Professional Documents
Culture Documents
PROJECT IDENTIFICATION
Project Name: Celebrezze VBA Renovation and Backfill and DFAS Consolidation Project
Page 1 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
TABLE OF CONTENTS
I. PROJECT DESCRIPTION 4
A. Base Contract (Design Stage) Services 5
B. Option (Construction) Services 5
II. GENERAL REQUIREMENTS 6
A. Project Duration and Schedule Milestone 6
B. Reference Materials 6
1. Standards and Criteria Documents 6
C. Project Team and Communications 10
1. Identification of the CMc Team 10
2. Project Delivery Team 11
3. Architect/Engineering Firm (A/E) 12
4. Construction Manager as Agent (CMa) 13
5. Commissioning Agent (CxA) 13
6. Communications Plan 13
D. Personnel Security Requirements 14
E. Project Management 14
F. Base Services (Design Stage) Progress Payments 16
G. Travel 17
H. Project Delivery Requirements 17
1. Construction Excellence 17
2. Art in Architecture Program AiA 17
I. SOW Security Requirements 18
III. SCOPE OF SERVICES 18
A. Scope Base VBA Backfill (Design Stage) Services 18
(Design Stage Services are Option #2 for DFAS Consolidation)
1. Design Stages in General 18
2. Collaboration with the A/E 18
3. Meetings 19
a) Project Initiation Meeting 19
b) Progress Meetings and Presentations 19
c) Design Submission Reviews 19
d) Risk Management Workshops 20
e) Building Information Modeling (BIM) 20
f) System Selection Analysis Meetings and Mockups 20
g) Value Management 20
h) Partnering 21
4. Deliverables 21
a) Required Deliverables 21
b) Constructability Review 22
c) Cost Estimating, Reconciliation, and Proposed Alternatives
(CERPA) 22
d) Preliminary Project Schedule and Analysis 23
Page 2 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Page 3 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
I. PROJECT DESCRIPTION
This Statement of Work (SOW) is for Construction Manager as Constructor (CMc) for the VBA
Renovation and Backfill project (also referred to as VBA Backfill) of approximately 170,000
square feet (sf), and the DFAS Consolidation project of approximately 149,600 square feet
(sf), at the Anthony J. Celebrezze Federal Building.
GSA has contracted with a separate architect-engineer (A/E) firm that is responsible for
developing complete design and construction documents for this Project. In addition, GSA
has contracted with a separate Construction Management Advisor (CMa) firm with
Commissioning Agent (CxA) services to provide certain services during the design and
construction phases of this Project. A copy of the A/E and CMa/CxA statements of work
(SOW) are included as an attachment to the Appendix. GSA has also issued an additional,
separate contract to an artist under the Art-in-Architecture program (VBA Backfill project only).
The Anthony J. Celebrezze Federal Building located at 1240 East 9th Street in downtown
Cleveland was named after Cleveland’s 49th mayor, United States Secretary of Health,
Education, and Welfare and Federal appeals judge Anthony J. Celebrezze. The building was
completed in 1967 and houses multiple federal government agency offices. The building has
32 stories, rises to a height of 419 feet and has approximately 1,007,000 square feet of
space. The building is eligible for listing on the National Register of Historic Places.
The VBA Renovation and Backfill project proposes the renovation and backfill of floors 9
through 13 at the Celebrezze Federal Building. The Veterans Benefits Administration (VBA),
currently on the 9th through 13th floors, will consolidate and modernize office space on the 9th
through 12th floors. The Department of Labor - Office of Workers' Compensation Programs
and the Department of Education, currently in Cleveland area lease locations, will backfill the
VBA vacated 13th floor. Several federal tenant agencies including Armed Forces Recruiting,
Navy, Railroad Retirement Board, and the Department of Labor - Bureau of Statistics,
currently on the 9th and 12th floors, will be relocated to vacant space on other floors in the
building to provide continued long-term housing for VBA. This will allow VBA to consolidate
office space to fewer floors in the building, all of which would be on the same elevator bank.
