Professional Documents
Culture Documents
PM Handbook Updated Edition 15 April 2016 PDF
PM Handbook Updated Edition 15 April 2016 PDF
MANAGEMENT
HANDBOOK
A Guide to Eptisa Project Managers
This manual presents the most important guidelines that EPTISA Project Managers
must follow when managing company projects, aiming to ensure a common
management approach and to comply with the required professional standards. All
changes to the contents of this manual must be approved by the PMO.
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 2
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 3
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
LIST OF ABBREVIATIONS
Abbreviation Definition
EVR Expenditure Verification Report
H&S Health and Safety
H&SC Health and Safety Coordinator/Company
H&SD Health and Safety Department of Eptisa
IE Incidental Expenditure
IFIs International Financial Institutions
IIC Engineering , Instrumentation and Control
P Project
PM Project Manager
PMBOK Project Management Body of Knowledge
PMI Project Management Institute
PMO Project Management Office
PPE's Personal Protective Equipments
QMS Quality Management System
RFQ Request for Quotation
ToR Terms of Reference
WBS Work Breakdown Structure
For EPTISA internal use only – do not distribute without permission from the PMO 4
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Aristotle
For EPTISA internal use only – do not distribute without permission from the PMO 5
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
CHAPTER I - INTRODUCTION
The contents presented in the following chapters of this PM Handbook are the result of the
extensive experience of a group of EPTISA senior project managers, who have resumed their
knowledge in a structured and comprehensive document, aiming to make it available to the
overall project management community and specifically to all those who are taking their first
steps in EPTISA as project managers.
The incorporation of the lessons presented in this PM Handbook in the daily life of the project
management community, should contribute to achieve the following specific objectives:
• The clear definition of roles and responsibilities of all involved in project management;
• The definition of critical project management processes and knowledge areas;
• Standardization of project management best practices;
• Contribution to the creation of a project management common culture in EPTISA
• Project measurable success
• The creation of common repository
Although, as previously said, the purpose of this document is not to explain in detail project
management concepts, but to capture the practical essence of project management in EPTISA,
the authors have followed one of the most widely recognized project management
methodologies to structure the contents of this PM Handbook – the Project Management
Institute1 methodology.
The authors encourage all those that wish to evolve in the project management career to
pursue a certification in project management, allowing their full recognition by peers and
clients as project management professionals.
We hope you enjoy the reading. Feel free to send us any comments and suggestions to EPTISA
Project Management Office: <eptisa_pmo@eptisa.com>
1
To find out more about the Project Management Institute go to: http://www.pmi.org/
For EPTISA internal use only – do not distribute without permission from the PMO 6
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
In the introduction chapter the Project Management Handbook describes the different roles
and responsibilities existing in a typical EPTISA project structure, aiming to clarify as best as
possible how the project implementation should be organized and how the project staff should
interact and deliver project products/deliverables.
In this initial chapter the typical profile of the Project Manager is also defined, including its
responsibilities, educational background, professional qualifications, languages proficiency and
experience. Such profile may be considered as a guideline for Project Managers aiming to
consolidate their professional career in EPTISA.
In chapter two a brief overview of the project management lifecycle is presented, as well as a
description on how project structures are organized in EPTISA companies – a general format is
presented taking into consideration that each Eptisa office may have its own specific structure.
Chapter three presents the most relevant contents for the common and proper understanding
of project management. It follows the methodology of the Project Management Institute,
aiming to prepare EPTISA project managers for the certification in project management.
In this chapter, five process groups and ten knowledge areas are presented and correlated
taking into consideration the five phases of project management. The way the information is
organized allows those involved in project management and specifically the project manager
to focus on the requisites and outputs of each process as progress is made in each project
phase.
Having completed the presentation of the fundamentals of project management the next
chapter is dedicated to explain the different types of service contracts (lump sum and fee
based) and the specificities of managing project for the international funding agencies, such as
the European Commission, one of the most important entities that finances projects
implemented by Eptisa. All these aspects are addressed in chapter four.
In chapter five, an implementation guide is proposed, aiming that Project Managers prepare a
common set of information to describe, plan, control and communicate projects’ status in a
standardized way.
Finally, the last three chapters refer to appendixes (chapter six), templates to be used (chapter
seven) and the people who make this manual possible (chapter eight).
For EPTISA internal use only – do not distribute without permission from the PMO 7
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
It is of utmost importance to have a clear understanding of the roles and responsibilities of all
those involved in project organization and implementation. The following description of roles
and responsibilities takes into consideration the most complex projects implemented by
Eptisa, with all the different roles required. In simpler projects multiple roles are assumed by
the same person and therefore the project structure becomes flattened.
The following image illustrates a typical project structure:
Project Sponsor
Financial
Controlling
Project
Project Manager
Management Office
Administrative
Support
Team Leader
Experts Sub-Contractors
Within the above structure there will be the following roles and responsibilities:
Project Sponsor: The Project Sponsor is the ultimate responsible for the project and its results,
both operational and financial. He should approve project financial baseline, provide the
resources (financial, technical and human) and formally authorize the project within Eptisa.
For issues beyond the control of the Project Manager, the Sponsor serves as an escalation
path. The Sponsor should also be involved in important issues for project outcome such as
authorizing changes in scope and go/no-go decisions when project risks are particularly high.
Project Manager: The Project Manager (in certain projects also designated as Project Director),
is the person assigned by the Project Sponsor to achieve project objectives. Specifically in the
case of Eptisa, the Project Manager is responsible for the project gross margin and therefore
for all the actions that impact on such indicator.
For EPTISA internal use only – do not distribute without permission from the PMO 8
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 9
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Team Leader: The Team Leader is responsible for managing the technical team and ensuring
that project deliverables are delivered on-time, within budget and with the required quality.
The main responsibilities of the Team Leader are:
In any case the Project Manager should not allow the Team Leader to manage any contractual
issues with the client or to accept any changes to the agreed scope of work or any other
project critical variables (time, cost, resources and quality).
Project success requires a clear distinction between roles and responsibilities and only the
Project Manager is in position to communicate and enforce such distinction.
Technical Team (experts and sub-contractors): The technical team is responsible for executing
the activities assigned by the Project Manager and the Team Leader and to deliver project
products on-time, within budget and with the agreed and desired quality.
Administrative Support: The team that constitutes the administrative support must ensure
that all required administrative and logistic activities are performed as required, such as for
example:
For EPTISA internal use only – do not distribute without permission from the PMO 10
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Eptisa Project Manager Profile can be summarized as a very proactive, versatile and
highly skilled professional with a proven track record in successfully delivering a diverse
range of projects
Although a Project Manager may have very different backgrounds and experiences he or she
should master three main areas of expertise: Technical, Management and Leadership.
Technical: The ability to understand the technical aspects of the work to be performed is
fundamental to ensure the full understanding of project scope, the activities to be developed
and the profiles to develop such activities. Although the Project Manager doesn’t have to be
able to produce project outputs (except in the cases where he not only is responsible for
managing the project but must also develop a work block or project activity), it is fundamental
that he has enough understanding to evaluate what has to be produced and with what
resources. A sufficient understanding of project technicalities will also grant the Project
Manager the respect of his technical staff and therefore help him in his mission.
Managerial: Running a project is like running a small company. The Project Manager must
focus on its product (project deliverables), the resources to produce them (technical, human
and financial), the organization of the work and the client and other stakeholders to whom he
reports. It requires good management expertise to make the project run smoothly and the
ability to communicate and interact positively with the team and project stakeholders is
probably the most important thing that the project manager should have in his mind.
Leadership: The third area that the Project Manager should develop is leadership, that is, his
ability to point the way forward to the team and to help them to solve project issues that may
prevent the team to do their technical work. It is not expected that the Project Manager has an
immediate answer to all problems that may appear but it is expected that he actively searches
for solutions within the project organization and provides support to the team at all times. It is
also expected that he evaluates such team and ensures it works smoothly even if difficult
decisions must be taken such as to replace a team member if he is unable to perform
adequately.
Although specific technical skills may be required depending on the nature of the project, the
above areas of expertise should be common to all Eptisa Project Managers, providing them the
ability to interchange between regions and sectors.
For EPTISA internal use only – do not distribute without permission from the PMO 11
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
As per the soft skills required for good project management, it is expected that the Project
Manager is a very good communicator, is able to generate positive dynamics on the team and
has always a good attitude even in face of more complicated issues.
The Project Manager should always be seen as a problem solver (in opposition to a
problem maker)
The progression of the Project Manager in the project management career is achieved by
ensuring the proper soft skills as well as the continuous development of the main areas of
expertise – Technical, Managerial, and Leadership. There are currently four levels of Project
Management, depending on the complexity of the responsibilities developed:
Promotion criteria includes the result of periodically evaluating dimensions such as “Merit and
Results”, Ability to Deliver” and “Attitude”.
Table – Job Level of Project Managers and the distribution of their responsibilities
For EPTISA internal use only – do not distribute without permission from the PMO 12
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Value Description
Responsibility is the duty to take ownership for the decisions we make or
Responsibility fail to make, the actions we take or fail to take, and the consequences that
result.
Respect is the duty to show a high regard for ourselves, others, and the
resources entrusted to us. Resources entrusted to us may include people,
money, reputation, the safety of others, and natural or environmental
Respect resources.
An environment of respect engenders trust, confidence, and performance
excellence by fostering mutual cooperation—an environment where
diverse perspectives and views are encouraged and valued.
Fairness is the duty to make decisions and act impartially and objectively.
Fairness Our conduct must be free from competing self interest, prejudice, and
favoritism.
Honesty is our duty to understand the truth and act in a truthful manner
Honesty
both in our communications and in our conduct.
For EPTISA internal use only – do not distribute without permission from the PMO 13
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Figure 1: Typical Costs and Staffing Levels Across a Generic Project Life Cycle Structure. (Ref:
Project Management Body of Knowledge, PMBOK Guide, Fifth Edition)
For EPTISA internal use only – do not distribute without permission from the PMO 14
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Figure 2: Impact of Variable based on Project Time. (Ref: Project Management Body of
Knowledge, PMBOK Guide, Fifth Edition)
Such generic structure, sets the definition for the five categories known as Project
Management Processes, as adopted by the Project Management Institute and explained in
detail in Chapter III, point 3.1:
• Initiating Process Group;
• Planning Process Group;
• Executing Process Group;
• Monitoring and Controlling Process Group;
• Closing Process Group;
For EPTISA internal use only – do not distribute without permission from the PMO 15
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Corporate
Departments
International
Spain Balkans Romania
Development
Institutional,
Economical and Social
Development
Transportation,
Infrastructures and
Laboratories
Instrumentation,
Information and
Comm. Technologies
Project Management takes place both in the territories and the divisions and is supported by
corporative organizational units, such as:
• The Financial Department;
• The HR Department;
• The IT Department;
• The Purchasing Department;
• The Legal Department;
Additionally the Project Managers may be supported by specific units existing within Eptisa
regional offices.
