Things to be submitted for PUB TOP for Detention Tank:
1) As-built survey drawing endorsed by QP and Registered Surveyor
2) As-built photo report endorsed by QP 3) As-built Hydraulic Calculations endorsed by QP (joint endorsement with M&E QP if pumped discharge) 4) QP endorsed undertaking letter for maximum discharge 5) QP joint endorsement with developer for SOP undertaking letter (private projects only) 6) Evidence of briefing to Town Council with minutes and attendance list (HDB projects only) 7) Standard Operations Procedure (SOP) endorsed by QP (with “DRAFT” watermark stamp) 8) Testing and Commissioning – PTE checklist by RE/RTO with QP joint endorsement with Main Contractor 9) Standard Operations Procedure (SOP) endorsed by QP(M&E) – applicable for Tanks with pumped discharge only) 10) Testing and Commissioning – M&E pump testing certification and documents (applicable for Tanks with pumped discharge only)