S.No. Grid Remaining Works Defects Remarks

1. In between grid 4-5 and Covering portion above glass door with cement Light Fixtures: 2-18 Watt
C-D board Led panel 300*300mm in
between grid B-C and C-D

2. In between grid 1-2 and Plaster work on brick masonry on upper ramp Painting work: Wall Surface
B-C inside basement on west side
in between grid 2-5 is not even
and seems single coated.

3. In between grid 1-3 Skirting work under ramp

5. In between grid 1-2 and Painting work on brick masonry on upper ramp
B-C

6. In between grid 1-2 Manually operated geared m.s. rolling shutter


with rectangular strips on entrance of basement

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Floor: Ground Floor


S.No. Rooms Remaining Works Defects Remarks

1. Visitors Waiting Cum  Drooping of light fixtures


meeting

2. Receipt of Samples & okay


Registration

3. Verification of okay
Documents

4. Sampling & Sample  Mosquito net on


Preparation windows is yet to be
placed Aug 17, 2020

5. Sample Preparation  Cleaning of paints on AC  Drooping of light fixtures


Wires
List of
6. Treatment Facility  Mosquito net on  Water leakage problem on AC  Rectification of AC problem is being Remaining
windows is to be  Drooping of light fixtures carried out. Works and
placed List of
Defects
7. PRA, Computer &  Cleaning of paints on AC  Small gaps on ceiling light fixtures
Servers Wire.

8. Library, Record &  Mosquito net on windows is  Door is too hard to push
Documentation to be placed  Drooping of light fixtures and small
gaps
 White patched on walls on south side

9. Toilets  Commode flush suction is not good

10. Reference Sample  Mosquito net is yet to be


Room(Cultures) placed

11. Reference Sample  Mosquito net is yet to be  Ac Wire without insulation on certain
Room(Plant Samples) placed. portion.
 Cleaning of paints on
AC wires
SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Floor: First Floor

S.No. Rooms Remaining Works Defects Remarks

1. M & B(Mycology And  Door is too hard to push


Bacteriology) Inspection Lab  Gap on ceiling light fixtures.
& Reference samples

2. M & B Media Room  Mosquito net on windows is yet to  Drooping of light fixtures  Glass door is good.
be placed  Small gaps on walls of along
 Cleaning of paint marks on AC AC outer boundary
wires

3. M & B Glassware  Mosquito net on windows is yet to  Drooping of light fixtures


be placed

4. M & B Treatment  Drooping of light fixtures  Glass Door is very good


Facility(Chemical &
Physical)

5. X-Ray Radiography Room

6. Entomology X-Ray sample  Mosquito net on windows is yet to  AC wire has no insulation on
preparation & Reference be placed certain portion
material  Patch on false ceiling

7. Entomology Inspection Room  Power connection of fan inside


HVAC duct
 Cleaning of paints on AC wire
8. Virology Sample Preparation  Cleaning of paints on AC wires  Drooping of light fixtures
Lab & Glassware/Chemical
Storage

9. Virology ELISA/PCR Lab  Cleaning of paints on AC


wires.
 Small gaps around light
fixtures

10. Virology General Laboratory  Mosquito net on windows is yet to  White patch on wall on side of  Water leakage problem is being
And Reference Specimens be placed AC rectified
 Water leakage to basement
false ceiling through AC pipes
from Floor trap

11. Entomology & Nematology  Cleaning of paints on HVAC duct


Glassware Storage & General  Cleaning of paints on AC wire
Laboratory

12. Entomology Treatment  Mosquito net on windows is yet to  No insulation on certain


Facility(Chemical only) be placed portion of AC wires.
 Plaster work to cover AC drain  Drooping of light fixtures
pipe

13. Entomology Sample  Mosquito net on windows is yet to  Small gaps around light
Preparation & Glass be placed fixtures.
ware  Small hole on wall above AC
fitting

14. Entomology Insect  Small hole on wall above AC


Culture Room fitting
 Water leakage to basement
false ceiling through AC pipes
from Floor trap

15. Gents Toilet  Fitting of urinal is not done yet  Ceiling exhaust fan above  Commode flush suction is not
shower is not that good in good
condition
 Plumbing line for urinal was
not left before

16. Ladies Toilet  Commode flush suction is not


good

17. Lobby  Drooping of light fixtures

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Floor: Second Floor


S.No. Rooms Remaining Works Defects Remarks

1. Lobby  Small gaps around light


fixtures.

