You are on page 1of 3

TECHNICAL HANDBOOK

PIPE LOOP OR EXPANSION JOINT?

For some applications, the choice is obvious.


3. The fluid is abrasive and flows at high velocity.
For most, however,
the decision can only be made after an 4. The available supporting structure is not adequate for
evaluation of a the size, shape or weight of a pipe loop.
variety of factors, not the least of which is the
5. A pipe loop may be impractical, as in low-pressure,
economic one. large-diameter piping.
A piping system subjected to temperature fluctuations 6. The construction schedule does not allow for the
will change in length if free to do so. If not free, it will additional work hours required to install a loop and its
exert reactive forces and moments on the equipment to supporting structure.
which it is attached. When the magnitude of such a
reaction would be unacceptable, flexibility must be For any of the following reasons, a pipe loop may be the
designed into the piping system. more appropriate choice:
Before the development of the expansion joint, flexibility 1. Directional changes are built into the pipe’s routing.
was provided by piping configurations that promoted
bending. A loop was commonly included in a long run of 2. The pocket in the pipe run that would be created by an
straight pipe. In recent years, expansion joints have often expansion joint cannot be tolerated.
been installed instead of pipe loops for a variety of
reasons. 3. An expansion joint would be impractical, as in
small-diameter, high-pressure piping.
The decision factors
4. Corrosive attack of the bellows element would be a
Both the pipe loop and the expansion joint will safely problem.
accommodate cyclic thermal movements, while retaining
pressure integrity. The choice for a particular system may 5. Expansion joints are not permitted by the applicable
be obvious because of space limitations. In many cases, code.
either will do the job with equal effectiveness and
reliability. Too often, the choice is based on personal
preference or on the “we did it that way before” principal.
The economic aspect, which should be paramount, often
is ignored.

The expansion joint most commonly installed in long


piping runs is designed so that the pressure is external
to the convolutions (Figure 1). This type of construction
makes longer axial movements possible than could
normally be accommodated with an internally pressurized
expansion joint. Inherent in this design are internal guide
rings, a full-thickness cover, self-draining convolutions
and insensitivity for flow direction. No lubrication or
packing is required. A drain connection can be installed
to remove sediment or condensate, or both.

Pipe loops have proven to be a safe and reliable way of


dealing with thermal expansion. Three typical loop
configurations are shown in Figure 2.

1. Space is inadequate for a pipe loop of sufficient


flexibility.

2. A minimum pressure drop through the line and the


absence of fluid turbulence are essential for process or
operating purposes.

2400 Longhorn Industrial Drive, New Braunfels, Texas 78130


Phone: (830)629-8080 FAX (830)629-6899 www.myej.net email: info@myej.net

Page 1
Material and labor costs

Because actual costs are always changing, factors are


presented for determining the costs of piping material
and labor in a simplified analysis. The material and labor
cost factors provided in Tables 1 and 2 are based on

nominal 8-in.-dia. standard-weight ASTM A53 Grade B


seamless pipe having a material cost of $1 O/ft [2] - i.e.,
all the other material-cost and all the labor-cost factors
listed in the tables are relative to this single cost. If the
current cost of the nominal 8-in-dia. standard-weight
ASTM A53 Grade B seamless pipe were still $10/ft, all the
cost factors in Tables 1 and 2 would be very close to
actual costs in dollars.

If, however, this 8-in.-nominal-dia. pipe were now to cost


$15/ft, for example, the current cost in dollars for material
and labor could be approximated by adding all the
applicable factors for material and labor, and multiplying
If none of these reasons apply to a particular piping this sum by 1.50. Thus, knowing the current cost of the
design, either a pipe loop or an expansion joint could be nominal 8-in.-dia. standard weight ASTM A53B seamless
selected. In such a case, the final decision should be pipe, one can quickly estimate the material and labor
based on economics. costs for pipes of other materials and sizes.