The project also provides the opportunity to complete much needed shell upgrades and to
remove hazardous materials, including ACM fireproofing, on affected floors. The scope will
include all new ceilings, lighting, fire alarm system, ductwork, VAVboxes and controls,
modification of stairwell handrails throughout the building for Architectural Barriers Act
Accessibility Standard (ABAAS) compliance, modification of the 12th floor public toilet rooms
for ABAAS compliance, Building Standard common corridor and elevator lobby finishes,
tenant improvements, rework of fire sprinkler drops/replacement of sprinkler heads at
renovated floor areas, and combination sprinkler standpipe/riser crossover work at the 20th
and 28th floors.
The DFAS Consolidation project proposes the renovation of floors 14, 22, 24, 25, 28, and 29
at the Celebrezze Federal Building. The Defense Finance and Accounting Service (DFAS)
has recently completed renovation work on the 23rd Floor, and will use this as a model for the
proposed floors. The scope will include abatement of existing floor as needed, new carpet
Page 4 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
and paint. New systems furniture will be provided by Tenant, with coordination and wiring of
panels by CMc under this contract. The electrical and data lines are to be reused to the
greatest extent possible, with additions as needed. Limited upgrades to mechanical and
electrical distribution systems may be required. No work is anticipated to be performed to or
above the existing ceiling. Phasing will be required to work with Tenant furniture procurement
funding. One phase must be complete before the next phase begins. Refer to the four phases
as described in the DFAS documents and in this Statement of Work. .
The design for the projects will conform to the Celebrezze Federal Building Design Standards,
Facilities Standards for the Public Buildings Service P-100, and other building codes and
standards as applicable to this project. Design services which will be accomplished through a
separate contract, will be necessary for the renovations and alterations of vacant space to
meet; the functional requirements of prospective tenants, fulfill policy and regulatory criteria,
and provide state of the art workplaces that help define interior design standards for the
building. Designed solutions shall be consistent with the latest objectives of GSA, prospective
tenants, and best practices in architectural planning and design.
The space required by prospective tenants is primarily general office space including; both
open office area and private offices, ancillary and support space such as conference rooms,
break rooms and storage. Prospective VBA Renovation and Backfill project tenants include
seven federal agencies with a total renovation requirement of approximately 170,000 sf.
DFAS Consolidation project tenants include several departments within the agency, such as
administration, call center, Legal, and IT with a total renovation area of approximately 149,600
sf.
For the DFAS Consolidation project, the design stage services are to be broken out
as Option #2. Although the design stage services described apply to both VBA
Backfill and DFAS Consolidation projects, not all will apply to the DFAS
Consolidation project. Services labeled “Exclude from DFAS Consolidation” are to
be excluded from that project, but included for VBA Backfill project.
As a general matter, the CMc Contractor shall review and become familiar with the
scope of services under the A/E’s SOW contract, especially the various standards,
guidelines, policies, and documents (also see Section II.B. Reference Materials
below) required to develop the design and construction documents. This review and
familiarization is vitally important as part of the Pre-Construction Services as the
Page 5 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
primary tasks of the CMc Contractor during the Design Stage are to provide
constructability and cost estimation reviews of the A/E’s submissions (see Section
III.A). At its core, the CMc Contractor will help to ensure that the design and
construction documents will enable the Government to exercise the Guaranteed
Maximum Price (GMP) Option at a price that is at or below the GMP.
Prior to the exercise of these Options, the Government and the CMc Contractor shall
agree on the Estimated Cost of the Work (“ECW”), which when combined with the
Fee and the Construction Contingency Allowance shall not exceed the Guaranteed
Maximum Price (GMP). Upon exercise of this Option for Construction Stage
services, the CMc Contractor shall be held responsible for completing the
construction stage work in its entirety.
Page 6 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
As a general matter, the Facilities Standards for the Public Buildings Service (P-100)
represents the overarching document that governs the CMc Contractor’s performance of work.
