You are on page 1of 27

METHOD OF WORK

ERECTION OF ARCH BRIDGE


JEMBATAN KEMBAR SAMARINDA

SUNYOTO

1
PROJECT : OWNER :
JALAN DAN JEMBATAN PU BINAMARGA

SCOPE OF WORK :
LOCATION : *) ENGINEERING SERVICE,
KALIMANTAN SELATAN PROVINCE ERECTION,
( Steel Structure System )
CONTRACTOR :
QUANTITY OF WORK :
- *) 1 SAP
PREPARED :
*) PT. BANGUN INTI GLOBAL SIZE OF MODUL :
SEE DRAWING

2
STAGE : 0 Preparation and Erection of CL Bridge

3
STAGE : 1 Erection of CL Bridge

4
STAGE : 2 Erection Side Spand 1st of CL Bridge

5
STAGE : 3 Erection Main Spand 1st of CL Bridge

6
STAGE : 4 Erection Side Spand 2nd of CL Bridge

7
STAGE : 5 Erection Main Spand 2nd of CL Bridge

8
STAGE : 6 Erection Side Spand 3rd of CL Bridge

9
STAGE : 6 Erection Main Spand 3rd of CL Bridge
 Erection Main Spand 3rd of CL Bridge,
 Erection Temporary Support & Temporary Structure,

10
STAGE : 8 Erection Side Spand 4nd of CL Bridge

11
STAGE : 9 Erection Side Spand 5nd of CL Bridge

12
STAGE : 10 Erection Side Spand 6nd of CL Bridge
 Erection Side Spand 6nd,
 Erection Main Spand 5nd of CL Bridge,

13
STAGE : 11 Erection Main Spand 6nd of CL Bridge

14
STAGE : 12 Erection Main Spand 7nd of CL Bridge

15
STAGE : 13 Erection Main Spand 8nd of CL Bridge

16
STAGE : 14 Erection Maind Span 9nd of CL Bridge, Temporary Structure

17
STAGE : 15 Erection Main Spand 10nd of CL Bridge

18
STAGE : 16 Erection Main Spand 11nd of CL Bridge

19
STAGE : 17 Erection Main Spand 12nd of CL Bridge

20
STAGE : 18 Erection Main Spand 13nd of CL Bridge

21
STAGE : 19 Erection Closure of CL Bridge

22
STAGE : 20 Dismantling Temporary Structure & Checking Elv. of CL Bridge

23
STAGE : 21 Instalation Hanging of CL Bridge

24
STAGE : 21 Instalation Deck of CL Bridge

25
Sunyoto,
Telp. : 0813-88955450
Web. : www.globalintigroup.com
Channel : www.youtube.com/user/globalinti3
E mail : big.globalinti@gmail.com

26
BUDGETING OF WORK
ERECTION OF ARCH BRIDGE
JEMBATAN KEMBAR SAMARINDA

SUNYOTO

27