To compare the pipe loop with the expansion joint on an The following example demonstrates this approach:
economic basis, one must consider more than just the
first cost of the materials. The analysis should also The U-bend pipe loop being considered would consist of
include the cost of labor to cut, bevel, fit and weld pipe 20 ft of 12-in. standard-weight A106B pipe and four
and elbows, as well as the cost of labor to fabricate a short-radius elbows. The current cost of 8-in. standard
supporting structure. weight A53B seamless pipe is $18/ft. What would be the
approximate cost of the loop?
In addition to these first ones, any continuing annual costs
associated with loops or expansion joints must be’ Using Tables 1 and 2, the cost of the pipe loop is estimated
included. For example, the annual costs associated with as follows:
pumping a liquid, such as hot water, around a loop rather
than through an expansion joint can be significant. Each Material cost - For pipe, $19.78 x 20 ft = $395.00; for elbows,
of these cost factors is presented in a simplified manner $194.90 x 4 = $779.60. This total is $1,175.20.
to aid the engineer in preparing a simple annual cost
comparison between pipe loops and expansion joints. Labor cost- For flame-cutting PIPE TO length, $12 , 25) x
2 = $24.50; for beveling pipe ends, $9.75 x 4 = $39.00; for
butt-welding pipe to elbows, $67.00 x 4 = $268.00; for
butt-welding elbow to elbow, $67.00 x 1 = $67.00; for
radiographing girth welds, $0. This total comes to $398.50.

Page 2
Material and labor costs total $1,573.80. Multiplying this figure Combining these equations into an annual pumping cost
by 1.8 (to adjust the Table 1 factor for 8-in. A53B pipe for the formula:
present higher cost of $18/ft) gives a grand total of $2,833.

Annual cost of pumping through a loop Here, Ca = annual cost of pumping, $; W = mass flow rate,
lb/h; 0 = volumetric flow rate, gal/min; f = friction factor, a
Because the annual cost of pumping a fluid through a pipe function of Reynolds number and the character of the pipe
loop can be significant, it should be a part of an economic wall (approximate values for fully turbulent liquid flow through
comparison. This cost results from the greater horsepower smooth pipe are listed in Table3); L = equivalent length, ft
required to overcome the loop’s head loss, which would not (determined by means of the equations previously provided);
be present with the straight through construction of an u = utilization factor, % (i.e., the percentage of time that the
expansion joint. The resistance, or head loss, in a pipe loop system will be in operation during a year); c = average cost
is assumed to consist of the loss due to curvature and the of electricity, $/kWh; e = pump and motor efficiency, %
frictional loss due to length [3]. To account for the curvature (normally 70- p = density of the pumped fluid, lb/ft’; and d =
and frictional losses, a pipe loop can conveniently be pipe 1. D., in.

Sample problem - pipe loop vs. expansion joint

A decision on whether to install a pipe loop or an expansion


joint can be resolved on the basis of economics. Hot water
at 150 psig and 3000 F is to be distributed at a flow rate of
1,459,000 lb/h through nominal 12-in.-dia. standard-weight
A106B pipe. The loop would be a short radius U-bend having
a width of 12 ft (i.e., h = 12 ft). Both the pipe run and loop
would be horizontal.

An externally pressurized single-bellows expansion joint


would cost $4,200. The cost of electricity averages $0.06/
kWh. The system is expected to be in operation an average
of 16 h/d. The loop supporting structure would cost $500.
The minimum rate of return, plus taxes and insurance, is
20%. Determine the most economical approach to provide
the needed pipe-system flexibility.

As previously calculated, the piping material and labor costs


for the loop add up to $2,833. The loop support costs an
additional $500. The equivalent length of the U-bends is 2(12)
described in terms of equivalent length (L), which is calculated + 116(l) = 140 ft. Via the pumping-cost equation, the annual
as follows: cost of pumping hot water through the loop would be:
(1,459,000)1(0.013)(140)(0.67)(0.06)1 (627,300) (0.70)
For short-radius elbows of U-bend and square-bend types, L (57.3)2( 12)5, or $633/yr.
= 2h + 11 6D; of the Z-bend type, L = 2h + 174D.
The tabulation in Table 4 shows that, while on the basis of
For long-radius elbows of the U-bend and square bend types, purchase costs the expansion joint is more expensive, it is
L = 2h +74D; of the Z-bend type, L = 2h + 111D. 35% less expensive based on total annual costs.

Here, h is the height (or, if horizontal, the width) of the loop,


ft, and D is the pipe I.D., ft. These equivalent lengths are References
based on an LID ratio of 30 for short-radius elbows and 20
for long-radius elbows [3].
1 . “Design of Piping Systems,” The M. W. Kellogg Co., Wiley,
New York, 1956, p. 210.
The standard method for calculating head loss in straight 2. Weaver, R., “The Piper’s Pocket Handbook,” Gulf Publish-
pipe is by the Darcy equation: ing Co., Houston, 1979.
3. “Flow Of Fluids Through Valves, Fittings, and Pipe,” The
Crane Co., New York, 1979.
4. Crocker, S., “Piping Handbook,” ed. R. C. King, McGraw-
Horsepower requirements are calculated via: Hill, New York, 5th ed., 1978.

Page 3

You might also like