In addition, other policies and procedures (such as those listed in Section II.Bl. Reference
Materials below) provide detailed procedures and requirements that the CMc Contractor shall
follow. The primary purpose of this Statement of Work (SoW) is to set forth services that the
CMc Contractor shall provide in addition to the services that will be outlined in final, approved
Construction Documents (drawings and specifications), which shall be completed by the
separate Architect/Engineering (A/E) firm hired as part of this project.
The CMc Contractor is directed to review the milestone data and base their proposal per
the dates indicated below:
DFAS Consolidation
Design Documents (DDs) Complete May, 2021
Page 7 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
B. Reference Materials
There are two types of Reference Materials. The first type are project-specific planning
documents and information listed in Section IV, Appendix. The second type are the
Standards and Criteria Documents, which are specifically set forth below.
● GSA, PBS P-100, Facilities Standards for the Public Buildings Service
○ http://www.gsa.gov/p100
● GSA National Business Space Assignment Policy
○ https://www.gsa.gov/cdnstatic/NBSAP_Feb_2013.pdf
● GSA Pricing Desk Guide, 4th Edition
○ https://www.gsa.gov/cdnstatic/Pricing_Desk_Guide_4th_Ed__2014.6.5_LP
OE_update_FINAL.pdf
● ePM Requirements
○ http://www.gsa.gov/epm
● General Services Administration Criteria
○ http://www.wbdg.org/ffc/gsa/criteria
● GSA, PBS P-120, Project Estimating Requirements
○ https://www.gsa.gov/cdnstatic/P_120.pdf
● Key Sustainable Products Standards
○ https://www.gsa.gov/cdnstatic/KSP_report_for_071415_%281%29.pdf
Page 8 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Page 9 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
The individual authorized to act on the behalf of the GSA in the administration of this
contract is the Contracting Officer (CO). The GSA CO may delegate certain of his or her
authorities to others who will be known as the Contracting Officer’s Representative
(COR) and if so, will notify the CMc, in writing, of the specific authorities delegated to,
and limitations placed upon, named authorized representatives. The CMc must not take
any direction, or act upon any information, from individuals other than those having the
requisite authority as confirmed by the GSA CO’s written notification.
Page 10 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
The CMc shall provide a Team Identification and Staffing plan as part of their
proposal. The Plan shall include the following sections at a minimum:
● Names of each major trade subcontractor, vendor, or supplier that the CMc
used or relied on in preparing their proposal;
● A brief description of the services provided by such company; and
● The work the company might perform on the project, if ultimately selected by
the CMc.
At a minimum, the CMc key team members shall consist of the following:
● Corporate construction executive
● Project manager
● Architectural review coordinator
● Engineering review coordinators - all disciplines
● Cost estimator(s)
● Construction superintendent
● Quality control superintendent
● Project engineer including Scheduling engineer
● Construction supervisors
● Safety program coordinator
● Industrial Hygienist
● Waste Management Coordinator
● Commissioning agent CxA Coordinator
In addition to the key team members identified above, the CMc shall provide
administrative, clerical, and technical personnel as necessary to perform the services
required under this contract.
Page 11 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
DFAS Consolidation
Page 12 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
perform their contracted services to ensure the design intent is fully realized during
the Construction Stage, and conveyed successfully into occupancy, facility
management, operation and maintenance at project completion.
6. Communications Plan
The GSA will develop, periodically update, and maintain throughout the course of the
project, a listing of the Project Delivery Team members and respective roles and
responsibilities as part of a communication plan. The CMc shall comply with GSA’s
project communication plan and refer to GSA’s CO for all requests and responses
concerning the project. The CMc shall also respond to GSA correspondence within
seven (7) calendar days.
The contractual responsibility of the CMc Contractor is to the GSA only and not to other
contractors, customer or tenant agencies, or local community interests where the project
is located. The CMc Contractor must direct all requests for information and questions
concerning the project and from customer or tenant agencies, local community interests,
inquiries from potential offerors, etc., to the GSA Project Manager (PM). Prior to meeting
or communicating with any parties other than the GSA personnel regarding the project,
the CMc must confirm all such meetings and/or communications with the GSA. The CMc
Contractor must not release any oral, written, or graphic information regarding this
project to outside sources without obtaining prior consent from the GSA.