Among other goals, the Project Management Office (PMO) (see Appendix B - PMO
Organization and Responsibilities) aims to simplify the interaction between the above
For EPTISA internal use only – do not distribute without permission from the PMO 16
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
corporative departments and Eptisa Project Managers, providing a single point of contact for
any financial / administrative / legal issues related to the above corporative functions.
Regarding technical issues, related to project implementation, the Project Manager should
directly address the Division where the project is assigned.
The list of contacts of the PMO as well as Divisions and Territories is available in Appendix C –
List of contacts for Project Management Support.
Regarding reporting and communication (to be further developed in Chapter III, section 3.8),
any Project Manager, independent of his/her origin (a Division or a Territory) will directly
report to the Project Sponsor, the ultimate responsible for project outcome. Such Project
Sponsor will be either the Head of the Division or the Head of the Territory.
In certain cases the Project Sponsor may delegate such responsibility to someone, such as, for
example, the Head of the Project Management Department in the case of the Territories or the
Area Directors, in the case of the Divisions.
The Project Manager will always report to a Territory and to a Division, directly or indirectly,
depending on where the Sponsor is based. For example, if the Sponsor is in the Territory, then
the Project Manager will directly report to the Territory and indirectly to the Division. On the
other end, if the Sponsor is in the Division, the Project Manager will directly report to the
Division and indirectly to the Territory.
The Project Manager must provide to all Eptisa stakeholders involved in the project,
periodical project information, whenever requested and according to the agreed reporting
templates (see Template T5 - Internal Progress Report). Typically, such internal
stakeholders are:
• The Financial Controller;
• The Head of the Territory;
• The Head of the Division;
• The Project Management Office;
The PMO will keep all the above mentioned organizational information updated and available
for Project Managers, through the Operations Portal (Appendix E – Information Systems to be
used by Project Managers).
Eptisa has implemented a system aiming to review periodically the project management
practices of the company. For any suggestion to improve project management, in any of its
dimensions, please contact the head of the project management department of your office,
the head of office or the Project Management Office Coordinator.
For EPTISA internal use only – do not distribute without permission from the PMO 17
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 18
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
4. Monitoring and Controlling: Those processes required to track, review, and regulate
the progress and performance of the project; identify any areas in which changes to
the plan are required; and initiate the corresponding changes.
5. Closing: Those processes performed to finalize all activities across all Process Groups to
formally close the project or phase.
The initiating process group is very straightforward since only has two processes:
P1. Develop Project Charter - This is the process of developing a document that formally
authorizes a project or a phase and documents initial requirements that satisfy the
stakeholder’s needs and expectations.
The Project Charter template is available on-line. The Project Manager is responsible to
fill it in and to keep it up to date.
Go to: https://eptinet.eptisa.com/apps/alta_proyecto_EPI/Default.aspx?LANG=en
P2. Identify project stakeholders - Identify stakeholders is the process of identifying all people
or organizations impacted by the project, and documenting relevant information regarding
their interests, involvement and impact on project success.
For EPTISA internal use only – do not distribute without permission from the PMO 19
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The planning process can’t be done one single time at the beginning of the project when most
of the relevant information may not be immediately available and due to the uncertainty that
characterizes all projects.
The interactive nature of planning is essential because project follows an uncharted path
where new information is continuously becoming available as the project progresses. Part of
the skill of project management is to evaluate how much time and effort is required to be put
into each stage of the planning exercise.
To develop this process group, some decisions will need to be made, such as:
• How detail to make the plan;
• How far ahead to plan;
• How to involve stakeholders in planning;
• How to keep the planning process streamlined;
• How to manage the data that is being fed back into the planning process;
• How to determine the quality and reliability of this information;
• How often to re-plan;
• How to administer changes to the plan;
• How to minimize the effect of changes on work in progress;
P4. Plan Scope Management - The process of creating a scope management plan that
documents how the project scope will be defined, validated and controlled.
P5. Collect Requirements - This process is essential for clarifying and managing expectations as
adjustments are made through the project.
For EPTISA internal use only – do not distribute without permission from the PMO 20
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
P6. Define Scope - This process produces a detailed description of the project and its products
and ensures the confidence and trust of stakeholders.
P7. Create Work Breakdown Structure (WBS) – This is the process where you break down the
project elements into manageable work packages, producing your WBS and dictionary – WBS
Components description, milestones, deliverables, activities, scope, dates, resources, costs,
and quality. Other outputs include the scope baseline that enables stakeholders and the
project manager to assess ongoing progress and the impact of necessary adjustments.
P8. Plan Schedule Management - The process of establishing the policies, procedures and
documentation for planning, developing, managing, executing and controlling the project
schedule.
P9. Define Activities, P10. Sequence Activities, P11. Estimate Activity Resources, P12.
Estimate Activity Durations – These four processes create the list of activities and their
attributes that are required for the project. These activities are then scheduled into network
diagrams along with estimates of the resources needed and the time it will take to complete.
P13. Develop Schedule – This process produces the schedule baseline and data needed to
complete the work.
P14. Plan Costs Management - The process that establishes the policies, procedures and
documentation for planning, managing, expending and controlling project costs.
P15. Estimate Costs – This part of the planning process produces the cost estimates for each
activity or phase.
P16. Determine Budget – This brings together all activity and work package cost estimates into
a complete project budget. This forms the documentation for the project funding that includes
contingency for potential issues that may arise and produces the cost performance baseline.
P17. Plan Quality Management – The quality management plan that this process produces
must define the quality metrics and checklists that take into account potential risks, cost
performance baseline and organizational and sustainability factors.
P18. Plan Human Resources Management – Each phase of the project plan must have the
correct resources and skills in the staff assigned to it. These individuals will form teams to
produce work packages or for phases. The resulting management plan details the skills, roles,
responsibilities, and reporting relationships that support the schedule of work and project
objectives.
P19. Plan Communications Management – Communicating the correct level of information in
a timely manner to all parties is essential for success. This management plan enables you to set
and manage stakeholder expectations through your regular updates on progress and project
changes. It also helps to create good working relationships within the project team, gaining
their support and cooperation.
P20. Plan Risk Management, P21. Identify Risks, P22. Perform Qualitative Risk Analysis, P23.
Perform Quantitative Risk Analysis, P24. Plan Risk Responses – If you want to complete your
project on time and within budget, the importance of assessing and planning for potential risk
is paramount. Your resulting risk register enables your communication with stakeholders to
keep them informed and make them aware of practical ground conditions.
P25. Plan Procurements Management – This management plan will define the approach your
project adopts towards procurement and identify potential suppliers you want to approach.
There will be detailed reports outlining procurement statement of work and decision-making
throughout the project life cycle.
For EPTISA internal use only – do not distribute without permission from the PMO 21
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The project management plan, including all the above in a comprehensive set of
information, should be periodically updated.
For EPTISA internal use only – do not distribute without permission from the PMO 22
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
P29. Acquire Project Team – This process is simply concerned with ensuring the composition
of people and that the skills match the project’s needs. It also ensures the availability of the
required individuals by clearly communicating project expectations and timelines.
P30. Develop project Team – This process enables the project manager to ensure that the
interactions and competencies within the team match the required level of performance. It is
also the process responsible for building a cohesive team and conducting regular team
assessment.
P31. Manage Project Team – This process involves managing and monitoring team members’
performance. The project manager will give constructive feedback to individuals or groups to
ensure that issues and conflicts are avoided.
P32. Manage Communications – A major contributor to a project’s success is how well
pertinent information is routinely communicated to the relevant parties. Selecting the best
means of communicating plays a key role in this process. Knowing what issues warrant a call to
a stakeholder and those that don’t helps to create a positive working environment.
P33. Conduct Procurements – All projects need to acquire certain resources from external
suppliers and having the necessary procurement processes in place ensures the correct
distribution of resources.
P34. Manage Stakeholders Engagement – Since your stakeholders are a significant party in
any project, communicating appropriately with them is an essential skill to acquire. Such
communications need to assure that their needs are being met, their concerns are heard, and
that issues that occur are being properly addressed.
It is essential that the project manager documents and assesses each change against its
impact on timescales and budget. All changes must be authorized by the project sponsor
and formal evidence of the change (including contract addendums if applicable) should be
developed.
For EPTISA internal use only – do not distribute without permission from the PMO 23
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
P37. Validate Scope – This process formally accepts project deliverables as being complete. To
attain this completed status all documentation relating to that phase or work package must be
included to be accepted as complete.
P38. Control Scope – Any changes to the scope baseline must be closely monitored and, once
accepted, reflected in the project scope and relevant work packages. These adjustments must
be communicated to the project stakeholders so that implications for the budget and
timeframes can be understood and agreed to.
P39. Control Schedule – The project schedule baseline is a critical document and it is essential
that any changes or adjustments that result from monitoring are properly incorporated and
communicated to all necessary parties. Careful and thorough monitoring will reduce instances
of major setbacks due to scheduling issues that have been poorly reported. It is also important
to monitor the project Critical Path, identifying the status of all those activities that impact
decisively on the overall schedule.
P40. Control Costs – Monitoring and controlling the costs of any project are critical aspects of
its success. It is essential that project status reports accurately current expenditure and
forecast spend, and highlight any variances from the cost baseline.
P41. Control Quality – Managing and controlling the quality of what is produced during a
project is vital to its success. This process monitors the quality of the executed activities,
assesses how well these match the required quality metrics and checklist, and recommends
any necessary changes.
P42. Control Communications – This is the process that defines and monitors the production
of performance status reports, measurements and forecasts. These reports form a key aspect
of the communication within the project team and stakeholders on how well progress maps
the project benchmark goals.
P43. Control Risks – This process plays a key role in project management and performance
because it documents identified risks, and monitors and evaluates any changes or responses to
this initial assessment. It also identifies, evaluates, and reports new risks, updating the risk
register as appropriate.
P44. Control Procurements – All projects require the procurement of some resources so that
their performance matches project timelines and budget. This process manages, monitors, and
documents the performance of suppliers against the contracted requirements. It also manages
these working relationships to ensure that any changes that occur during the contract period
are properly incorporated and delivered.
