented the Physical and
the Project Financial Progress of the Project. Physical Progress - 97%
Financial Progress - 97%
Contractor to complete the remaining works
within 2 to 3 working days after the lockdown
becomes less intensive.
World bank group asked the client if they are Client was satisfied with how the building
3. Building satisfied with the outcome of the building. has turned out to be.
4. Variation Consultant extension of time and variation on World Bank group has said that the variation
the amount was discussed. on the amount will be discussed later on
Client has approved to take the issue to the separate meeting after they receive all the
required level. supporting documents.
5. Budget Client has mentioned about the shortage of World Bank group has suggested to take
budget around 3 crore 80 lakhs to the world permission to use the amount allocated for
bank group. procurement of lab equipments and then
request for the budget later to Ministry of
Finance incase the amount becomes
insufficient for the procurement of lab
equipments.
6. Completion Certificate Issuance of completion certificate letter was Consultant to issue certificate of completion
discussed between consultant, Client, after the completion of remaining works.
Contractor and world bank