Act Dur Men ES EF LS LF TF

1-2 2 5 0 2 6 8 6
1-3 2 4 0 2 0 2 0
1-4 0 0 0 0 5 5 5
2-5 2 2 2 4 8 10 6
2-6 5 3 2 7 8 13 6
3-7 4 6 2 6 2 6 0
4-8 5 2 0 5 5 10 5
5-9 6 8 4 10 10 16 6
6-9 3 7 7 10 13 16 6
7-8 4 4 6 10 6 10 0
8-9 6 3 10 16 10 16 0

Resource Allocation Chart

Resources Priority Resources


Halt Time Available Activity MXD TF Rank Allocated
0 8M 1-2 5X2 6 III 0
1-3 4X2 0I 4M
4-8 2X5 5 II 2M
2 6M 1-2 5X2 4 II
3-7 6X4 0I 6M
5 2M 1-2 5X2 1I
6 8M 1-2 5X2 0I 5M
7-8 4X4 0 II
8 8M 2-5 2X2 6 III
2-6 3X5 6 II 3M
7-8 4X4 0I 4M
12 5M 2-5 2X2 II
8-9 3X6 I 3
13 5M 2-5 2X2 II
6-9 7X3 I
18 8M 2-5 2X2 II
6-9 7X3 I 7
21 8M 2-5 2X2 I 2
23 8M 5-9 8X6 1 8
29

Project is done in 29 days