For EPTISA internal use only – do not distribute without permission from the PMO 24
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
A carefully structured project closure phase should ensure that the project is brought to a
controlled end, which in practice means that:
• All of the project deliverables are formally transferred to the client and other
stakeholders;
• All of the lessons learned from the project are documented and archived;
• Any contracts established by the project are formally closed;
The processes included within the closing process group are the following:
P46. Close Project or Phase – This is the process of finalizing all activities across all of the
Project Management Process Groups to formally complete the project or phase. When closing
the project, the project manager will review all prior information from the previous phase
closures to ensure that all project work is complete and that the project met its objectives.
P47. Close Procurements – This is the process of formally closing any contract set up by the
project and involves verification that all work and deliverables were accepted. It also involves
administrative activities such as finalizing open claims, updating records to reflect final results,
and archiving such information for future use.
For EPTISA internal use only – do not distribute without permission from the PMO 25
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Each of the ten knowledge areas contains the processes that need to be accomplished within
its discipline in order to achieve effective project management. Each of these processes also
falls into one of the five process groups, creating a matrix structure such that every process
can be related to one knowledge area and one process group.
For EPTISA internal use only – do not distribute without permission from the PMO 26
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Knowledge Area
Monitoring and
Initiating Planning Executing Closing
Controlling
Project
32. Manage 42. Control
Communications 19. Plan Communications
communications Communications
Management
For EPTISA internal use only – do not distribute without permission from the PMO 27
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Plan Scope Management - The process of creating a scope management plan that
documents how the project scope will be defined, validated and controlled.
• Collect Requirements - Determine and document project stakeholder’s requisites and
sustainability principles to meet project objectives;
• Define Scope – Develop the detailed description of the project;
• Create the Work Breakdown Structure (WBS) – Subdivide project deliverables and
project work into manageable components;
• Validate Scope – Formalize the acceptance of the completed project deliverables;
• Control Scope – Monitor the status of the project scope and manage changes regarding
project scope baseline;
The correct understanding, definition and control of the Scope of Work can be considered as
one of the fundamental responsibilities of the Project Manager and the fact that in many cases
the Scope of Work as described in the Contract is not absolutely clear to both the client and
the consultant, makes it mandatory to revise it in detail and to clarify it immediately or in the
first weeks of the project.
Not acknowledging such need will result in serious misunderstanding that will affect the
project outcome, resulting in additional work to be performed, rework of work already
completed, additional time to finish the project, additional resources, and ultimately client
dissatisfaction and the erosion of project gross margin.
The inception period is the opportunity to revise with the Client and other Project
Stakeholders the Scope of the Work, aiming to clarify project tasks, products and quality
requirements, and to confirm estimated project margin.
It is a major responsibility of the Project Manager to fully understand the Scope of Work and to
clarify with the Client what is within the agreed scope and what is not (scope exclusions).
2
As defined in the Project Management Body of Knowledge – Fifth Edition
For EPTISA internal use only – do not distribute without permission from the PMO 28
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The project should deliver the agreed Scope of Work, not less (contractual breach), nor more
(additional project costs).
The final, detailed and approved definition of the Scope of Work should be stated in the
Project Scope Statement (attached), constituting the scope baseline of the project. This
baseline scope is then monitored, verified and controlled throughout the lifecycle of the
project.
Any change to the agreed scope will require a formal approval by the Project Sponsor (the
Office or Division General Managers or whom they delegate the responsibility). This is the case
of changes that will impact on project variables such as: Quality, Schedule, Budget, Resources
or Risk.
Any change to the Scope of the Work that may impact on project gross margin (either
negatively or positively) requires the approval of the Project Sponsor.
The fact that the decision to accept any change to the scope belongs to the Sponsor (or
whomever he delegates), requires that the Project Manager provides him all relevant
information. The Scope Change Register (attached) should therefore be filled-in and sent to
the Project Sponsor for approval, aiming the authorization for proceeding with a contract
addendum.
As per the client acceptance of the project products (Verify Scope), the Project Manager
should always have evidence of such acceptance. Therefore, after the delivery of any project
product and taking into consideration the periods estimated in the contract for the client
review, it is imperative that the Project Manager formally requires the product acceptance,
allowing subsequent invoicing. Such requirement for product acceptance may be in the form
of a mail addressed to the person in the client in charge of monitoring deliverables or a more
formal letter, depending on the terms of the contract.
Although some clients disregard the need to provide the acceptance for project products
it is imperative the Project Manager has evidence of such request.
Project Register
MS Project (or similar)
For EPTISA internal use only – do not distribute without permission from the PMO 29
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Planning
o Plan Schedule Management – Describe procedures and supporting documents to
be used during schedule management;
o Define Activities – Describe actions to be performed to produce the project
deliverables;
o Sequence Activities – Document the relationships among the activities;
o Estimate Activities Resources – Estimate the type and quantities of resources
needed to perform each activity (material, human resources, equipment or
supplies);
o Estimate Activities Durations – Estimate the number of work periods (hours, days,
weeks) needed to complete each activity according to the resources estimated
o Develop Schedule – create a schedule model according to the sequence of activities
and their estimations (resources and duration);
• Monitoring and control
o Control Schedule – Monitor the status of the project activities and manage changes
regarding project time baseline;
The project schedule is a key component of the Project Management Plan, and has a direct
impact, among others, on the cost of the project (cost needed to support the activities in the
project) and opportunity cost (the loss of potential gain from other projects that this company
could execute if resources wouldn’t be on this project).
Different iterations on the Planning activities (included time planning activities) are usually
executed, until the schedule is defined at the right level of detail, no conflicts are found with
the other project constraints (scope, quality, cost, risk, resources) and the project schedule is
included in the project management plan and approved.
It is important to make a difference between the project deliverables described in the WBS
(see Project Scope Management section) and the activities. Remember that it is common to
have different activities for a single work package.
When estimating resources for activities, the first question should always be “purchase or do”,
so that the Project Manager makes a decision about which activities will be executed by
internal resources and which would be subcontracted. This is an important decision, and both
the organization assets and the environmental factors of the project have to be taken into
account (remember an activity executed in a country might be totally different in other
3
As defined in the Project Management Body of Knowledge – Fifth Edition
For EPTISA internal use only – do not distribute without permission from the PMO 30
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
country because of multiple reasons, like legal frameworks, cultural factors, labor calendars,
etc.)
Once the resources for each activity are clear, it is time to estimate durations.
Once activities, sequences among them, resource requirements, durations and schedule
constraints are available, the project schedule can be created. Once more, remember that
developing an acceptable project schedule is often an iterative process.
The inception period is the opportunity to revise with the Client and other Project
Stakeholders the Project Schedule, aiming to clarify project activities, milestones and
relationships among activities.
Thus, it is a major responsibility of the Project Manager to fully understand the Project
Schedule and to clarify with the Client relationships with external activities (such as
information or resources to be received prior to an activity).
Prior to the presentation for approval of the project schedule, resources should be optimized
and some schedule compression is recommended, but remember that highly compressed
schedules might mean more risky projects.
The final, detailed and approved schedule should be stated in the Project Schedule,
constituting the Schedule Baseline of the project. This schedule baseline is then monitored
and controlled throughout the lifecycle of the project.
Any change to the agreed Schedule Baseline will require a formal approval by the Project
Sponsor (the Office or Division General Managers or whom they delegate the responsibility).
This is the case of changes that will impact on project variables such as: Quality, Schedule,
Budget, Resources or Risk.
Any change to the Schedule Baseline requires the approval of the Project Sponsor,
including any change to the schedule of final deliverables or milestones linked to invoices
to be delivered.
The fact that the decision to accept any change to the schedule belongs to the Sponsor (or
whomever he delegates), requires that the Project Manager provides him all relevant
information. The Change Register (Template T6 – Scope Change Register) should therefore be
filled-in and sent to the Project Sponsor for approval, aiming to get the authorization for
proceeding with a contract addendum.
For EPTISA internal use only – do not distribute without permission from the PMO 31
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Finally, control schedule is the process of monitoring the status of the project activities to
update project progress and manage changes to the schedule baseline. At this process, the
Project Manager should be concerned about:
• Determining the current status of the project schedule and reporting it using the Project
Progress Report (Template T5 - Internal Progress Report Template). Frequency of
reporting must be approved by Sponsor;
• Analyzing the factors that result in schedule changes and influence on them;
• Managing the actual changes as they occur.
For EPTISA internal use only – do not distribute without permission from the PMO 32
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
This chapter will be further developed in updated editions of the PM Handbook, including a
more detailed description of the relevant procedures related to project financial management
and control.
New tools are currently being designed aiming to help the Project Managers managing and
monitoring the project costs (see Appendix D – Key metrics for project monitoring and control
and Template T8 – Cost Structure Table). Nevertheless, at this point of time, such new tools
have not yet been fully implemented and therefore will be further explained and developed in
a next edition of the Handbook.
The payment to EPTISA of the invoice and of the fees and expenditure claimed is conditional
on the factual findings of the EVR.
The following table resumes the documents and the information required to develop the EVR
as well as the persons/authorities responsible for providing such information.
For EPTISA internal use only – do not distribute without permission from the PMO 33
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Nº Document Responsible
6 Table with Experts’ fees and inputs distribution per month Project Director
The Project Manager must understand the requisites for the preparation of the EVR,
ensuring from the early project beginning that all information is available and duly
classified, decreasing the administrative time required for the preparation of the reports
and for invoicing the client.
For EPTISA internal use only – do not distribute without permission from the PMO 34
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
As first part of the action, it is necessary to have clearly under control all information of the
project related to contract, scope, parties involved and their responsibilities.
After this, the Eptisa Integrated Quality Management System (QMS) will be the main tool to
accomplish all aspects necessary to get a quality job.
The main person responsible for this assurance of Quality is the Project Manager, but all
the aims and objectives of a quality job must involve all employees and all workforce of
the project from the highest direction levels to all staff.
The essentials of the Eptisa QMS are widely explained in several procedures that Quality
Department has developed along the years, and they are focused to help to accomplish all
quality aspects that an UNE-EN-ISO 9001 certified enterprise like Eptisa needs in all its projects,
these aspects together with the particular specifications of the client will be assured by the
following procedures:
EPT-PG-016_ Quality Plans: This document states a method to deliver a quality project and
linked to all significant tasks involved in the project. Quality Plan is the key document of the
Quality System but needs to be particularized for project and shows how to control and assure
that Project is performing according to the requirements.
First revision of the Quality Plan is done before the start of work, but is a live document and is
updated frequently during the project.
