Professional Documents
Culture Documents
1.0 SCOPE/PURPOSE
This procedure covers the methodology to be followed for carrying out plastering in line with the
2.0 REFERENCES
mortar
3.0 RESPONSIBILITY
The site manager will provide inputs to the project execution plan to ensure that
lifting strategies & philosophy are addressed. And is responsible for the overall
management of the project construction team to ensure that safe and effective
Shall report to Site Manager, Shall be responsible for planning, execution and
3.5 QC ENGINEER
Shall report to site Engineer
Shall be responsible for attending all Inspection Stages as required by
Inspection test Plan.
Shall be responsible of performing all checks and shall prepare necessary
Inspection Reports.
4.0 MATERIALS
Cement
Sand
Water
Chicken mesh
Waterproofing compound.
Ensure the workers use safety appliances like safety belts in height,
helmets, safety goggles while carrying out chipping etc while carrying out
Ensure the working area is kept clean for easy access and protect edges of
Note: Furthermore the safety matters shall comply to Health and Safety Plan
6.0 EQUIPMENTS
Corner trowels
Spirit level
Scraper
Claw hammer
Float
Nail
Grinder for block cutting
Scaffolding platform
Electric drills
Trowels and hand tools
Spade
Wheel barrow
3m long aluminum straight edge
Mason square
Measuring tape
8.0 IMPLEMENTATION/PROCEDURE
walls)
Complete all pipelines works to their final positions and levels for
conduits, TV Antenna lines & piping work for other services if any
Surface Preparation:
Chipping and clearing the debris in areas of skirting and dado after
hammer or with a chisel and hammer and then wash it thoroughly with
water. This will roughen up the concrete surfaces and ensure a good
Note: Form work for concrete meant to receive plaster, should preferably not
be given any oil coating, as these are likely to remain on the concrete,
interfering with bonding of the plaster. Care must be taken to remove the oil
The surface should be hard, rough and clean. The joints should be
rough the surface with pick or a similar tool, if the surface of stone in
Fix in position button marks at a spacing not more than one length of
the straight edge (viz 1.2m or 1.5m as the case may be for the entire
more, do carry out the making up coat well in advance and scratch the
curing.
The sand has to be washed to remove impurities like mud, if required, and
In case wet sand is to be used, check for quantity of water in mortar and
Mix mortar in a number of batches, a batch being the quantity (or volume
Add water to the dry mix of sand and binder (not other wise).
If specified in the contract, do add the admixture to the mixed mortar and
Plastering:
1) Wet the surface to receive plaster one hour before, so that while starting
3) Plastering shall be started from the top and worked downwards to the floor
4) Throw the mortar for an area coverable by the straight edge, both
8) While proceeding with the work, do float and finish the joints in I stage
9) Intermittently do check the surface for plumb, line and level and make up
all deficiencies.
10) Provide 15 mm thick single coat plaster in internal and external surfaces of
Check thoroughly before and immediately after plastering, the line and levels.
Check thoroughly before and immediately after plastering, the surface areas for
unevenness, surface blemishes etc so that all rectification (if required) can be
carried out with in the final setting time, with out much additional costs.
Clean the floor area where plastering is to be taken up, to ensure plastering
Restrict the access to area where plastering is complete (This will ensure better
Finish the plaster touch up works near the skirting, after skirting and dado
Ensure all touch ups are done neatly after pre-cast slabs are embedded in
position, working platforms are inserted in position, and sanitary fixtures are
While stopping the work for the day, do ensure the surface end line is cut
inclined at 45 degrees or 60 degrees. When starting the work next day, join the
new plastering and old plastering with neat workmanship (so that the joint is
Round the edges than to keep sharp 90 degree edges (pencil round namely a
small curvature of less than 5mm radius). Similarly at the junction of ceiling to
Do not allow mortar mixing on unclean area, with out a platform and in large quantities.
Do not allow of free sprinkling of dry cement in the mortar or on the surface being
plastered, as this may cause uneven shrinkage and lead to development of shrinkage
cracks.
Do not mix different bands of cement in same room / same area as this will show colour
difference (till plastered surface are covered with some other finish).
Do not allow any breaking or chipping open the plastered areas, for laying pipes etc once
plastering is completed