2. Survey & Surveillance Room  Plaster work to cover walls


damaged by AC drain pipe
 Cleaning of paints on AC wires

3. Molecular Lab(Entomology,  Mosquito net on windows is yet


Pathology, Nematology & to be placed
Virology)  Cleaning of paints on HVAC
duct

5. Dark Room  Cleaning of patches on walls  Hole on walls above AC


fitting

6. Inoculation Room  Cleaning of paints on AC wires  Small gaps on walls


around AC fitting

7. Autoclave Room  Mosquito net on windows is yet


to be placed

8. Chemical/Glassware Storage  Mosquito net on windows is yet  Drooping of light fixtures


to be placed

9. General Lab(Entomology,  Mosquito net on windows is yet  Drooping of light fixtures


Pathology, Nematology & to be placed
Virology)  Cleaning of paints on Ac wires
 Plaster work on walls damaged
by AC drain pipe

10. Record &  Mosquito net on windows is yet


Documentation to be placed
Room  Cleaning of paints on Ac wires
 Plaster work on walls damaged
by AC drain pipe

11. Reference Sample  Mosquito net on windows is yet  Patches on walls around
Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Floor: Third Floor

S.No. Rooms Remaining Works Defects Remarks

1. Corridor  Drooping of some light


fixtures

2. Office Incharge Room  Mosquito net on windows is yet  Drooping of light fixtures
to be placed
 Cleaning of paints on AC wires

3. Toilet  Mirror light portion into  Position of mirror and mirror light will
the windows be changed and aligned but they cannot
 Mirror and basin is not change the position of basin.
aligned

4. Officer Room First  Mosquito net on windows is yet


to be placed
 Plaster work to cover AC drain
pipe on walls

5. Officer Room Second  Mosquito net on windows is yet  Drooping of light fixtures
to be placed

6. Admin & Account Room  Mosquito net on windows is yet  Hole on wall above AC
to be placed fitting.
7. Non Officers Room  Mosquito net on windows is yet  Hole on brick wall above
to be placed AC

8. Lobby okay

9. Pantry okay

9. Training Hall  Projector  Door in between grid C-D


 Fitting of new Projector stand is not smooth
 Drooping of light fixtures.

10. Training Hall Balcony  Fitting of handrail on top of glass


railing is being carried out

11. Terrace  Tile works infront of water tap in  Cracks infront on  Fitting of handrail on top of glass
between grid 3-4 projected paraphet wall railing is being carried out
 Concrete has been set on the infront of Office in charge
terrace in between grid 5-6 and room and officer 2nd room
should be removed

12. Gents toilet  Urinal partition is yet to be  Commode Flush suction is not good.
placed

13. Ladies toilet  Commode Flush suction is not good.

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR
Floor: Fourth Floor

S.No. Rooms Remaining Works Defects Remarks

1. Corridor  Patch on false ceiling


infront of staircase.
 Cement patch on wall of
corridor near DB box

2. Battery Room okay

3. Store/Pantry Room okay

4. Terrace  Cement patch on staircase


to roof .
 Cement patch on tiles of
terrace.

5. Toilets  Commode Flush suction is not good.

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Floor: Roof
S.No. Rooms Remaining Works Defects Remarks

1. Upper Terrace  Plaster and painting works on


vent cover
 Adding Clamps on Earthing wire
 Lightening Arrester work

2. Terrace  Plumbing work from backwash


pipe of filter system to floor trap.
 Plaster and painting works on
vent cover.

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Others

S.No. Rooms Remaining Works Defects Remarks

1. Guard House  Painting work is incomplete on


North face of building.
 Painting work on bottom of
paraphet walls of guard house.
 Gardening works: Cladding on
garden walls outside of guard
house and Flowering works.

2. Incinerator Shed  Enamel Painting work on m.s


square pipes truss of incinerator
shed.

3. Waste water  Enamel Painting work on m.s


treatment plant shed square pipes truss of treatment
plant shed.

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

others

S.No. Rooms Remaining Works Defects Remarks

4. Fourth Floor level  Solar water heater is yet to be


installed.

5.  Fire Extinguisher is yet to be


placed in position on the
building.

6. Boundary Walls:  Beading work on inside of


North Side boundary walls on North side of
building.

East Side  Beading work of boundary


walls on East side of building.
 Painting work is remaining on
corner of boundary wall near
external toilet on East Side of
building.

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Facade of building

S.No. Building Elevation Defects Remarks

Building South Elevation  White patch on bottom of Z-beam on


first floor level
East Elevation  Walls of east side of building below
first floor level is wet.

West Elevation  One light should be removed on west


façade of building on third floor
level, which is not removed yet

Aug 17, 2020

List of Remaining Works and List of Defects


SPS/ PLANT QUARANTINE AND REGIONAL PLANT PROTECTION LAB BUILDING, HARIHAR BHAWAN, LALITPUR

Others

S.No. Rooms Remaining Works Defects Remarks

1. Lift Core  Granite floor to be placed on the


base of lift.
 ACP work on top of the lift on
fourth Floor level to be done.

2. Trash Chute  Finishing of ACP inside trash Chute


near window side.
3. Festival lights  Festival lights is to be fitted on  Few defective festival lights on
third and fourth floor level second floor level on west side.
Completely.

4. Generator Shed  Manually operated geared m.s.


rolling shutter with rectangular
strips is to be installed.