Quality Plan has a standard structure that could be adapted to specific requirements of the
project if necessary. The expected index is shown below:
For EPTISA internal use only – do not distribute without permission from the PMO 35
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The most important part of this procedure is widely developed in the following procedure EPT-
PG-02 _Design Control, where it is shown how to plan, review, verify and control the changes
of all design activities in order to meet the clients’ requirements, regulations and our own
specifications.
Records: Lists of baseline data. Proceedings of planning. Design reviews. Checklists. Change
Orders.
Other procedures affect to quality of the project in a similar way and its scope is explained in
the following documents:
EPT-PG-01_Contracts Revision: It states the way Eptisa has to make offers and contracts with
clients, to ensure that the requirements of the clients are clearly understood and that we have
the full capacity to satisfy them.
EPT-PG-04 _ Acquisitions and contracting: It sets the actions to take in order to get products
and services that comply with the specified requirements.
For EPTISA internal use only – do not distribute without permission from the PMO 36
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Records: Work Certificates Satisfaction Questionnaires. General info about client satisfaction.
EPT-PG-10 _Non Conformities Control: It states the way to act when a deviation from an
expected result (Non Conformity) is detected on any of the activities affected by the Quality
System during the life of the project. The objective is to avoid a submission to client of a Non
Conforming product.
EPT-PG-11_Preventive and Corrective Actions: It sets the procedure to do to avoid the causes
that create Non conformity both real and potential, using with efficiency the corrective or
preventive actions.
EPT-PG-12 _Records Control It shows documents that are used as Quality System records and
the way to control them.
EPT-PG-15 _Claims: It states the way to act once a client claim is received.
EPT-PG-18 _Legal Requirements: It describes the way to identify and to know legal mandatory
requirements in the Project, including aspects such as environmental regulations, and policies
of Eptisa, showing moreover the way to comply with them.
EPT-PG-19 _Internal and external communication It shows how Eptisa has to establish
communications, both internal and external necessary to control the development of the
Project and its quality aspects.
These are the main procedures that directly affect the projects but Eptisa QMS has a very wide
scope reaching all aspects of the company, some of the most useful are:
EPT-PG-13 _Internal Audits: It describes how to plan, develop and monitor the internal audits
to check its efficiency, verifying systematically that all quality activities comply with the
established method.
For EPTISA internal use only – do not distribute without permission from the PMO 37
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
EPT-PG-14 _Training: It sets the method to assure and register the necessary competencies
training of the employees involved in the project.
Records: Records of training sessions, CV, Training needs, Certificates of staff education.
In the pursuit of a quality project, opinions and suggestions of involved employees can
help to achieve a high value improvement of the project quality.
As any major Management System, several procedures, templates and guidelines are
necessary to perform a good quality project and Project Managers always can rely on the
Quality Department of Eptisa to solve any issue and respond to all clarification requirements.
Full version of the related documents and templates, are available on the intranet,
(Spanish and English versions) for all departments of Eptisa and they are managed by the
Responsible of the Quality Department.
For EPTISA internal use only – do not distribute without permission from the PMO 38
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
a) Organizational Plan:
This is the process to identify and document the roles and responsibilities in the project, the
skills and abilities required, the way of communication and to define a Human Resources Plan.
The Project Manager is responsible for defining the roles and providing the information on
what resources will be needed to complete the work on each of the activities within the
project. Every member of the Project Team is responsible for knowing his role and associated
responsibilities and level of authority (who designates resources, make decisions, sign
approvals, etc.).
An effective Organizational Plan has to take into account the availability and competence of
the team members, that can belong to Eptisa or not, the needs of the same resources in other
projects, etc. A bad plan can affect other important areas of the project like the quality, cost,
deliveries calendar, etc.
This is the process to obtain the necessary team to develop every one according to the tasks
and specialties of the project.
Although the Project Manager cannot be involved, he should follow the process in order to
negotiate and influence on the people in charge of this recruitment, because not get the
adequate team, with the desired proficiency, could impact the success of the project.
When Eptisa cannot provide internal resources to develop the services, they will have to
obtain services from freelancers, subcontractors, etc.
For EPTISA internal use only – do not distribute without permission from the PMO 39
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The acquisition process must be carried out according to the Corporate Recruitment Rules of
Eptisa, and the selection criteria must be based on the availability, cost, experience,
competence, knowledge, skills, aptitude, international factors, etc., depending on the needs
within the project.
The result of this selection must be a Project Team with at least one resource assigned to each
role, and where each member (internal or external) have the right level of skill knowledge and
experience to perform the work within a given time frame.
Once the Project Team has been made up, it is important that the Project Manager reviews
and clarifies tasks and responsibilities with every member of the team, to make sure they
know their roles and they have the required knowledge and skills to carry out the work.
This is the process to improve the competencies, the team interaction and relationship, with
the aim of getting a better performance and development of the project.
The Project Manager must manage the resources, assess and improve the project team,
working on that early within the project, iteratively and interactively with other aspects of
planning such as time, cost and scope. To achieve success on that, good interpersonal and
people skills are keys for Project Managers.
It is well-known that the members of a team perform much better than just a group of
individuals, but nevertheless the individual development (technical and managerial) is the
basis of the team development. Development as a team is critical to the project´s ability to
meet its objectives: If the staff to be assigned is not expected to have competencies needed by
the project, those competencies will need to be developed as part of the project.
Eptisa Human Resources Department is developing several tools and techniques to assess the
employee performance, with the aim to establish a systematic way of evaluation, providing
constructive feedback and enabling Eptisa professionals to continually improve their
performances.
This process implies to follow the performance of the team, tracking the work carried out and
solving potential problems, managing changes, etc. to make sure that the team members
perform exactly according to the Project Management Plan.
This is probably one of the most complex areas as people can be unpredictable, can give rise to
an unexpected conflict, the level of their morale can go up or down, and also of course for
either personal or professional reasons, some may leave the project in an unplanned manner,
affecting on the project objectives such as the schedule, the budget, quality, etc.
For that, via this process, the Project Manager must keep the team working at their optimal
performance levels and must regularly assess the performance of the team, so that in case
there are any performance issues these can be acted on swiftly and managed so that the issue
is resolved.
For EPTISA internal use only – do not distribute without permission from the PMO 40
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
There are three important skills for Project Managers in this process: leadership to establish
direction to the team, motivating and inspiring them, influencing skills as persuasion, listening,
and building trusting relationships, and effective decision-making based on the knowledge of
the goals and objectives to get in every stage of the project.
Project Managers must communicate to the team a clear vision of what must be accomplished
and how the team needs to contribute to achieve it, while the team members must trust that
the Project Managers have the appropriate leadership skills and abilities to make the project a
success, and also to have trust that they will empower them to perform as well as offering
support when and where needed.
Different techniques and tools can be used to manage the team, as observation and
conversation, performance appraisals to provide the staff with feedback on how they are
performing on their tasks, conflicts management to resolve issues that can be technical,
business, environmental or just about any aspect of the project, etc.
During the development of the project, the Progress Reports show how the objectives are
being reached against the baseline plan, using such elements as scope, time and cost, and how
effective the project team is being.
One of the consequences of this analysis or process could be the need to make changes in the
team, due to a person not having sufficient qualifications to carry out the work, is delayed on
his performance causing delays in the Project Schedule, has high hourly rates exceeding the
budget, etc. In that case actions must be taken in the form of a Change Request that can
conclude with the assignment of that person to another task, the replacement of some part of
the team, the need of subcontracting the work, etc.
For EPTISA internal use only – do not distribute without permission from the PMO 41
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
It´s well known that the activities of Eptisa are very different, for this reason the scope of work
of a project and the necessary resources to complete it are completely different depending on
the project we are executing, but the way we communicate is very similar regardless of the
kind of project we are executing.
We will use a typical organization chart to explain the previous points. (It´s a complex example,
some projects don´t require a breakdown so complicated).
For EPTISA internal use only – do not distribute without permission from the PMO 42
PROJECT
ROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
As a general rule, only employees included in green group can communicate the type A
communications. The Project Manager will decide when an employee included in orange
group can communicate the type A communications, for a specific issue.
The way the project team should communicate with the client (e-mail,
(e Skype meeting, etc)
Skype,
will be determined during kick off meeting, by project director.
As a general rule, we must communicate with our client at least once a month, to talk
about the main issues related to scope of project and the degree of progress of the
project.
The kick off meeting with our client is an essential point at the beginning of the project where
we must establish, with our client, the final scope and work plan of the project.
For EPTISA internal use only – do not distribute without permission from the PMO 43
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Internal Communications:
The project team can use different ways of communication depending on where the project
and the different members of the team project are located (videoconference, e-mail, phone
calls, meetings, etc).
The kick off meeting with project team is the most important communication tool at the
beginning of the project and will be used by Project Manager aiming to define and to inform
members of project team about the following points:
Once the kick off meeting has finished, the members of project team should communicate
between them continuously.
The frequency of communications and the detail of these communications will change
depending on the project, but as general rule, the Project Manager and the rest of
members of project team should communicate between them, at least, every week. The
Project Manager and Team Leader should fill out the Internal Progress Report, once in a
month.
For EPTISA internal use only – do not distribute without permission from the PMO 44
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The engineering risk management process involves five main components. In a project
management plan, each of these has its own significance. The components are:
Good Risk Management is proactive, not reactive and seeks to reduce the probability of
an adverse event occurring as well as the magnitude of its impact.
The project manager or engineer should develop a written risk management strategy which
includes the methods used to execute a project’s risk management plan. This should be
included as part of a larger project management plan. Adequate resources need to be
available to manage risk. The key to writing a good Engineering Risk Management Plan is to
provide the necessary information so the project team knows the objectives, goals, tools and
techniques, reporting, documentation, and communication roles and responsibilities.
For EPTISA internal use only – do not distribute without permission from the PMO 45
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Identifying Risks
Project risks should be examined to a level of detail that permits and evaluator to understand
the significance of the risk and its causes and to potentially examine the root causes. The
Sustainability Principles Checklist, as well as the use of surveys of customers, end users, and
other stakeholders could be useful inputs for the risks identification process. Some typical risk
categories include Cost, Schedule, Technical, Feasibility, Logistics, HR, Support, Contract,
Management, Political and Engineering, social and environmental impacts.
Analyzing Risks
Risk analysis is the systematic process to estimate the level of risk for identified and approved
risks. Normally, this involves the creation of a risk matrix which quantifies the probability and
consequence of the defined risks and a conversion to an overall risk level.
