Time & Action Plan: S No. Date Day Action/Activity Department Remarks
Time & Action Plan: S No. Date Day Action/Activity Department Remarks
S
Date Day Action/Activity Department Remarks
No.
1 23rd May, 2020 Saturday Performer Invoice Commercial 2 days after Master L/C
11 3rd June, 2020 Wednesday Testing of fabric & QA/QC Department Testing and approval of trims
trims and fabric if they meet the
S
Date Day Action/Activity Department Remarks
No.
quality standards
16 7th June, 2020 Sunday Bulk fabric produced Production 3 days after fabric approval
18 8th July, 2020 Wednesday Pilot production start Production 100-150 pieces
Pilot production
19 11th July, 2020 Saturday Production 2-3 days after the start date
completion
Bulk cutting
21 13th July, 2020 Monday Cutting 1 day after start date
completion
22 14th July, 2020 Tuesday Bulk stitching starts Stitching The day after cutting starts
Bulk stitching
23 16th July, 2020 Thursday Stitching 2 days after start date
completion
24 15th July, 2020 Wednesday Bulk finishing starts Finishing 1 day after stitching starts
25 18th July, 2020 Saturday Bulk finishing Finishing 1 days after stitching
S
Date Day Action/Activity Department Remarks
No.
completion completion
Booking of shipping
28 19th July, 2020 Sunday Commercial Not that relevant
vessel
29 25th July, 2020 Saturday Final Inspection Buyer Before shipping approval