Page 13 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
The CMc is required to provide one (1) Point of Contact (POC) that will be responsible
for the security clearance process management of their employees throughout the
duration of the contract. This CMc Contractor POC will coordinate and communicate with
the GSA appointed security clearance representative (or POC) throughout the course of
the project to ensure all applicable clearances are submitted and processed.
E. Project Management
GSA will require the CMc Contractor to utilize an Enterprise electronic Project
Management (ePM) system, which is a fully configured version of Meridian Systems’
Proliance Construction Management Software, on this project. GSA’s goal is to
implement this state-of-the-art technology to reduce administrative and overhead costs,
eliminate redundancies, and institute a collaboration tool to ensure better accountability
among all project team members. This technology will provide up-to-date information,
encourage disciplined methods for monitoring progress, ensure better communication
regarding changes, provide improved documentation, and enable PBS executives to
have real-time access to status of projects.
a) Definition
ePM is defined as an internet-based information and project communication
system that allows the entire project team to collaborate in a centralized and
secured repository. All project-specific correspondence, workflow processes, and
documentation will be stored and routed within the ePM system.
Page 14 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
c) Equipment
The ePM system is based on the Proliance software that was developed by
Meridian Systems. Users will be provided a username and password after they
have completed the HSPD-12 process (See Section IV Appendix). All
workstations require a high-bandwidth Internet connection.
d) Training
GSA will provide no cost training to familiarize team members with the ePM
system. However, GSA will not reimburse the CMc for any travel related to ePM
training.
GSA will hold several training sessions, as needed, to familiarize team members
with the system, and all appropriate CMc staff are expected to attend these
sessions or otherwise receive proper training on the system’s use. Furthermore,
all CMc team members who are actively participating on the project must have
access to the proper computer equipment and software to access and utilize the
ePM system and be trained in the proper usage of said equipment and software.
GSA will provide ePM system administration and end-user support for the
duration of the project. The ePM minimum requirements (including IT equipment)
can be found at: http://www.gsa.gov/epm.
e) Support
GSA will provide ePM system administration and end-user support for the
duration of the project. The ePM minimum requirements (including IT equipment)
can be found at: http://www.gsa.gov/epm.
Page 15 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
f) Personnel Requirements
The CMc shall be required to have an adequate number of people who can
complete the HSPD-12 background check process to have rights to log into the
ePM system.
g) Data Ownership
GSA shall retain ownership of all data entered into the system and shall
administer and distribute all information contained therein (See Section IV
Appendix for PBS SECURITY ORDER 3490.1).
The GSA COR will review the CMc’s work on a regular basis to ensure that the
Contractor is in compliance with the requirements of the contract and monitor
performance. Failure to perform services and to submit items not required by the SOW
shall result in a reduced payment until the work has been properly performed. If the work
can no longer be successfully performed, the contract amount shall be reduced by the
value of the work not completed.
All draft invoices shall be sent to the GSA CO and GSA COR. Only after the CO, or other
delegated party, grants approval of a draft invoice may the CMc submit approved
electronic invoices to the website shown below (strongly encouraged). Instructions on
registration information can be found at https://finance.ocfo.gsa.gov/ specifically, at the
following links:
Page 16 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
G. Travel
Unless otherwise indicated in the Section III. Scope of Services, the CMc shall be
responsible for travel costs to support, as needed, the requirements contained in this
SOW, including all Base Services related to design related reviews, inspections,
progress meetings, presentations, workshops, other reviews and site visits.
The CMa shall confirm collaboration of the A/E’s Lead Designer and selected
artist(s) in the development and integration of art and architectural/site designs, in
addition to verifying coordination of integral architectural and/or engineering
elements required by the artwork(s) in the construction documents.
Page 17 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Page 18 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Ideally, the A/E and its subcontractors will communicate freely with the CMc and its
trade subcontractors, and vice versa. This will ensure mutual understanding of both
the A/E's design intent and the CMc's means and methods, and thus ensure greater
certainty in pricing the construction work. It also increases the likelihood that design
errors and omissions are recognized and resolved during the design process. In
addition, this collaboration takes place during a time that does not significantly
impact the construction schedule and that can result in expedited production and
review of shop drawings once construction commences.
