Following tools shall be arranged before start of the Chasing Work on Block Wall for PVC Conduits.
Necessary measures will be taken for the safety of the equipment and any other works affected by the
works subject of this document.
Mason Trowel
Wheel Barrow
Plumb
Joint Filler
Mortar mixer
Mechanical Cutter
Chisel
Hammer
Plaster mesh
Dust Mask / Respirator
Relevant entities which might require protection include any such works in the vicinity of the area of
work or on the service access or discharge path.
The construction team will ensure that any such requirements are documented. Protection of adjacent
equipment’s or assets should be done to protect them from any dust or debris.
Workers must wear necessary safety gear in order to prevent any injury from use of tools and from the
dust generated during cutting/chasing process.
Chase cut-outs should always be vertical or horizontal between start and finish on the wall – never cut a
chase at an angle between these two, nor step the channel.
Vertical chases should be no deeper than one third of the wall thickness
Horizontal chases should be no deeper than one sixth of the wall thickness
Chases on opposite sides of a wall should not be in line, i.e. ‘back to back’
Location of conduits to be marked as per the approved drawings and MEP requirements.
Block wall shall be cut by grinder as per the marking and required depth to be attained by chisel with
hammer.
After finishing the cutting on block wall, more chipped hollow blocks area shall be refilled by mortar
prior to fix the conduits.
After the installation of conduits, the remained area shall be filled by cement mortar.
Plaster mesh shall be fixed in vertical direction for avoiding the cracks.
Plaster mesh shall be covered by cement mortar prior to start Rush coat/plastering.
The work area shall be maintained neat and tidy as reasonable practical at all times.