Qualitative Analysis
A commonly used qualitative risk analysis method involves risk scales for estimating
probability of occurrence and a risk mapping matrix. For each identified risk a probability and
a consequence is assigned, then a risk mapping matrix (see Template T4 - Risk Register) is
drawn up to categorize each risk and draw up a value for Risk Exposure.
In the Risk Management Plan (within the Project Management Plan) strategies to deal with
each risk are normally placed into four basic categories:
1. Accept: Also known as retention, the project manager or organization is willing to live
with the risk without further mitigation.
2. Avoid: The project can avoid the risk by removing whatever requirement caused it to
appear. The risk is sidestepped.
3. Mitigate: Also called mitigation, this involves recognizing the risk is there and
performing actions to minimize it, developing contingency plans in case the risk comes
to pass, or developing fall-back provisions.
4. Transfer: Sharing of the risk with another party, or outright transfer.
Within the Risk Management Plan, provisions should be in place to systematically track and
evaluate the effectiveness of the risk response actions against established metrics. Some
techniques that can be used for monitoring and controlling risk are:
Risk Metrics: Formal, periodic assessments evaluating whether the risk management plan is
achieving its intended objectives – whether the probability of risk occurrence or the impact is
reducing, thereby reducing the Risk exposure value.
For EPTISA internal use only – do not distribute without permission from the PMO 46
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Risk Management should span across the entire life cycle of a project – starting from
bidding stage, continuing during transfer from bidding to execution, during execution
and even post execution
The Risk Management process should ideally start right from the bidding stage. While
responding to a Request for Proposal it would be prudent to look at some of the possible risk
factors like technical capability, availability of right resources, financial viability, availability
of funds and any history of poor / delayed payments of the Client.
Once the project is won and while the transfer is happening from the Business Development
Team to the Project Execution Team, the project team should look into the possible risk areas
like availability of planned resources, likelihood of meeting planned margin, availability of
contingency/provisional budget, possibility to cover overheads, likelihood of meeting
schedule, additional resource requirements, if any and any possible hidden costs.
Once the project is in execution, the Project Management Team should list down and detail
the possible risks with other relevant details in the ‘Risk Register’ for all those items that may
come up during project execution. An exhaustive list of possible risk sources is provided in the
‘Risk Register’. The same has to be monitored regularly and updated either on addition of a
new risk or at least on a monthly basis. The High-category risks need to be brought to the
notice of the Project Director and there should be a clear cut list of mitigation or contingency
measures to reduce the impact or probability of the risk.
For EPTISA internal use only – do not distribute without permission from the PMO 47
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Although there is extensive literature regarding the good practices of procurement , there are
a few basic rules that should be enforced by all Project Managers, ensuring that i)
procurement processes are executed as efficiently as possible, ii) prices are optimized, iii)
processes are traceable and iv) full transparency applies at all times and there is evidence of it.
3.10.1 General procurement rules for procuring goods and services in Eptisa:
1. Clearly identify what activities must be outsourced / sub-contracted;
2. Identify the potential seller base, specifically companies or individuals with whom
Eptisa worked before. Identify how well previous sellers performed;
3. Review specific procurement rules issued by Eptisa client;
4. Send a formal “request for proposal” ensuring that the scope, requisites of the work
financial conditions and any other relevant conditions are clearly described;
5. Having received the different budgets and ensuring they are comparable, draw up a
comparative table, using the template T13. Comparative Table;
6. Per principle a minimum of three proposals should be received and compared;
7. Prepare a report explaining why the goods or services should be awarded to a specific
sub-contractor and get the approval of the project sponsor if he requires so (in case of
doubt ask him);
8. Ensure that you get the approval of your client for the service provider you intend to
award a contract. In many cases such approval or no-objection is mandatory:
9. Once the service provider has been chosen, a contract must be prepared, including all
relevant information such as the project internal reference and the relevant analytic
codes of the different concepts;
10. As the project is moving, monitor how the service provider is accomplishing the
requirements of the contract and act accordingly;
11. Once the subcontractor has finished his activity the procurement process must be
closed. Among other tasks the Project Manager must ensure that:
a. The subcontractor fully completed all his obligations;
b. There are no claims / disputes to be solved;
c. All invoices have been paid to the sub-contractor;
For EPTISA internal use only – do not distribute without permission from the PMO 48
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Identify the job description according to the Terms of Reference and client requisites;
• Review Eptisa Expert Databases to find possible matches;
• If required, publish job post in the media or address specialized recruitment agencies;
• Evaluate in detail received CVs;
• Discuss with the project team the possible scenarios and candidates, aiming to promote
acceptance of the new incorporation;
• Prepare a short list of candidates (minimum three if possible) after confirmation of their
academic and professional experience;
• Interview the candidates, evaluating in detail the competence and suitability of the
consultants. Special consideration should be given to:
o Personal attributes: ethical, observant, tenacious, etc;
o Relevant education;
o Knowledge and skills necessary to meet the overall objectives for the project;
o Ability to work in team;
o Work experience;
• Ensure agreement on economical conditions and any other terms of the assignment;
• Request the client formal approval for the incorporation of the consultant;
• Prepare the contract and deploy the consultant.
Do not deploy the Consultant to the project without ensuring i) the formal approval of
the client and ii) the formal contract between Eptisa and the Consultant.
Additionally, specific control measures should be taken by the Project Manager, to ensure as
best as possible, that the candidates fully comply with the requirements of the position. Some
of these are:
• Requests directly to the consultant accurate information regarding his availability for the
project (i.e. if the consultant is not committed for a different project; if his current working
schedule is compatible with the new schedule project, etc). Written confirmation must be
requested;
• Revise Eptisa internal databases for consultant’s availability and performance evaluation. In
addition, requests information about consultant’s availability and feedback to PM in the
country of the consultant’s latest experience;
• Requests information about the consultant to former hiring companies about his
performance in previous experiences;
• Requests information to the client or beneficiaries.
For EPTISA internal use only – do not distribute without permission from the PMO 49
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 50
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Be sure to identify as soon as possible who is responsible for the definition and approval
of the scope of the work. You will not want to be in a position where you find out that,
for example, after you deliver project products, you are meeting for the first time the
person in charge for reviewing them.
In the case of projects financed by third parties, that is, projects where the beneficiary of
project products isn’t the same as the one that finances the project, an adequate management
of stakeholders is even more critical in order to ensure that although in the beginning there is
a very diversified range of interests and expectations, as project progresses, they are all
funneled into the project´s best interest.
For EPTISA internal use only – do not distribute without permission from the PMO 51
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Studies, evaluations, audits, organization of events, trainings are usually procured as global
price contracts. Studies include a variety of tasks such as the identification and preparation of
projects, feasibility studies, economic and market studies, technical studies, drafting a legal
document, evaluations and audits, etc.
In these types of project contracts scope and project deliverables are well defined and the
payment of the service will be based on the delivery of the agreed outputs in specific moments
of time. The client may withhold totally or partially such payments if he considers that
contractual results have not been reached.
The main advantage of Fixed Price Contract is that both parties know the scope of the work,
and the total cost of the task before the work is started.
The risk is that more time and costs are often involved with the activities than were first
estimated. Setbacks can also occur because certain information is not available or is not
available when it should be. Conversely, if the work is performed efficiently, the earning
capacity can be increased. With a well defined scope of work and schedule, additional services
can be identified and compensated for, thus limiting risks.
It is utmost critical that the project scope and project deliverables are fully understood and
clarified by both the Project Manager and the Client as soon as the project starts to ensure
that there is minimum possibility of non acceptance of the deliverables and the need for
additional work, that will increase project costs and therefore reduce project gross margin.
In the case there is the need to change the scope initially agreed, such change must be
properly managed. This fundamentally means that the proposed changed must be evaluated in
terms of its impact in project main variables (time, cost, quality and resources) and that any
decision must be supported by the formal approval of the Project Sponsor.
The Project Manager must take full advantage of the inception period to clarify with the
client the project scope and project deliverables, avoiding future rework and / or
additional scope, and, as result, eroded project margin.
In the case that the fulfillment of the contract depends on sub-contracted goods and services,
appropriate contracts should be made to ensure risk transfer to the sub-contractor. This may
be done, for example, ensuring that the sub-contractor fully covers certain work blocks and
that payments are made by Eptisa only after the client pays Eptisa. Obviously, as soon as
For EPTISA internal use only – do not distribute without permission from the PMO 52
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
possible, the scope and project deliverables must be fully clarified so a proper contract can be
arranged.
In any case, within a global price contract, the project manager shouldn’t arrange fee based
contracts with sub-contractors. In such a case the project manager will be increasing the risk of
over paying the sub contractor and reducing project gross margin.
Fee-based Contracts
Fee based contracts are chosen whenever the output is unpredictable or when the workload
to achieve the specified output is impossible to quantify in advance. Therefore it is
economically more advantageous for the client to pay the services on the basis of time actually
worked.
This type of contract provides for payment based on time spent, applying stipulated rates for
different categories of experts, and out-of-pocket expenses.
Risk arising from this type of project is usually limited and more related with the lack of
management skills from the side of the consultant that for different reasons may not be able
to deliver efficiently the expected range of activities.
In these types of contracts the Project Manager must be prepared for administrative
micromanagement from the client side. The client will require extensive proof of how working
days have been spent and procedures must be in place to ensure time sheets are well
prepared with requisite details, in line with the project activities plan.
It is crucial to control the experts´ work to ensure they deliver as planned, that is, they commit
with a certain number of days to complete their activities and that they comply with such
commitment. Otherwise the Project Manager may face a situation where he doesn’t have
enough man days left to complete the job and no valid excuses to request additional man days
to the client. In this case the completion of the work would be done at the expenses of Eptisa
since the additional days required to complete project activities would not be paid by the
client.
Due to the need of significant project administrative control it is also a key factor that the
Project Manager has at his disposal an administrative team with the time and skills required to
organize all administrative issues, fundamental for ensuring project revenue and margin.
Within the several factors in control for effective project delivery (Global price contracts or Fee
based Contracts), the following ones are most critical:
For EPTISA internal use only – do not distribute without permission from the PMO 53
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Close contact with the client to ensure project progress and project difficulties are fully
understood;
• Preparation of sub-contracts with experts that minimize the possibility of the expert
not completing the agreed activities within the agreed period of time;
• Administrative team capable of dealing efficiently with all administrative tasks;
For EPTISA internal use only – do not distribute without permission from the PMO 54
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Project initiation is critical for project success and the actions taken by the Project Manager in
this initial stage will decisively influence project final gross margin. Although there are many
important issues to be led and managed as soon as the project is awarded (even before
contract signature), there are critical actions to be triggered that the Project Manager should
not forget:
For EPTISA internal use only – do not distribute without permission from the PMO 55
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Fully clarify all tax and legal issues (example: Inability to understand how to invoice
8 taxes applied to invoicing, local contracting, properly or how to contract according to
etc.). country and project requisites.