3. Meetings
At a minimum, the CMc shall attend all of the meetings listed in this section. For
each meeting, the CMc shall determine the appropriate mix of attendees based on
the subject matter. Unless otherwise noted, all meetings shall be held via a
web-based (teleconference) meeting platform provided by the A/E.
Page 19 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
More than one IDR or cost reconciliation meeting may be necessary for any
submission, if that submission is not satisfactorily resolved and accepted by the
GSA following the initial IDR or cost reconciliation meetings. The need for
additional meetings in order to achieve an acceptable submission in accordance
with P-100, shall not justify excusable delay.
With each deliverable from the CMc, the parties will discuss whether the Risk
Registry needs to be modified based on the then-current state of the project.
These workshops shall be held on site at the Celebrezze Federal Building in
Cleveland, OH.
Page 20 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
g) Value Management
The CMc concept has value management as one of its main objectives. The CMa
will provide a Value Engineering (VE) program expert and / or independent
professional experts in all disciplines to facilitate and participate in a VE
workshop during the Design Stage of this project. The A/E, CMa, GSA staff, and
other government and customer stakeholders will also participate in the
workshop.
The CMc shall participate and provide professional experts in all disciplines for
the one (1) day value management workshop. The session will be held
concurrent with a design submission at the end of the Design Development (DD)
phase.
h) Partnering
To most effectively accomplish this contract, the GSA will require the CMc and its
subcontractors to participate in a cohesive partnership with the Government and
its Customers and other Contractors. The CMc and its subcontractors, as
needed, shall attend three (3), one (1) day (8 hour/each) partnering sessions
during the design and construction stages of the project which will be hosted by
the GSA’s CMa Contractor. The CMc shall provide the CO with a list of the key
personnel from the CMc and its subcontractors who will participate in the
partnering sessions. The CO may, in his/her sole discretion, add or remove any
individual from the list. The CMc shall be responsible for any travel costs
associated with attending these sessions.
The first session shall be held prior to the start of the Construction Stage. The
date, time and location will be determined by GSA closer to the time of
scheduling.
The second session shall be held after the start of the Construction Stage and
will not occur sooner than a 6 month interval from the first partnering session.
The date, time and location to be determined by GSA closer to the time of
scheduling.
The third session shall be held during the Construction Stage, preferably during
the midpoint of construction and will not occur sooner than a 6 month interval
from the second partnering session. The date, time and location to be determined
by GSA closer to the time of scheduling.
4. Deliverables
The CMc will provide a written deliverable based on the A/E’s design related
submissions for each of the following design milestones:
Page 21 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Each written deliverable from the CMc is due to the CO within 14 calendar days from
the CMc Contractor’s receipt of the A/E’s design submission.
a) Required Deliverables
For each design submission from the A/E, the CMc shall provide a written report
that separately addresses each of the following topics:
● Constructability Review
● Cost Estimating, Reconciliation, and Proposed Alternatives
● Schedule Analysis
● Construction Work Phasing and Sequencing Plan
● Early Work Package Suggestions
● Risk Analysis
The CMc shall be responsible for notifying the Contracting Officer of errors,
omissions, inconsistencies, or other issues that may potentially impact the project
goals, the ECW, schedule, design quality, or project scope.
b) Constructability Review
The CMc shall review the design submissions with reasonable care and advise of
any errors, inconsistencies, inaccuracies, or incompleteness which may
negatively impact cost, schedule, or quality both within their report and via
email/in writing. The CMc shall provide recommendations on constructability;
improving life cycle costs; sustainability; LEED; systems analysis; functionality;
enhancing operational flexibility; and minimizing labor or material shortages. The
CMc shall also review the submissions for accuracy, completeness, sequencing,
and coordination.
