SECTION – A
SECTION – B
b) Compare and contrast issues involved in vehicle routing in the following applications:
i. Employee pick-up for a software service company"
ii. Product delivery to retailers by a soft drink company (the van is also expected to pick-up the empty
glass bottles)"
c) Describe why you think the sales of the following products are predictable or unpredictable:
i. A music CD of a new artist
ii. Light bulbs
Discuss what supply channel characteristics should be for each product in terms of production processes,
transportation services, inventory levels, order processing and vendor responsiveness.
One of the major components namely "starter switch" is always the problem" Since the EDPL does not observe
any systematic Inventory control methods in their purchasing activities, they just order the quantity as and when
the demand arises. As this product is not available off the shelf, many a times delays occur in arranging for
assembled dashboards to MSIL. This in turn results into a financial loss to EDPL due to penalties imposed by
MSIL as per the agreements towards delays in supply of dashboard assembly.
The information gathered from EDPL shows that annual demand of the item, starter switch is 5000 nos. The unit
price of the item is Rs. 50 each. The inventory carrying cost and ordering cost is 20% and, Rs.40 per order
respectively.
Questions:
1. Explain the role of fourth party logistics in the above case.
2. How EDPL can avoid financial penalties imposed by MSIL?
3. Calculate Economic Order (EOQ) for the item under reference, by using the available information.
*********