For EPTISA internal use only – do not distribute without permission from the PMO 56
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Review and validate the economical Such issues will appear later, after the expert
10 conditions agreed with individual experts is involved in the project and when the PM
and companies. has less negotiating power.
Plan the project structure and develop / Inability to understand roles and
communicate fundamental project responsibilities as well as the procedures
12
procedures (ex. experts time control, invoice that regulate the interactions between the
approval, cash disbursements control, etc.). team and other projects stakeholders.
Plan a meeting with the team and start The PM will face the client without a clear
13 planning the project (work blocks, activities, understanding of the team and the project
resources, procurement, milestones, etc.). to be implemented.
Prepare the sub-contracts with project It is not allowed that project service
17 service providers ensuring their scope of providers start to develop project activities
work is as clear as possible. without a signed contract.
Prepare consortium agreements with all It is not allowed that the project starts
18 project partners ensuring contractual terms without required agreements with
are as clear as possible. consortium partners.
For EPTISA internal use only – do not distribute without permission from the PMO 57
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
This should also be the moment to take into consideration some practical issues that if they
are not addressed properly will contribute significantly to the erosion of project gross margin.
Many of the complex issues that arise during project implementation could be mitigated if the
project manager is aware about the factors that resulted in such problems in the first place.
The following list aims to develop awareness regarding most common and expensive mistakes
to be avoided:
1. Ensure the full understanding of the project scope of work, dividing it into manageable
work blocks and activities, and that all sustainability principles have been considered in
the design of the project. In case of sub-contracting, ensure sub contracted activities
are clear to both parties and minimize the risk of additional payments;
2. Ensure you read and understand the contract: type of contract, contractual issues
(rights and obligations), scope of work (deliverables), program, change orders, price
breakdown or fee, way of payments, claims, penalties, etc., in order to know how to
proceed in case of a breach for one of the parties;
3. Review the budget considered during the offer process, ensuring that all expected
costs were included in it;
4. Do not allow service providers to start working without a formal contract4. In such
cases service providers will gain negotiable power and will decrease project manager´s
ability to negotiate adequate contractual, economical and financial terms;
5. At the beginning of the project, evaluate all the risks that could happen during the life
of it and their consequences, and review them with an adequate frequency, in order to
control them and solve them with the less possible impact (especially cost impact);
6. If you are managing a global lump-sum contract do not sub-contract project activities
on a fee basis. Such situation will increase the risk of not being able to complete the
scope within budget due to claims of additional money by service providers, claims
that in principle you can’t forward to your client;
7. Agree payment terms with sub-contractors in line with the ones of the main contract,
avoiding the need for EPTISA to finance the project;
8. Do not lose control on procurement processes for the purchase of goods and services,
especially if you delegate such processes. Always get a minimum of three proposals for
each service sub-contracted5;
9. If the client / beneficiary decides to change any project critical variables, for example
to decrease time for completion or increase scope, ensure you understand the full
impact of such scenario on project costs, quality or resources before you accept it. All
project relevant changes require the production of an Addendum (a mandatory
requirement);
4
It is mandatory that all service providers have a formal contract with Eptisa before start to performing
their work.
5
This is a mandatory requirement both for Eptisa as well as to clients such as International Funding
Institutions, in the case of incidental expenditures;
For EPTISA internal use only – do not distribute without permission from the PMO 58
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
10. Ensure to evaluate your team leader as soon as possible (especially if he is a free
lancer) and if he is not up to the task replace him immediately. An incompetent team
leader has the potential to ruin the project and cause severe financial losses;
11. Don’t allow the team leader to gain control over your client. Maintain a periodic
presence with the client and ensure all non-technical issues are led by you;
12. In the case of fee based contracts ensure you keep control on used and planned
working days. If such control doesn’t exist you may face a situation where available
working days are not enough to the full completion of project scope;
13. Formalize all relevant contractual communications with the client and avoid at all cost
that any relevant meeting or agreement is not properly registered (minute meetings);
14. In the case you use freelancers on the project team, and especially in the case of team
leaders, keep in mind that their main professional goal is to maintain their good
relations with their current and future “true” employer, that is, the IFIs that evaluate
their CVs and consider them fit or not for the job. This may generate biased behaviors
not being clear that they will work for the full benefit of EPTISA;
15. Do not let your emotions interfere in your decisions or in your relation with the team.
All your decisions should be made based on facts and after careful study of the matters
you have to decide upon;
16. Ensure that you have adequate (in quantity and quality) administrative staff to deal
with the project, especially in the case of projects that require extensive administrative
wok such as the ones financed by IFIs that incorporate relevant budgets for incidental
expenditures;
IV. Plan the project and prepare the Project Management Plan
The actions taken in the previous phase will set the bases for proper project planning. Here the
project manager must develop a set of templates that will set the course of action and register
the baseline for project monitoring and control.
As a minimum, the documentation developed during this phase should result in a
comprehensive Project Management Plan, addressing the following:
• The detailed description of the scope of work, validated by the client (Template T3 –
Project Scope Statement);
• The definition and detailed description of the project products to be delivered (no specific
template available);
• Project team organization, including the description of roles and responsibilities of each
team member;
• The definition of the work schedule including activities, dates and resources involved. Such
document should be prepared in MS Project or in a similar format;
• The staffing plan (no specific template available);
• The risk matrix, as per the existing template (Template T4 - Risk Register);
For EPTISA internal use only – do not distribute without permission from the PMO 59
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Estimation of project costs and revenues including a cash-flow estimate if required. In this
case the attached Table of Costs should be used (Template T8 – Cost Structure Table);
• The standard set of project key performance indicators, as per the existing table (Appendix
D – Key metrics for project monitoring and control);
• The communication plan (no specific format available).
All the above documentation constitutes the project baseline and should be updated
periodically in order to ensure the complete understanding of project status by the Project
Manager and relevant Project Stakeholders.
The project documentation generated during the project life cycle, should be organized,
following the structure presented in Appendix G – Structure for classifying project information.
All relevant documentation should be available in the company network, ensuring that
backups are made and that information is available at all times.
All contractual information (main contract between Eptisa and the client as well as
contractual amendments) should be made available to the Project Management Office.
The project must be thoroughly discussed by the project manager with the project team, so
that the roles and responsibilities are clearly identified and understood, the project work plan
is defined and agreed and all relevant issues that may impact the project are discussed. During
this stage the content of the kick-off meeting presentation must be discussed and
responsibilities must be assigned regarding who is responsible for what content.
Having prepared the kick-off meeting contents with the project team the second step should
be discussing with the client or project beneficiary its expectations regarding the presentation,
ensuring that the produced contents are per client requisites and the meeting is properly
organized and all resources (room, projectors, entrance permits, etc.) are available.
For EPTISA internal use only – do not distribute without permission from the PMO 60
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 61
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Such information should be uploaded to the Project Register and to the Operations Portal
whenever possible or sent directly to the PMO.
The following list of activities must be performed to ensure an appropriate project closure:
• Project products delivered with a certificate of acceptance by the client;
• Full project amount collected;
• Pending cost receipts classified and sent to the financial department for processing ;
• Payments to service providers completed;
• Bank guarantees collected from client and delivered to the corporate financial
department;
• Contracts and amendments with main client signed;
• Claims with main client and service providers settled;
• Any assets belonging to the client returned to the client (with certificate of
acceptance);
• Client satisfaction inquiry results issued to all internal relevant stakeholders;
• Project certificate of completion issued by the client / beneficiary;
• Final internal project report issued to all relevant internal stakeholders;
• Lessons learnt case prepared and issued to all relevant stakeholders;
• Project documentation classified and archived in appropriate systems;
• Information regarding project team performance updated in applicable systems;
For EPTISA internal use only – do not distribute without permission from the PMO 62
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
CHAPTER VI - APPENDIXES
For EPTISA internal use only – do not distribute without permission from the PMO 63
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
To plan, direct and coordinate activities in all phases and processes of the designated project, to ensure that
GENERAL goals or objectives of the project are accomplished on time, within the budget, ensuring that the client´s
ROLEPM (*) requirement are met
(*) See section 1.4 EPTISA Project Manager Profile. Table – Job Level of Project Managers and
their distribution of responsibilities
For EPTISA internal use only – do not distribute without permission from the PMO 64
Appendix B – Project management Office Responsibilities and Organization
• Maintain an updated list of • Definition and mapping of • Provide Functional • Ensure availability and
PM staff; PM Processes; Support to PM regarding classification of project
• Provide information to • Update of the PM IT Systems: products;
project directors and other Handbook; - Project Register; • Evaluation of Project
PM staff: • Evaluation of the PM - Operations Portal; Managers;
- Project Financial function (questionnaire - Knowledge • Follow-up of project
Information preparation, analysis of Management System; periodical reviews (ex.