The deliverable from the CMc shall, at a minimum; (1) be performed in the same
level and detail as set forth in the P-100, Appendix A, (2) comply with the Cost
Page 22 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Management Matrix found at Table A-1 and (3) comply with the cost-estimating
requirements for capital construction projects as set forth in the P-120.
The GSA will reconcile the CMc estimate with other estimates to ensure that the
project being designed will be constructible within the project's budget and is
consistent with the established GMP. The reconciliation will not only focus on the
total GMP, but will also take into account the major cost elements that make-up
the total GMP (e.g., structural, MEP, exterior, general conditions, etc.). Large
discrepancies or variances in the estimates (whether in whole or in part) should
be reconciled prior to exercising the GMP Option.
If the design (or its major cost elements) appears to exceed the ECW, the CMc
shall propose alternatives that will deliver the project at or below the GMP Option.
The CMc and its major trade subcontractors, vendors, or suppliers shall
participate in reconciliation meetings.
Page 23 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
1. Pre-Construction Conference
The Pre-Construction conference referenced in Specification Section 013100 will
be held at the Celebrezze Federal Building in Cleveland, OH.
2. Submittal Schedule
Prepare and submit a submittal schedule in accordance with the Division 1 of the
construction specifications for review and approval by the GSA. The submittal
schedule shall identify specifically which submittals require review by the CxA.
Ensure that all subcontractors understand, agree to, and conform to their
respective roles, responsibilities, and timeliness requirements for submittal
processing.
Refer to FAR 52.236-21, Specifications and Drawings for Construction, for further
submittal review requirements.
Page 24 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
5. Project Documentation
The CMc shall be required to update the Project Record Documents (including
the BIM) at the 30%, 60%, and 90%, at a minimum, construction complete basis
to reflect as-built conditions, field changes, scope changes, or other changes to
the design and construction documents. The CMc shall work closely with and
collaborate with the A/E and CMa during these updates. Upon the 100% project
completion, the CMc shall transfer all updated Project Record Documents to the
A/E so they can formalize and finalize all aspects. These updates will be
uploaded to ePM per Division 01, Section 017810, Project Record Documents.
7. Payment Requests
Provide an advance copy of the construction progress report to the CMa and
GSA Contracting Officer and their designated representative within seven (7)
calendar days prior to submitting the monthly payment request per specification
section 012900.
Page 25 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
The CMc shall attend and participate in three (3) CE PRs, which will be
conducted at approximately 15%, 60%, and 90% construction completion. The
final peer review is held at 90% if significant issues were cited in the previous
construction peer reviews. If no significant issues were previously cited, the final
session will be held as a project “lessons learned” session, in which case peers
do not attend. Each CE PR will be conducted in ½ day session over the course
of a two (2) consecutive day period. The review will start on the afternoon of Day
1 and continue the morning of Day 2. These reviews will be held at the project
site in Cleveland, OH. At a minimum, the CMc’s Project Executive, onsite Project
Manager and Superintendent shall attend and participate.
11. Commissioning
The CMc shall perform all functions, roles, responsibilities of the “construction
contractor” as further set forth and explained in the GSA Building Commissioning
Guide, and of the “GC”, or “contractor” as further set forth and explained in the
Commissioning specification section 019113.
1. Turnover Process
The CMc shall attend a one day pre-turnover meeting facilitated by the GSA.
Page 26 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
2. Closeout Documentation
The CMc shall verify that the room numbering list complies with the COBie
requirements set forth in the Contract Documents and matches the data structure
of the computerized maintenance management system (CMMS).
The CMc shall provide approved as-built drawings and specifications for AE
development of record documents.
Page 27 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
6. Contract Closeout
The CMc shall assist the GSA in establishing a final breakdown of the total CMc
contract amount into a core and shell component and TI and security
components for each tenant (i.e. each client billing record) as per the PBS P-120
Public Building Service Cost and Schedule Management Policy and the Pricing
Desk Guide.
Page 28 of 29
CMc Design & Construction Phase September 15, 2020
Celebrezze VBA Renovation and Backfill and DFAS Consolidation Prospectus
Page 29 of 29