- Project Audits Information results, definition of action • Report and follow-up with update of KPIs / Project
- Projects References and plan); IT Department the Progress Reports);
Certificates • Develop project internal correction of systems • Evaluation of client
- Invoice / Payments project assessments and errors; satisfaction (development
Information audits; • Definition of requisites for of questionnaires and
- PM processes • Ensure fulfillment of all PM systems development; analysis of results);
- PM templates and requirements of project • Manage with IT • Keeping an up-to-date
documents closure; implementation of new register of projects
- Quality and Safety • Capture project functionalities; underway;
- Roles and responsibilities management best practices
within the company with and lessons learned
impact on PM • Keeping an up-to-date
• Project cost drivers and projects repositories /
unitary costs assets;
• Organize training sessions;
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
PMO General
Coordination
For EPTISA internal use only – do not distribute without permission from the PMO 66
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Contractual Support
Rafael Durán rduran@eptisa.com
(contract with providers and clients)
Administrative Support
Olga Polukhina opolukhina@eptisa.com
(including payments to service providers)
For EPTISA internal use only – do not distribute without permission from the PMO 67
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
TABLE OF KPIs
1 2 3
B Labour cost Currency Total labour cost used to date Values stored in Navision All
Gross Sales
E #¡DIV/0! #¡DIV/0! #¡DIV/0! % Generated gross sales margin as % Automatic Calculation ((A-D)/A)x100 All
margin (%)
Gross Costs
F #¡DIV/0! #¡DIV/0! #¡DIV/0! % Generated gross cost margin as % Automatic Calculation ((A-D)/D)x100 All
margin (%)
For EPTISA internal use only – do not distribute without permission from the PMO 68
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Pending
H 0,00 Currency Production that we haven´t executed yet Automatic Calculation (A1-A2) All
Production
I Total Invoicing Currency Total value invoiced to date Values stored in Navision All
Over Planned Cost Over Planned Cost Manual. It must be filled out by PD, taking Over Planned Cost
Project Status - Quality evaluation of project costs to date
M On Planned Cost On Planned Cost Text account items D, I, J and his own knowledge On Planned Cost All
Costs regarding cost baseline
Under Planned Cost Under Planned Cost about the progress of the project Under Planned Cost
Ahead of Schedule Ahead of Schedule Manual. It must be filled out by PD, taking Ahead of Schedule
Project Status - Quality evaluation of project time to date
N On Schedule On Schedule Text account items H, L and his own knowledge On Schedule All
Time regarding time baseline
Behind Schedule Behind Schedule about the progress of the project Behind Schedule
Available days Number of days available for scope Contracted days - Used
P Working days Manual. It must be filled out by PD. Fee based
(per profile) completion per technical profile days
For EPTISA internal use only – do not distribute without permission from the PMO 69
Appendix E – Corporate Information Systems Used in Project Management
Manag
There are currently available at Eptisa two
t main systems that provide information regarding
project implementation and therefore are used by Project Managers, as well as other internal
project stakeholders.
i. Operations Portal
ii. Project Register
All the above are corporative systems, supported by a technological platform developed and
maintained by Eptisa, aiming
iming to register project data and to produce accurate and timely
project information for the benefit of all Eptisa project stakeholders.
Between the several entities within Eptisa that benefit from the existence of such systems and
make their management decisions
ecisions based on the information provided by the systems we can
highlight, for example, the project sponsor, the heads of the project departments, the heads of
divisions, the heads of territories, the financial department, etc.
https://eptinet.eptisa.com/ingenieria/areaInternacional/opmgnt/default.aspx
The Operations Portal is a web based platform that aggregates all contents that may be
required by Project Managers when implementing their projects.
There are several functionalities available, from which the most relevant are:
PROJECT
ROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The functional support to the project managers and the project management staff is provided
by the Project Management Office.
https://eptinet.eptisa.com/apps/alta_proyecto_EPI/Default.aspx?LANG=en
The Project Register aims to classify and register all relevant project data, allowing Eptisa staff
to quickly access the information without the need to request it to the Project Manager.
The Project Register also aims to ensure the formal authorization, from the Project Sponsor, to
start the project and to assign all required human, technical and financial
financial resources. The
Project Manager is responsible to keep the system up to date during project progress.
The system can be accessed through the Operations Portal, both for the project opening as
well as to future consulting and updating.
For EPTISA internal use only – do not distribute without permission from the PMO 71
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
This table has been elaborated to help the employees during the costs estimation. While we
are drawing up the bid, we have to consult the items of this table and we have to include all of
them that would be necessary to complete the scope of work.
As you can see, each item is linked to a code. In this way, everyone can draw up the bid using
their own files, but, once we have finished the quotation, we have to fill out the summary
sheet where we will include the total costs of each code.
This summary sheet will be used by Project Director to open a new “P” and will be used by
sponsor to validate the bid and to approve the new “P”.
Note 1: Table of costs, is a general table, drawn up thinking about the different and
multiple activities of EPTISA. You won´t probably need an important number of these items
when you are calculating a bid, but it´s essential to check this table each time you are
estimating a bid, because if you do it you won´t forget any cost necessary to complete the
scope of work.
Note 2: When you are drawing up a bid for a project located abroad, you have many ways
to obtain the information you need: looking up on the internet or asking your workmates.
Don´t forget there are many departments can help you to answer different questions
(Human Resources Department, Legal Department, and Financial Department).
Moreover, if Eptisa has a branch in that country, your workmates can give you important
information.
Note 3: Be careful if you are estimating a bid for a project placed abroad with a different
legal tender than yours, because the currency exchange may oscillate throughout the life
cycle of the Project. Therefore, you should negotiate this point with the requester or you
should add a financial cushion for this point.
For EPTISA internal use only – do not distribute without permission from the PMO 72
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
PROJECT DIRECTORS: All costs incurred in performing the different project´s tasks, will be
recorded using the same code of the table of costs for bids. Therefore, Project Directors will be
able compare every recorded cost when the new “P” was opened and costs incurred in every
phase of the project life cycle.
Note 4: When we are managing the project we must ensure that our subcontractors,
manufacturers and suppliers, send us the invoices with two references: P reference
(PXXXXXX) and analytic code (code 2200X, 2300X, etc). This step is crucial if we want to
obtain an analytic sheet without mistakes and costs incorrectly recorded in the project.
22001. External Experts: This item includes the hourly rate of external experts assigned to the
project multiplied by number of hours estimated.
22002. Subcontractors: this item includes costs of subcontractors that we need to achieve the
scope of work (e.g.: subcontracted driller machines, subcontracted specific studies,
subcontracted designs, etc).
23001. Expense Allowance: This item includes the allowance for employees. The estimated
allowance will be different depending on where the project is located. The commercial
employee has to take into account the standard of living of the country when he is estimating
the cost of this item.
23002. Hotels and meals: this item is used when the employee doesn´t receive the expense
allowance and the company pays him the costs of hotels and meals.
23003. Rental Apartment: this item will be used when there is a special agreement between
company and employee. The company pays the costs of the apartment (rent, and costs of
heating, electricity and water). Therefore the employee receives a minor allowance related to
item 23001.
23004. Taxis: this item includes costs of employees travelling by taxi. (e.g. the way from office
to airport, etc).
For EPTISA internal use only – do not distribute without permission from the PMO 73
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
23007. Flight/train tickets: While the commercial employee is drawing up the bid, it’s
important to check the average costs of tickets.
23008. Km: this item includes the travel expenses, when the employee travels by his own car.
(“with withholding tax” is a special breakdown for Basque Country´s employees).
23009. Vehicles: Costs related to purchase of vehicles. (If project´s life is very long, it´ll be
more profitable to buy cars instead of renting cars during a long period of time).
23010. Maintenance of Vehicles: If we decide to buy cars we mustn´t forget annual costs
related to maintenance (insurance and inspection costs).
23011. Visa Facilitation: costs of visa facilitation for employees who will work abroad. The
commercial employee must consult this item with Human Resources Department.
23012. Travel Insurance/medical insurance: If it´s necessary to move workers abroad, the
commercial employee has to consult this item with Human Resources Department.
23013. Other travel Expenses: This item includes all of travel expenses that are not included in
items 23001 to 23012.
24001. Materials or goods: costs related to purchase of materials, reading equipments, a new
software, 3G cards, a specific computer, etc, with the exception of costs included in items
25004, 25005 and 25006.
24002. Freight Transport Cost: This item includes costs of Seur, MRW, DHL or similar.
24003. Import/Export Costs: this item compiles all costs related to customs and taxes when
we are importing materials or equipments from other country or when we are exporting them
to another country. Some countries have high taxes, therefore, while we are drawing up the
bid we must check if it´s necessary to export / import something.
25001. Rental of Office Space: If the scope of project requires an Office in situ, we have to
estimate the cost of monthly rental. If we have no idea of the rental cost of this item and we
don´t know anyone who has knowledge about this item, we can look up on the internet the
average rental of office spaces.
25002. Costs of Office Space: All costs related to its maintenance. E.g.: monthly cost of
electricity, heating, cleaning and security (if would be necessary). Communication costs are not
included, because they are included in item 25003.
25003. Communications: costs of mobiles phones, internet and fixed line telephony services.
25004. Office Supplies and Equipments: costs related to purchasing of paper, pens,
mechanical pencils, printer cartridges, etc or costs related to purchasing or renting and
maintenance of printer photocopier or similar.
For EPTISA internal use only – do not distribute without permission from the PMO 74
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
25005. Workplace: depending on the size of your human team, you will need more or less
workplaces. As an average term, a workplace will be constituted by a desk, an office chair, a
desktop computer or a laptop and a filling cabinet. Don´t forget the furniture for the meeting
room (a table and some chairs).
25006. Printing and binding expenses: Don´t underestimate this item. If the scope of project
makes you print several color copies of a large report (A3 sheets, A4 sheets and drawings)
periodically, and you have to bind it, this cost increases easily.
26001. Financial expenses: costs of bank guarantees and similar. The commercial employee
must ask Financial Department about this cost.
26002. Assets Depreciation: Sometimes we buy equipments, machines etc, thinking about use
them during a long period of time. These equipments are assigned to a Project firstly and
when we don´t need them, we will assign them to other different Project. In this case, costs
recorded to different projects must be considered as costs of depreciation of the equipment
and not the total purchase cost. But it should also be taken into consideration whether the life
of project is very long (more than 7 or 10 years) or whether we won´t use those equipments in
others Projects, in that case, the total purchase cost of the equipment must be recorded to the
project.
26003. Other Financial costs: this item includes other financial costs not included in items
26001 and 26002. (E.g.: costs of recovering money coming from other country. This cost can be
very important depending on the country where project is located). The Commercial
employee must consult this item to Legal and Financial Departments of EPTISA.
27003. Health and Safety Plan: costs related to draw up the Health and Safety Plan. (Most of
times we won´t write it because we´ll have to accept Main Contractor´s Health and Safety
Plan).
27004. Personal Protective Equipments. (PPE): costs related to purchasing of PPE. If the
Project needs a very specific PPE (climbing equipment or similar) they will be paid by the
project, but usual PPE (safety helmet + reflective jacket+ safety boots + safety gloves and
working clothes) should be charged as an overhead cost of the Company.
27008. Productive Expenses not billable: specific item for IIC Department.
For EPTISA internal use only – do not distribute without permission from the PMO 75
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
27009. Other Taxes: this item compiles all taxes not included in previous items.
27010. Other insurances: this item compiles all insurance costs not included in previous items.
27011. Other costs: this item compiles all costs not included in previous items.
Group 28000: Incidental Expenditures (It´s a specific group for some project funded by
International Institutions)
For EPTISA internal use only – do not distribute without permission from the PMO 76
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
APENDIX – TABLE OF COSTS FOR BIDS AND ANALYTICAL CONTROL OF PROJECTS (SUMMARY SHEET)
Group for
Monthly Analytic Code DESCRIPTION COSTS (€) / Code COSTS (€) / Group
Reassessment
23002 Hotels and meals (When an employee doesn´t use the expense allowance)
Rental Apartment (When the company pays the monthly rental cost of the
23003
apartment)
23004 Taxis
23013 Other travel expenses (costs that are not included in items 23001 - 23012)
OT Communications:
-
- Mobile comunications
(25000) 25003
- Internet
- Fixed line telephony services
Office Supplies and equipments (eg: paper, pencils, pens, printer
25004
photocopier, etc)
Workplace (table, office chair, desktop computer or laptop and filing cabinet
25005
)
FC 26002
Assets Depreciation (e.g. reading equipments, machines, laptops, software,
-
vehicles, etc)
(26000)
Other Financial costs (e.g.percentage of costs for payment between
26003
different countries, etc)
For EPTISA internal use only – do not distribute without permission from the PMO 77
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
OC Transfer from P to P -
27006
(27000)
27007 Manufacturing internal costs
TOTAL COSTS
-
(€)
GROSS SALES
#¡DIV/0!
MARGIN
GROSS COSTS
#¡DIV/0!
MARGIN
For EPTISA internal use only – do not distribute without permission from the PMO 78
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
1. Contractual Documentation
1.1. TOR: Tender Rules and RFQ
1.2. Technical and economic Offer
1.3. Adjudication and contract
1.4. Modifications to contract. Formal documents where are included the
different changes from the original contract, including postponements,
temporary cancellation, etc.
2. Planning
2.1. Organization. Including Organization Chart as well as tasks and
responsibilities of Project Team. If the project team is modified, this item will
be modified too.
2.2. Schedule. It must be updated and it should be as detailed as the project
requires.
3. Communications
3.1. Inputs. All communications received related to the project.
3.2. Outputs. All communications sent related to the project.
3.3. Meeting Minutes: including meetings with our client, our subcontractors
or Project Team´s internal meetings
3.4. Contacts related to the Project. Names, phone numbers and e-mails.
For EPTISA internal use only – do not distribute without permission from the PMO 79
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
5. Quality Control
5.1. Audits
5.2. Quality Plan
5.3. Templates filled out
5.4. Procedures
6. Economic Management
6.1. Opening Estimation (template of costs for bids).
6.2. Costs Control. Excel files with monthly analytic costs.
6.3. Reassessment. Excel Files with monthly reassessed revenues and monthly
reassessed costs.
6.4. Invoices sent to the client.
8. Closure
8.1. Certificates of work finished.
8.2. Lessons learned.
At this moment this is the structure to be used for project management documentation,
although no system is still implemented, but it must be used as a way to organize information
in the same way through the whole organization. Once systems are available, documentation
should be uploaded to them in order to improve management.
For EPTISA internal use only – do not distribute without permission from the PMO 80
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Health and safety procedures are an important part of our projects and we mustn’t
underestimate them.
All activities require compliance with health and safety procedures, regardless of the type of
activity. These procedures will be less demanding if the employees work at office and they
don´t have to visit the work on site. Nevertheless if employees have to work on site or they
have to visit the work on site (because is necessary to take photos, to collect samples, etc), the
procedure is more demanding and, in case of accident, if the project wasn´t following the
health and safety regulations it could end in a tricky situation for the company, the project
leaders and other employees (Sponsor, Project Director, Head of Division, Head of Territory,
Health and Safety Coordinator, etc). In fact, in severe cases, it would involve civil and criminal
liability.
Nowadays, the H&S Department of Eptisa, is responsible to draw up the main information
related to H&S. However Eptisa is growing abroad and our technicians aren´t used to deal with
health and safety regulations of other countries, yet. For this reason is necessary to coordinate
efforts between our technicians and new health and safety coordinators who will be
contracted or subcontracted, in those countries where we don´t have knowledge about health
and safety regulations.
• Manage and update general database of Health and safety (training courses of H&S,
medical check-up, etc).
• Draw up the occupational risk prevention plans of different work centers.
• Draw up the risk assessments of different work centers.
• Draw up the prevention activities schedule of different work centers.
• Draw up the emergency measurements of different work centers.
Each territory should name/contract a health and safety coordinator or should subcontract a
company that is specialized in H&S who knows H&S regulations of the country where Eptisa is
going to work.
Those cases where the employees of Eptisa will work at office (consulting, drawing up
engineering projects, etc), the H&S procedure will be less demanding and it could be
developed by HSD.
Those cases where employees of Eptisa will work on site, continuously or intermittently, the
number of H&S documents, that it´s necessary to be filled out, will get increased, and the
complexity of these documents will be higher. For this reason, Eptisa should name/contract a
H&S coordinator or should subcontract these type of activities to a specialized company.
For EPTISA internal use only – do not distribute without permission from the PMO 81
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
• Health and Safety Plan or Risk Assessment or Adhesion to Client´s H&S Plan (It depends
on the type of work we are going to do);
• Template signed by the employee, where he declares he has received H&S plan and he
knows the risks related to his work;
• Certificates related to training courses that have been received by employees assigned
to the project;
• Template signed by each employee assigned to the project, where he declares he has
received his personal protective equipments (PPE´s);
• Medical Review Pass for each employee assigned to the project;
• Template signed by the employee where the worker is assigned as “Preventive Resource
on Construction Site” (this responsibility is a legal duty in Spain but it does not occur
other countries);
• Specific Diploma related to Health and Safety. (Those cases where it is necessary to have
a specific certificate beyond the certificates related to general training courses);
• Act of approval related to H&S Plan;
• Written notification related to Work Center opening;
• Subcontracting book;
• Authorization for construction machinery handling (It depends on the type of work).
Note 1: It´s important to keep in mind we will always need a health and safety procedure.
Depending on our activity or type of work, this procedure will be less or more demanding
and it will be solved by H&SD of Eptisa or by a H&SC or a subcontracted company,
respectively.
Note 2: If a project is being developed and anomalies related to Health and Safety are
detected, the Project Manager will have the authority to disrupt the project until those
anomalies are solved, regardless of the opinion of Head of Division/Territory or Sponsor.
For EPTISA internal use only – do not distribute without permission from the PMO 82
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
If H&SD or H&SC has to draw up the H&S Plan or Risk Assessment they will need minimum
information and it will be will be notified by PM as follows:
1. Project name
2. Client name
3. Where the project is going to be performed.
4. Detailed description related to works.
5. Description about human and materials resources.
6. Number of workers and their roles.
7. Budget and deadline for implementation.
8. Any additional or complementary information requested by HSD or H&S Coordinator.
If our client has developed the H&S Plan, we will request it and our H&S technicians will review
it. Once the document has been checked, we only have to sign the Adhesion Charter to H&S
Plan and we won´t have to draw up a H&S Plan.
For EPTISA internal use only – do not distribute without permission from the PMO 83
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The list of sustainability principles, as well as the results of the survey, will take part of the
technical offer of the project to be shared by the client. The list of sustainability factors to be
assessed by the Project Manager will be gradually adapted to each of the thematic areas of
activity.
The general checklist is already available, and has been adapted to the Water Management
Area as well. In addition, a training Module has been created, explaining the steps to be
followed in order to put the checklist into practice. All the documentation is available on our
Eptinet, following this path:
This exercise is expected, not only to be a mainstay of the quality assurance process of the
project, but also an important source of information across different knowledge areas,
including project scope management and project risk management. It shouldn’t imply any
additional cost for the project.
For EPTISA internal use only – do not distribute without permission from the PMO 84
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 85
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
For EPTISA internal use only – do not distribute without permission from the PMO 86
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
The following table indicates the name of all those that have contributed to the preparation
and / or revision of the current edition of the Project Management Handbook.
The Project Management Office takes the opportunity to thank them for all the effort required
to produce this manual, and at the same time ensuring their usual and demanding professional
activities.
Handbook Coordination Committee (the following group coordinated the preparation of the
Handbook and provided concepts and contents)
Content providers (the following group has provided concepts and contents)
Emilia Linares Fortis PMO – Legal Area Eptisa Servicios de Ingeniería S.L.
María José Barranco Plaza Head of Quality Management Eptisa Servicios de Ingeniería S.L.
Maria Barberán González PMO – Financial Area Eptisa Servicios de Ingeniería S.L.
Juncal Sánchez Fernández Corporate Services – HR Area Eptisa Servicios de Ingeniería S.L.
Ignacio Hernandez
Head of Project Management Eptisa Servicios de Ingeniería S.L.
Aguirrebengoa
For EPTISA internal use only – do not distribute without permission from the PMO 87
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Branko Mikasinovic Head of Project Management Eptisa Regional Office for SEE
Eptisa Tecnologías de la
Juan Peralta Malvar Project Manager
Información
Head of Corporate
Margarita Marticorena Blanco Eptisa Servicios de Ingeniería S.L.
Development
Corporate Director – Financial
Jose Maria Pascual González Eptisa Servicios de Ingeniería S.L.
Department
For EPTISA internal use only – do not distribute without permission from the PMO 88
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
P17. Plan Quality Management – The quality management plan that this process produces
must define the quality metrics and checklists that take into account potential risks, cost
performance baseline and organizational and sustainability factors.
- On page 27 in the area of Project Scope Management at the planning stage is included
point 6. “Apply Sustainability Principles Checklist”.
- On page 28 point 3.3 Project Scope Management, the sustainability principles are
included as one of the requisites to meet project objectives.
Project risks should be examined to a level of detail that permits and evaluator to understand
the significance of the risk and its causes and to potentially examine the root causes. The
Sustainability Principles Checklist, as well as the use of surveys customers, end users, and
other stakeholders could be useful inputs for the risks identification process. Some typical risk
categories include Cost, Schedule, Technical, Feasibility, Logistics, HR, Support, Contract,
Management, Political and Engineering, social and environmental impacts.
For EPTISA internal use only – do not distribute without permission from the PMO 89
PROJECT MANAGEMENT HANDBOOK – A Guide to Eptisa Project Managers Updated Edition 14 Sep 15
Review the project scope (ToR, technical proposal and contract) and identify those
incoherencies, needs for clarification and possible service improvements based on the
Sustainability Principles Checklist that have not been solved during the negotiation of the
contract.
1. Ensure the full understanding of the project scope of work, dividing it into manageable work
blocks and activities, and that all sustainability principles have been considered in the design
of the project. In case of sub-contracting, ensure sub contracted activities are clear to both
parties and minimize the risk of additional payments;
- On page 67, the List of Contacts for Project Management Support in EPTISA is updated.
The general checklist is already available, and has been adapted to the Water Management
Area as well. In addition, a training Module has been created, explaining the steps to be
followed in order to put the checklist into practice. All the documentation is available on our
Eptinet, following this path:
For EPTISA internal use only – do not distribute without permission from the PMO 90